In: Accounting
Thakin Industries Inc. manufactures dorm furniture in separate
processes. In each process, materials are entered at the beginning,
and conversion costs are incurred uniformly. Production and cost
data for the first process in making two products in two different
manufacturing plants are as follows.
Cutting Department |
||||
Production Data—July |
Plant 1 |
Plant 2 |
||
Work in process units, July 1 | 0 | 0 | ||
Units started into production | 24,600 | 19,680 | ||
Work in process units, July 31 | 3,690 | 615 | ||
Work in process percent complete | 60 | 80 | ||
Cost Data—July |
||||
Work in process, July 1 |
$0 | $0 | ||
Materials |
467,400 | 354,240 | ||
Labor |
288,312 | 135,300 | ||
Overhead |
127,920 | 128,904 | ||
Total |
$883,632 | $618,444 |
3). For each plant
determine the unit costs of production. (Round unit
costs to 2 decimal places, e.g. 5.25.)
4). For each plant show the assignment of costs to units
transferred out and in process.
Expert Answer
3)
Unit costs of production: | |
T12 Tables | $ 37.00 |
C10 Chairs | $ 31.51 |
Working:
T12 Tables:
Physical Units | |||
Units in Work in process, July 1 | 0 | ||
Units started in Production | 24600 | ||
Total Units to account for | 24600 | ||
Equivalent Units | |||
Physical Units | Materials | Labor + Overheads | |
Units completed and transferred out | 20910 | 20910 | 20910 |
Units in Work in process, July 31 | 3690 | 3690 | 2214 |
Total Units accounted for | 24600 | 24600 | 23124 |
Total Costs to be accounted for | |||
Materials | Labor + Overheads | Total | |
Work in process, July 1 | 0 | 0 | 0 |
Costs added during the month | 467400 | 416232 | 883632 |
Total costs to be accounted for | 467400 | 416232 | 883632 |
Cost per Equivalent unit | |||
Materials | Labor + Overheads | Total | |
Total costs to be accounted for | 467400 | 416232 | 883632 |
Total equivalent units accounted for | 24600 | 23124 | |
Cost per equivalent unit | 19.00 | 18.00 | 37.00 |
C10 Chairs:
Physical Units | |||
Units in Work in process, July 1 | 0 | ||
Units started in Production | 19680 | ||
Total Units to account for | 19680 | ||
Equivalent Units | |||
Physical Units | Material | Labor + Overheads | |
Units completed and transferred out | 19065 | 19065 | 19065 |
Units in Work in process, July 31 | 615 | 615 | 492 |
Total Units accounted for | 19680 | 19680 | 19557 |
Total Costs to be accounted for | |||
Material | Labor + Overheads | Total | |
Work in process, July 1 | 0 | 0 | 0 |
Costs added during the month | 354240 | 264204 | 618444 |
Total costs to be accounted for | 354240 | 264204 | 618444 |
Cost per Equivalent unit | |||
Materials | Labor + Overheads | Total | |
Total costs to be accounted for | 354240 | 264204 | 618444 |
Total equivalent units accounted for | 19680 | 19557 | |
Cost per equivalent unit | 18.00 | 13.51 | 31.51 |
4)
Assignment of costs: | |
Plant 1: | |
Units transferred out | $ 773,670 |
Units in process | $ 109,962 |
Plant 2: | |
Units transferred out | $ 600,738 |
Units in process | $ 17,717 |
Working:
T12 Tables | ||
Costs accounted for: | ||
Transferred out (20910 x $37) | 773670 | |
Work in process | ||
Materials (3690 x $19) | 70110 | |
Conversion costs (2214 x $18) | 39852 | 109962 |
Total costs | 883632 | |
C10 Chairs | ||
Costs accounted for: | ||
Transferred out (19065 x $31.51) | 600738 | |
Work in process | ||
Materials (615 x $18) | 11070 | |
Conversion costs (492 x $13.51) | 6647 | 17717 |
Total costs | 618455 |
Please note: There is a difference of $11 in the total costs of C10 chairs on account of rounding off.