In: Accounting
Bakker Industries sells three products (Products 611, 613, and 615) that it manufactures in a factory consisting of four departments (Departments 1 through 4). Both labor and machine times are applied to the products in each of the four departments. Neither machines nor labor can be switched from one department to another.
Bakker’s management is planning its production schedule for the next several months. There are labor shortages in the community. Some of the machines will be out of service for overhauling. Available machine and labor time by department for each of the next 6 months is listed below.
Department |
|||||||||
|
|||||||||
Monthly Capacity Availability |
1 |
2 |
3 |
4 |
|||||
|
|
|
|
|
|||||
Normal machine capacity in machine hours |
3,500 |
3,500 |
3,000 |
3,500 |
|||||
Capacity of machines being repaired in machine hours |
(500) | (400) | (300) | (200) | |||||
Available machine capacity in machine hours |
3,000 |
3,100 |
2,700 |
3,300 |
|||||
Labor capacity in direct labor hours |
4,000 |
4,500 |
3,500 |
3,000 |
|||||
Available labor in direct labor hours |
3,700 |
4,500 |
2,750 |
2,600 |
Labor and Machine Specifications per Unit of Product | |||||||
|
|||||||
Product |
Labor and Machine Time |
||||||
|
|
||||||
611 |
Direct labor hours |
2 | 3 | 3 | 1 | ||
Machine hours |
2 | 1 | 2 | 2 | |||
613 |
Direct labor hours |
1 | 2 | -- | 2 | ||
Machine hours |
1 | 1 | -- | 2 | |||
615 |
Direct labor hours |
2 | 2 | 1 | 1 | ||
Machine hours |
2 | 2 | 1 | 1 |
The Sales Department’s forecast of product demand over the next six months is presented below.
Product | Monthly Sales Volume (Units) | ||
|
|
||
611 | 500 | ||
613 | 400 | ||
615 |
1,000 |
Bakker’s inventory levels will not be increased or decreased during the next six months. The unit price and cost data valid for the next six months are presented below.
Product |
||||||
|
||||||
611 |
613 |
615 |
||||
|
|
|
||||
Unit selling price |
$196 |
$123 |
$167 |
|||
Unit costs: | ||||||
Direct material |
$ 7 | $ 13 | $ 17 | |||
Direct labor: |
||||||
Department 1 |
12 | 6 | 12 | |||
Department 2 |
21 | 14 | 14 | |||
Department 3 |
24 | -- | 16 | |||
Department 4 |
9 | 18 | 9 | |||
Variable overhead |
27 | 20 | 25 | |||
Fixed overhead |
15 | 10 | 32 | |||
Variable selling |
3 | 2 |
4 A: Determine whether the monthly sales demand for the three products can be met by Bakker Industries’ factory. Use the monthly requirement by department for machine hours and direct labor hours for the production of Products 611, 613, and 615 in your calculations. B: If Bakker chooses to maximize contribution margin through the bottleneck operation, what total contribution amount will the company achieve? Support the schedule with appropriate calculations, and present a schedule of the contribution to profit that would be generated by the production schedule selected. If Bakker chooses to maximize throughput margin, what total throughput margin will the company achieve? Support the schedule with appropriate calculations, and present a schedule of the contribution to profit that would be generated by the production schedule selected. C: |
Answer A
Total Labour Hours Required | Total Machine hours Required | ||||||||
Product | Demand (Units) | D1 | D2 | D3 | D4 | D1 | D2 | D3 | D4 |
611 | 500 | 1000 | 1500 | 1500 | 500 | 1000 | 500 | 1000 | 1000 |
613 | 400 | 400 | 800 | 0 | 800 | 400 | 400 | 0 | 800 |
615 | 1000 | 2000 | 2000 | 1000 | 1000 | 2000 | 2000 | 1000 | 1000 |
Required Hrs | 3400 | 4300 | 2500 | 2300 | 3400 | 2900 | 2000 | 2800 | |
Available Hrs | 3700 | 4500 | 2750 | 2600 | 3000 | 3100 | 2700 | 3300 | |
Surplus / (Deficit) | 300 | 200 | 250 | 300 | (400) | 200 | 700 | 500 |
It can be clearly seen that total machine hours required in department D1 is 3400 while machine hours available is only 3000 hours. Hence, there is shortfall of 400 machine hours.
Thus the monthly sales demand for the three products cannot be met by Bakker Industries’ factory
Answer B
Since machine hours of department 1 is bottleneck, contribution per MH of Department 1 is to be calculated to determine the ranking of products.
Product | ||||
611 | 613 | 615 | ||
Selling Price | 196.00 | 123.00 | 167.00 | |
Material | 7.00 | 13.00 | 17.00 | |
Labour | ||||
D1 | 12.00 | 6.00 | 12.00 | |
D2 | 21.00 | 14.00 | 14.00 | |
D3 | 24.00 | - | 16.00 | |
D4 | 9.00 | 18.00 | 9.00 | |
Variable Overhead | 27.00 | 20.00 | 25.00 | |
Variable Selling Price | 3.00 | 2.00 | 4.00 | |
Contribution | 93.00 | 50.00 | 70.00 | |
Machine hours required in D1 | 2.00 | 1.00 | 2.00 | |
Contribution per Machine hour of D1 | 46.50 | 50.00 | 35.00 |
Ranking II I III
Since the contribution per machine hour of D1 is highest in case of Product 613, it wil be produced first and then product 611 and 615 sequentially.
Product Name | Machine Hour of D1 utilised | Units Produced |
613 | 400 | 400 |
611 | 1000 | 500 |
615 | 1600 | 800 |
3000 |
Total Contribution as per above production schedule:
Product | ||||
611 | 613 | 615 | ||
Units Manufactured | 1000 | 400 | 1600 | |
Contribution Per Unit | 93 | 50 | 70 | |
(As calculated Above) | ||||
Total Contribution | 93000 | 20000 | 112000 |
Aggregate Contribution of all products = $ 225000
Answer C:
Throughput Margin in Calculated by reducing Direct Material Cost from the Sales.
Product | ||||
611 | 613 | 615 | ||
Selling Price | 196.00 | 123.00 | 167.00 | |
Direct Material Cost | 7.00 | 13.00 | 17.00 | |
Throughput Margin | 189.00 | 110.00 | 150.00 | |
Machine hours required in D1 | 2.00 | 1.00 | 2.00 | |
Contribution per Machine hour of D1 | 94.50 | 110.00 | 75.00 | |
Units Produced | 1,000 | 400 | 1,600 | |
Total Throughput Margin | 1,89,000 | 44,000 | 2,40,000 |
Total throughput margin for all products = 4,73,000