Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3]
Mickley Company’s plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500:
Direct materials |
$ |
280 |
Direct labor |
$ |
140 |
Required:
1. What is the total manufacturing cost assigned to Job A-500?
2. If Job A-500 consists of 60 units, what is the unit product cost for this job?
Solution
1- Total manufacturing cost | $ 610.00 |
2- Unit product cost | $ 10.17 |
Working
Direct material | $ 280.00 |
Direct labor | $ 140.00 |
Manufacturing overhead | $ 190.00 |
Total manufacturing cost | $ 610.00 |
Number of units in job | 60 |
Unit product cost | $ 10.17 |
.
Labor cost | $ 140.00 |
Labor rate per hour | $ 14.00 |
Total hours worked | 10 |
Predetermined overhead rate | $ 19.00 |
Overhead appplied | $ 190.00 |