Question

In: Accounting

Sunland Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...

Sunland Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows.

Cutting Department

Production Data—July

T12-Tables

Work in process units, July 1 0
Units started into production 24,200
Work in process units, July 31 3,630
Work in process percent complete 60

Cost Data—July

Work in process, July 1

$0

Materials

459,800

Labor

283,624

Overhead

125,840

   Total

$869,264

(a1).

Compute the physical units of production.

(a2)

Compute equivalent units of production for materials and for conversion costs.
(a3)

Determine the unit costs of production.
(a4)

For each plant show the assignment of costs to units transferred out and in process

b.

Produce a production cost report

Solutions

Expert Solution

Production Cost Report
Equivalent Units
Physical Conversion
Quantities Units Materials Costs
Units to be
accounted for
WIP, July 1 0 0 0
Started into 24200
production
Total Units 24200
Units accounted
for
Transferred Out 20570 20570 20570
WIP, July 31 3630 3630 2178
Total Units 24200 24200 22748
Conversion
Costs Materials Costs Total
Unit Costs
Total Costs $ 4,59,800.00 $ 4,09,464.00 $ 8,69,264.00
Equivalent Units 24200 22748
Unit Costs $            19.00 $            18.00 $             37.00
Costs to be
accounted for
WIP, July 1 $                    -  
Started into
production $ 8,69,264.00
Total $ 8,69,264.00
Costs accounted
for
Transferred Out (W.N.1) $ 7,61,090.00
WIP, July 31 (W.N. 2) $ 1,08,174.00
Total $ 8,69,264.00
W.N.1
Cost of units transferred out
Units Cost/unit Costs
Materials 20570 $   19.00 $ 3,90,830.00
Conversion 20570 $   18.00 $ 3,70,260.00
$ 7,61,090.00
W.N.2
Cost of Closing WIP
Units Cost/unit Costs
Materials 3630 $   19.00 $    68,970.00
Conversion 2178 $   18.00 $    39,204.00
$ 1,08,174.00

Related Solutions

Crane Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Crane Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department Production Data—July T12-Tables Work in process units, July 1 0 Units started into production 22,800 Work in process units, July 31 3,420 Work in process percent complete 60 Cost Data—July Work in process, July 1 $0 Materials 433,200 Labor...
Crane Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Crane Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department Production Data—July T12-Tables Work in process units, July 1 0 Units started into production 22,800 Work in process units, July 31 3,420 Work in process percent complete 60 Cost Data—July Work in process, July 1 $0 Materials 433,200 Labor...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 22,400 17,920 Work in process units, July 31 3,360 560 Work in process percent...
Crane Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Crane Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department Production Data—July T12-Tables Work in process units, July 1 0 Units started into production 22,800 Work in process units, July 31 3,420 Work in process percent complete 60 Cost Data—July Work in process, July 1 $0 Materials 433,200 Labor...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department Production Data—July T12-Tables Work in process units, July 1 0 Units started into production 20,400 Work in process units, July 31 3,060 Work in process percent complete 60 Cost Data—July Work in process, July 1 $0 Materials 387,600 Labor...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department Production Data—July T12-Tables Work in process units, July 1 0 Units started into production 21,800 Work in process units, July 31 3,270 Work in process percent complete 60 Cost Data—July Work in process, July 1 $0 Materials 414,200 Labor...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 24,600 19,680 Work in process units, July 31 3,690 615 Work in process percent...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Work in process units, July 1 0 0 Units started into production 21,600 17,280 Work in process units, July 31 3,240 540 Work in process percent...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department Production Data—July T12-Tables Work in process units, July 1 0 Units started into production 20,400 Work in process units, July 31 3,060 Work in process percent complete 60 Cost Data—July Work in process, July 1 $0 Materials 387,600 Labor...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at...
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows. Cutting Department Production Data—July T12-Tables Work in process units, July 1 0 Units started into production 21,000 Work in process units, July 31 3,150 Work in process percent complete 60 Cost Data—July Work in process, July 1 $0 Materials 399,000 Labor...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT