In: Accounting
Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] Mickley Company’s plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: Direct materials $ 280 Direct labor $ 140 Required:
1. What is the total manufacturing cost assigned to Job A-500?
2. If Job A-500 consists of 60 units, what is the unit product cost for this job?
Solution
| Total manufacturing cost | $ 610.00 | 
| Unit product cost | $ 10.17 | 
Working
| Direct material | $ 280.00 | 
| Direct labor | $ 140.00 | 
| Manufacturing overhead | $ 190.00 | 
| Total manufacturing cost | $ 610.00 | 
| Divided by : Number of units in job | 60 | 
| Unit product cost | $ 10.17 | 
.
| Labor cost | $ 140.00 | 
| Labor rate per hour | $ 14.00 | 
| Total hours worked | 10 | 
| Predetermined overhead rate | $ 19.00 | 
| Overhead applied | $ 190.00 |