In: Accounting
Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making a product are as follows.
Cutting Department |
||
Production Data—July |
T12-Tables |
|
Work in process units, July 1 | 0 | |
Units started into production | 21,000 | |
Work in process units, July 31 | 3,150 | |
Work in process percent complete | 60 | |
Cost Data—July |
||
Work in process, July 1 |
$0 | |
Materials |
399,000 | |
Labor |
246,120 | |
Overhead |
109,200 | |
Total |
$754,320 |
(a1)
Compute the physical units of production.
T12 Tables |
||
Units to be accounted for |
eTextbook and Media
Save for Later
Attempts: 0 of 3 used
Submit Answer
Using multiple attempts will impact your score.
10% score reduction after attempt 2
(a2)
Compute equivalent units of production for materials and for conversion costs.
Materials |
Conversion Costs |
|||
T12 Tables |
eTextbook and Media
Save for Later
Attempts: 0 of 3 used
Submit Answer
Using multiple attempts will impact your score.
10% score reduction after attempt 2
(a3)
Determine the unit costs of production.
Materials |
Conversion Costs |
Total Costs |
||||
Unit costs-T12 Tables |
$ |
$ |
$ |
eTextbook and Media
Save for Later
Attempts: 0 of 3 used
Submit Answer
Using multiple attempts will impact your score.
10% score reduction after attempt 2
(a4)
Show the assignment of costs to units transferred out and in process.
T12 Tables |
||
Costs accounted for: |
||
Transferred out |
$ |
|
Work in process |
||
Materials |
$ |
|
Conversion costs |
||
Total costs |
$ |
eTextbook and Media
Save for Later
Attempts: 0 of 3 used
Submit Answer
Using multiple attempts will impact your score.
10% score reduction after attempt 2
(b)
Prepare the production cost report for July 2020.
THAKIN INDUSTRIES INC. |
||||||||
Equivalent Units |
||||||||
Quantities |
Physical |
|
Conversion |
|||||
Units to be accounted for |
||||||||
Work in process, July 1 |
||||||||
Started into production |
||||||||
Total units |
||||||||
Units accounted for |
||||||||
Transferred out |
||||||||
Work in process, July 31 |
||||||||
Total units |
||||||||
|
|
Conversion |
|
|||||
Unit costs |
||||||||
Total Costs |
$ |
$ |
$ |
|||||
Equivalent units |
||||||||
Unit costs |
$ |
$ |
$ |
|||||
Costs to be accounted for |
||||||||
Work in process, July 1 |
$ |
|||||||
Started into production |
||||||||
Total costs |
$ |
|||||||
Cost Reconciliation Schedule |
||||||||
Costs accounted for |
||||||||
Transferred out |
$ |
|||||||
Work in process, July 31 |
||||||||
Materials |
$ |
|||||||
Conversion costs |
||||||||
Total costs |
$ |
1 | |||||
T12 Tables | |||||
Units to be accounted for | 21000 | ||||
2 | |||||
Materials | Conversion Costs | ||||
T12 Tables | 21000 | 19740 | |||
3 | |||||
Materials | Conversion Costs | Total costs | |||
Unit costs T12 Tables | 19.00 | 18.00 | 37.00 | ||
4 | |||||
Costs accounted for: | |||||
Transferred out | 660450 | ||||
Work in process | |||||
Materials | 59850 | ||||
Conversion costs | 34020 | 93870 | |||
Total costs | 754320 |
Cutting Department-Plant 1 | |||||
Production Cost Report | |||||
For the Month Ended July 31, 2020 | |||||
Equivalent Units | |||||
Physical Units | Materials | Conversion Costs | |||
Units to be accounted for | |||||
Work in process, July 1 | 0 | ||||
Started into production | 21000 | ||||
Total units | 21000 | ||||
Units accounted for | |||||
Transferred out | 17850 | 17850 | 17850 | ||
Work in process, July 31 | 3150 | 3150 | 1890 | ||
Total units | 21000 | 21000 | 19740 | ||
Materials | Conversion Costs | Total | |||
Unit costs: | |||||
Total costs | 399000 | 355320 | 754320 | ||
Equivalent units | 21000 | 19740 | |||
Unit costs | 19.00 | 18.00 | 37.00 | ||
Costs to be accounted for | |||||
Work in process, July 1 | 0 | ||||
Started into production | 754320 | ||||
Total costs | 754320 | ||||
Cost Reconciliation Schedule | |||||
Costs accounted for | |||||
Transferred out | 660450 | =17850*37 | |||
Work in process, July 31 | |||||
Materials | 59850 | =3150*19 | |||
Conversion costs | 34020 | 93870 | =1890*18 | ||
Total costs |