Question

In: Finance

Imagine that the net present value of a hydroelectric plant with a life of 70 years...

Imagine that the net present value of a hydroelectric plant with a life of 70 years is $23.73 million and that the net present value of a thermal electric plant with a life of 35 years is $18.77 million. Rolling the thermal plant over twice to match the life of the hydroelectric plant thus has a net present value of ($18.77 million) + ($18.77 million)/(1 + 0.05)35 = $22.17 million.

      

Now assume that at the end of the first 35 years, there will be an improved second 35-year plant. Specifically, there is a 30 percent chance that an advanced solar or nuclear alternative will be available that will increase the net benefits by a factor of three; a 60 percent chance that a major improvement in thermal technology will increase net benefits by 50 percent; and a 10 percent chance that more modest improvements in thermal technology will increase net benefits by 10 percent.

       a. Should the hydroelectric or thermal plant be built today?

       b. What is the quasi-option value of the thermal plant?

Solutions

Expert Solution

Greetings,

a) whenever we have two mutually exclusive projects ie only one has to be accepted then we should choose the project having highest NPV provided there are comparable in terms of risk, life etc. Whenever the projects have unequal lives, then we need to either find out Annualised benefit or repeat the shorter project for more than once and try it to equate it with the life of the longer project. For instance - if project A is 6 yrs long and project B is 2 years long, then B can be repeated 3 times during the life time of A. So NPV of B will be standing at t=0, 2 and 4 and hence discounting is required accordingly.

In the given case, second approach is followed ie second project can be repeated twice, hence NPV of 18.77m stand at t =0 and at t=35, hence 2nd NPV needs further discounting and final answer is 22.17m which is less than first project hence we should go with the first project today ie hydroelectric plant should be built today.

b) After completion of 35 years, first project can not be undone as it is for 70 yrs, but second one may not be repeated again if we don't find it to be worthy in future. Hence second project gives us the option of repeating it after 35 years or do not repeat it. So our decision today shall be based upon the value of that option as well which it offers.

We need to find out the weighted average NPV during second period of 35 years given the improved model or improvements in the existing model.

Ist Scenario - NPV will increase by a factor of 3. Interpreting it to be in the manner that NPV will treble is it will become 18.77*3=56.31m with 30% probability giving us 56.31*.30=16.893m

2nd scenario - NPV will increase by 50% and become 18.77*1.5=28.155m with 60% probability giving 28.155*.6=16.893m again

3rd scenario - NPV will increase by 10% ie it will become 18.77*1.1=20.647 with 10% probability giving us 2.0647m

Adding up the 3 figures NPV come to be 35.85m approx. This will be discounted 35 yrs back @5% hence PV of NPV = 35.85/1.05^35 =6.5M approx.

So total NPV of second project considering real option is 18.77+6.5=25.27m. It is more than the NPV of first plant, hence we should construct second plant after considering the value of option.

Value of option = 25.27m-22.17m =3.1m ie the value by which NOV of second plant increased.

Note- Please acknowledge that there is second interpretation of the words "increase by a factor of three" as increase by 33.33%. If this is the case then there will be changes in the scenario 1 and the wwhol answer accordingly.


Related Solutions

1. If the net present value of project A is +$70, and of project B is...
1. If the net present value of project A is +$70, and of project B is +$50, then the net present value of the combined project is: Group of answer choices +$80 +$140 None of the above +$60 +$120 +$20 2. Are there problems with using the payback rule? The following are disadvantages of using the payback rule except: Group of answer choices The payback rule does not have the value additive property The payback rule does not use the...
Net Present Value
NBA stars Kevin Durant and Chris Paul own a company that faces a 40% tax rate and uses a 14% discount rate. They just invested $677,000 in equipment for the banking app “Goalsetter” that would be depreciated on a straight-line basis to zero over the 6-year life of the project. The equipment will be salvaged for $182,000 at the end of the project. Kevin Durant and Chris Paul know that the project's operating cash flow will be $165,300 per year. What is the NPV of this project if it...
Net present Value
Company A wishes to invest in 4 projects X, W, Y & Z whose net benefits are given in the table below. Project Years   0 1 2 3 4 W (1000) 1200 0 0 0 X (1361.1) 500 500 500 500 Y (1000) 1200 1500 0 0 Z (2000) 1000 0 0 0 Using a discount rate of 10% appraise the 4 projects using the NPV criteria.
Net Present Value Method, An index computed by dividing the total present value of the net...
Net Present Value Method, An index computed by dividing the total present value of the net cash flow to be received from a proposed capital investment by the amount to be invested.Present Value Index, and Analysis for a service company Continental Railroad Company is evaluating three capital investment proposals by using the net present value method. Relevant data related to the proposals are summarized as follows: Maintenance Equipment Ramp Facilities Computer Network Amount to be invested $679,831 $436,634 $209,605 Annual...
The NPV (net present value) of Plan Alpha is $ (130,539) The NPV (net present value)...
The NPV (net present value) of Plan Alpha is $ (130,539) The NPV (net present value) of Plan Beta is $ 233,001 The IRR (internal rate of return) of Plan Alpha is $ 19.36 %. The IRR (internal rate of return) of Plan Beta is $ 21.25 %. Which​ plan, if​ any, should the company​ pursue? Based on the results​ above, the company should pursue Plan Beta because the NPV is positive and the IRR is greater than the​ company's...
Net present value Using a cost of capital of 11​%, calculate the net present value for...
Net present value Using a cost of capital of 11​%, calculate the net present value for the project shown in the following table and indicate whether it is​ acceptable, Initial investment ​(CF 0CF0​) negative 1 comma 143 comma 000−1,143,000 Year ​(t​) Cash inflows ​(CF Subscript tCFt​) 1 $81,000 2 $138,000 3 $193,000 4 $258,000 5 $311,000 6 $377,000 7 $270,000 8 $98,000 9 $45,000 10 $29,000 The net present value​ (NPV) of the project is _____​$ ​(Round to the nearest​...
Find Net Present Value.
Franklin Company is considering investing in two new vans that are expected to generate combined cash inflows of $32,000 per year. The vans’ combined purchase price is $99,000. The expected life and salvage value of each are seven years and $20,100, respectively. Franklin has an average cost of capital of 12 percent. (PV of $1 and PVA of $1) (Use appropriate factor(s) from the tables provided.)   Required Calculate the net present value of the investment opportunity. (Negative amount should be...
Net present value (NPV)The net present value (NPV) rule is considered one of the most...
Net present value (NPV)The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions.Consider this case:Suppose Pheasant Pharmaceuticals is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,225,000. The project is expected to generate the following net cash flows:YearCash FlowYear 1$275,000Year 2$475,000Year 3$450,000Year 4$450,000Pheasant Pharmaceuticals’s weighted average cost of capital is 8%, and project Beta has the same risk as the...
A plant asset with a cost of $270,000, estimated life of 5 years, and residual value...
A plant asset with a cost of $270,000, estimated life of 5 years, and residual value of $45,000, is depreciated by straight-line method. This asset is sold for $190,000 at the end of the 2nd year. a) Prepare the entry for depreciation for the year? b) Prepare the entry for the sales of the asset.
What is the net present value of receiving $250 in 5 years from now if the...
What is the net present value of receiving $250 in 5 years from now if the interest rate is 11%?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT