Question

In: Accounting

When evaluating the progress of capital projects, managers should investigate both cost over runs and cost...

When evaluating the progress of capital projects, managers should investigate both cost over runs and cost under runs. Why is it important that both are investigated?

Solutions

Expert Solution

Capital projects are large projects which involves huge investments and time taken for completion of such projects is also very long.
Evaluation of such projects by their managers also become necessary as first the budget of projects is required to be made and then there is a lot of price variation in material costs, labour costs, etc due to long time period and there are a lot of cost overruns and cost underruns.

Managers should investigate both cost overruns and cost underruns as first of all cost overruns are such course which are increased from budgeted costs, such increase can be an expected increase and cost underruns are decrease in costs from the budgeted costs.

For manager it becomes important that both (overruns and underruns) costs are investigated as such investigation would help the manager to find out the current position of their capital projects.
It would also help in determining the steps to be taken to reduce the overrun costs and how to maintain underrun costs.
As overrun costs are not beneficial costs whereas underrun costs are beneficial costs.


Related Solutions

If a company applies its cost of capital to all projects, it runs the risk of...
If a company applies its cost of capital to all projects, it runs the risk of accepting some negative-NPV projects that are _____ the company’s existing projects. a. riskier than b. of lower risk c. of the same risk d. of shorter life than e. of longer life than
Consider the following two projects. The cost of capital for both projects is 15%. Project Year...
Consider the following two projects. The cost of capital for both projects is 15%. Project Year 0 1 2 3 4 5 Alpha -55,000 15,000 14,000 22,000 30,000 35,000 Gamma -80,000 40,000 30,000 25,000 25,000 20,000 Calculate the IRR for each project and determine which one is better. Calculate the NPV for each project and determine which one is better. Based on profitability index method, which project is better? Overall, which project should be accepted assuming they are mutually exclusive?...
5. (a) What criteria should managers take into account when evaluating the effectiveness of recruitment and...
5. (a) What criteria should managers take into account when evaluating the effectiveness of recruitment and selection processes and why? (b) Discuss the biases associated with unstructured interviews and suggest ways in which managers can overcome them.
What decision criteria should managers use in selecting projects when there is not enough money to...
What decision criteria should managers use in selecting projects when there is not enough money to invest in all available positive-NPV products? Provide an example
There are primary and secondary decision tools when evaluating capital expenditure projects. What are some of...
There are primary and secondary decision tools when evaluating capital expenditure projects. What are some of the considerations that a finance manager should take into account when deciding whether the firm should embark on a project and why?
Should firms reassess their cost of capital as they assess potential projects or acquisitions?
Should firms reassess their cost of capital as they assess potential projects or acquisitions?
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 9%. The first project (A) will cost $100,000 initially. The project will then return cash flows of $35,000 for 4 years. The second project (B) will cost $75,000 initially. The project will then return cash flows of $65,000 in year 1, $10,000 in year 2, and $5,000 in year 3. The third project (C) will cost $70,000 initially. The project will then return...
Information You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount...
Information You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 8%. The first project (A) will cost $200,000 initially. The project will then return cash flows of $50,000 for 5 years. The second project (B) will cost $250,000 initially. The project will then return cash flows of $115,000 for the next 2 years and $30,000 for 2 years after that. The third project (C) will cost $100,000 initially. The project will then...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 10%. The first project (A) will cost $25,000 initially. The project will then return cash flows of $8,000 for 4 years. The second project (B) will cost $40,000 initially. The project will then return cash flows of $15,000 for the next 2 years and $10,000 for 2 years after that. The third project (C) will cost $30,000 initially. The project will then return...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 10%. The first project (A) will cost $25,000 initially. The project will then return cash flows of $8,000 for 4 years. The second project (B) will cost $40,000 initially. The project will then return cash flows of $15,000 for the next 2 years and $10,000 for 2 years after that. The third project (C) will cost $30,000 initially. The project will then return...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT