Question

In: Finance

Information You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount...

Information

You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 8%.

The first project (A) will cost $200,000 initially. The project will then return cash flows of $50,000 for 5 years.

The second project (B) will cost $250,000 initially. The project will then return cash flows of $115,000 for the next 2 years and $30,000 for 2 years after that.

The third project (C) will cost $100,000 initially. The project will then return cash flows of $39,000 for 3 years.

Question 1

What is Project A's NPV?

Question 2

What is Project A's IRR?

Question 3

What is Project A's Payback Period?

Question 4

What is Project A's PI?

Question 5

What is Project B's NPV?

Question 6

What is Project B's IRR?

Question 7

What is Project B's Payback Period?

Question 8

What is Project B's PI?

Question 9

What is Project C's NPV?

Question 10

What is Project C's IRR?

Question 11

What is Project C's Payback Period?

Question 12

What is Project C's PI?

Question 13

If all three projects are INDEPENDENT, which project(s) would you ACCEPT?

A) Project A

B) Project B

C) Project C

D) Projects A and B

E) Projects A and C

F) Projects B and C

G) Projects A, B, and C

Question 14

If all three projects are MUTUALLY EXCLUSIVE, which project(s) would you ACCEPT?

A) Project A

B) Project B

C) Project C

D) Projects A and B

E) Projects A and C

F) Projects B and C

G) Projects A, B, and C

Solutions

Expert Solution

Question 1
Project A's NPV $ -364
Question 2
Project A's IRR 7.94%
Question 3
Project A's Payback Period 4 Years
Question 4
Project A's PI                   0.998
Workings:
Cash flows
Year Project A Project B Project C
0 $       -2,00,000 $ -2,50,000 $ -1,00,000
1                 50,000       1,15,000           39,000
2                 50,000       1,15,000           39,000
3                 50,000           30,000           39,000
4                 50,000           30,000
5                 50,000
Project A
At 8% At 5%
Year Cash flows Discount factor Present Value Year Cash flows Discount factor Present Value
1                 50,000           0.9259           46,296 1      50,000      0.9524        47,619
2                 50,000           0.8573           42,867 2      50,000      0.9070        45,351
3                 50,000           0.7938           39,692 3      50,000      0.8638        43,192
4                 50,000           0.7350           36,751 4      50,000      0.8227        41,135
5                 50,000           0.6806           34,029 5      50,000      0.7835        39,176
Total       1,99,636 Total    2,16,474
Less:Initial cost     -2,00,000 Less:Initial cost -2,00,000
Net Present Value               -364 Net Present Value        16,474
PI = Present value of cash inflows /Initial cost
=       1,99,636 / 2,00,000
=             0.998
IRR = 5%+(8%-5%)*(16474/(16474+364))
= 7.94%
IRR is the rate at which NPV is zero.
Payback period is the time upto which initial cost is recovered back,
Payback Period = Initial cost/Annual cash inflows
= 200000 / 50000
=               4.00

Related Solutions

You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 9%. The first project (A) will cost $100,000 initially. The project will then return cash flows of $35,000 for 4 years. The second project (B) will cost $75,000 initially. The project will then return cash flows of $65,000 in year 1, $10,000 in year 2, and $5,000 in year 3. The third project (C) will cost $70,000 initially. The project will then return...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 10%. The first project (A) will cost $25,000 initially. The project will then return cash flows of $8,000 for 4 years. The second project (B) will cost $40,000 initially. The project will then return cash flows of $15,000 for the next 2 years and $10,000 for 2 years after that. The third project (C) will cost $30,000 initially. The project will then return...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 10%. The first project (A) will cost $25,000 initially. The project will then return cash flows of $8,000 for 4 years. The second project (B) will cost $40,000 initially. The project will then return cash flows of $15,000 for the next 2 years and $10,000 for 2 years after that. The third project (C) will cost $30,000 initially. The project will then return...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate...
You will be evaluating three projects for Hasbro Toys. Hasbro's cost of capital or discount rate is 8%. The first project (A) will cost $25,000 initially. The project will then return cash flows of $10,000 for 5 years. The second project (B) will cost $50,000 initially. The project will then return cash flows of $30,000 for the next 2 years and $10,000 for 2 years after that. The third project (C) will cost $30,000 initially. The project will then return...
As director of capital budgeting, you are reviewing three potential investment projects with the following cost...
As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections. Cash Flow Project A Project B Project C Investment Cost ($400,000) ($375,000) ($400,000) Year One Cash Flow $200,000 $75,000 $50,000 Year Two Cash Flow $50,000 $75,000 $120,000 Year Three Cash Flow $75,000 $85,000 $140,000 Year Four Cash Flow $50,000 $225,000 $125,000 Year Five Cash Flow $125,000 $60,000 $125,000 1.Calculate the Internal Rate of Return (IRR) for each project. 2.Assuming your...
When evaluating the progress of capital projects, managers should investigate both cost over runs and cost...
When evaluating the progress of capital projects, managers should investigate both cost over runs and cost under runs. Why is it important that both are investigated?
1. a) You’re a marketing analyst for Hasbro Toys. You get the following data: Ad Expenditure...
1. a) You’re a marketing analyst for Hasbro Toys. You get the following data: Ad Expenditure ($100) Sales Revenue ($1,000) 1 1 2 1 3 2 4 2 5 4    Compute and interpret the sample correlation coefficient between advertising expenditure and sales revenue. b) An experiment results in one of the following sample points: E1, E2, E3, E4, or E5.     Find P(E3) if P(E1) = 2P(E3), P(E2)= 0.1, P(E4) =0 .2 and P(E5) = 0.1 c) For each...
You are given the task of calculating the cost of capital of Kingston Toys. The company...
You are given the task of calculating the cost of capital of Kingston Toys. The company faces a tax rate of 40%. The company has 100,000 common shares. You estimate that the beta of the common stock is 1.5. The equity market risk premium is estimated to be 5%, and the risk-free rate is 5%. The company has just paid a dividend of $2 per share. You expect that the dividends will grow at a rate of 15% until Year...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING NET CASH FLOWS: COST OF CAPITAL IS 12% YEAR 0 1 2 3 4 X $-2,000 $250 $380 $480 $2,000 Y $-1,800 $1,600 $600 $200 $420 Calculate Project X's DISCOUNT PAYBACK PERIOD (DPB) A. 1.57 B. 1.78 C. 3.47 D. 3.89 E. 5.22
Problem 10.35 Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is...
Problem 10.35 Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,308,961 -$1,198,212 1 257,000 344,000 2 363,000 344,000 3 425,000 344,000 4 520,000 344,000 5 761,000 344,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT