In: Accounting
The
NPV (net present value) of Plan Alpha is $
|
(130,539)
|
The
NPV (net present value) of Plan Beta is $
|
233,001
|
The
IRR (internal rate of return) of Plan Alpha is $
|
19.36
|
%.
|
The
IRR (internal rate of return) of Plan Beta is $
|
21.25
|
%.
|
the required rate of return
Requirement 2:
IRR is stated as the discount rate of a project which makes all the present value of cash inflow and outflow indifferent. In other word at a discount rate equals to IRR, NPV of a project is zero. If cost of capital of a company is same as that of IRR of the project then NPV of the project is zero. For higher cost of capital than IRR, NPV is negative. For a lower cost of capital than IRR of the project, NPV of the project is positive and it is acceptable. Hence based on the relation between NPV, IRR and company’s required rate of return, the answers are as expected in the above requirement 1.
The internal rate of return is the interest rate that makes the net present value of an investment zero. Thus, if an investment’s net present value is positive, the internal rate of return is higher than required rate of return and if net present value is negative, the internal rate of return is lower than required rate of return.