In: Accounting
Welch Company budgeted the following cost standards for the
current year:
Direct materials = 1.40 pounds per unit @ $1.50 per pound
Direct labor = 0.75 hours per unit @ $6 per hour
Actual production and costs were as follows:
Units produced = 2,800
Direct materials used = 4,500 lbs.
Direct materials purchased = 5,000 lbs. @ a cost of $5,850
Direct labor incurred = 2,000 hours at a cost of $13,000The labor
efficiency variance was
Question 8 options:
$600 F |
|
$400 U |
|
$4,800 F |
|
$1,000 U |
Answer $600 F
Labor efficiency variance = ( Actaul hours - standard hours ) * Standard rate per hour | ||
= ( 2,000 - 2,100 ) * 6 | ||
= $600 F |
Standard hours = Actual units * standard hour per unit | |
= 2,800 * 0.75 | |
= 2,100 hours |