Question

In: Economics

Consider the following project cash flow series along with project balances. Knowing the relationship between the...

Consider the following project cash flow series along with project balances. Knowing the relationship between the project cash flow and their project balances calculate interst rate used net future worth at the project life, and its percent worth

Year

Cash flow

Project balance

0

$-1000

$-1000

1

$200

$ -900

2

$490

-$500

3

$550

$0

4

-$100

-$100

5

$310

$200

Solutions

Expert Solution

Year Cash flow Project balance DF at 10% DF at 15% NPV at 10% NPV at 15%
0 -1000 -1000 1.00 1.00 -1000.00 -1000.00
1 200 -900 0.91 0.87 181.82 173.91
2 490 -500 0.83 0.76 404.96 370.51
3 550 0 0.75 0.66 413.22 361.63
4 -100 -100 0.68 0.57 -68.30 -57.18
5 310 200 0.62 0.50 192.49 154.12
? 0.14 NPV 124.18 3.01

So, we need to find interest rate (IRR) at which NPV is zero

IRR = R1+((NPV1*(R2-R1))/(NPV1-NPV2))
R1 = Lower discount rate
R2 = Higher discount rate
NPV1 = Higher Net Present Value at R1
NPV2 = Lower Net Present Value at R2

IRR = 0.1+ (124.18*(0.15-0.1))/(124.18-3) = 0.1+0.0512 = 0.1512 or 15.12 percent

NPW is zero at 15.12 percent

Year Cash flow Project balance Compounding factor Future worth
0 -1000 -1000 1.00 -1000.00
1 200 -900 1.15 230.24
2 490 -500 1.33 649.38
3 550 0 1.53 839.10
4 -100 -100 1.76 -175.63
5 310 200 2.02 626.78
NFW 1169.87

So, NFW = $1169.87


Related Solutions

Consider the following cash flow for an apartment development project:
Consider the following cash flow for an apartment development project: Year     Cash Flow 0          $(522,720) 1          $(441,716) 2          $74,260 3          $83,684 4          $93,391 5          $1,983,228 What is the IRR? What is the total profit? What is the Net Present Value (NPV) if the discount rate is 10%?  
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II)...
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II) 0 -$12,300 -$44,000 1 $1,800 $14,000 2 $6,000 $30,000 3 $2,000 $5,000 4 $5,000 $10,000 5 $7,000 $5,000 The required return is 10% for both projects. Assume that the internal rate of return (IRR) of Project I and Project II is 18% and 15%, respectively. a) Which project will you choose if you apply the NPV criterion? Why? b) Which project will you choose...
consider a project with the following cash flow; Year cash flow shs '000' abandonment value shs...
consider a project with the following cash flow; Year cash flow shs '000' abandonment value shs '000' 0 (16,000) 1 7,000 ___________ 2 6,000 1,100 3 4,000 9,000 4 4,000 5,000 The cost of capital is 15% and re-investment rate is 20%. Required; i) Determine the optimal abandonment period.
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2 Cash Flow Year 3 Cash Flow Year 4 Cash Flow Discount Rate A -100 40 50 60 N/A .15 B -73 30 30 30 30 .15 Assume that projects A and B are mutually exclusive. The correct investment decision and the best rational for that decision is to: Group of answer choices a.invest in project A since NPVB < NPVA. b.invest in project B...
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project...
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project B(Rs) 0 -40000 -50000 1 20000 10000 2 15000 20000 3 15000 40000 The cash flow of project A are expressed in real terms while those of project B are expressed in nominal terms.The appropriate nominal discount rate is 15% and the inflation rate is 4%. Which project should be choosen.
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1...
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1 -80,500 2 138,425 3 -105,455 4 30,030 Required: 1.1.Fill in the following table: Cost of Capital (%) Project NPV 0 5 10 15 20 25 30 35 50 1.2.Use the values developed in part (1.1) to draw an NPV profile for this project. 1.3.What is the IRR for this project? 1.4.Describe the conditions under which the company should accept this project.
Consider a project generating the following cash flows over six years: Year Cash Flow (R in...
Consider a project generating the following cash flows over six years: Year Cash Flow (R in millions) 0 -59.00 1 4.00 2 5.00 3 6.00 4 7.33 5 8.00 6 8.25 Required: 1. Calculate the NPV over six years. The discount rate is 11%. 2. This project does not end after the sixth year but instead will generate cash flows far into the future. Estimate the terminal value, assume that cash flows after year 6 will continue at R8.25 million...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
Cash flow series Annual Cash Flow ($ per year) Annual Cash Flow ($ per year) Annual...
Cash flow series Annual Cash Flow ($ per year) Annual Cash Flow ($ per year) Annual Cash Flow ($ per year) Year Prob = 0.3 Prob = 0.22 Prob = 0.48 0 –5000 –6000 –4000 1 1000 500 3100 2 1000 1500 1200 3 1000 2000 100 Determine the expected present worth of the following cash flow series if each series may be realized with the probability shown at the head of each column. Let i = 20% per year....
Consider the following alternatives for a Beta company investment project: Net cash flow n Proyect A...
Consider the following alternatives for a Beta company investment project: Net cash flow n Proyect A Proyect B 0 -10,000 -20,000 1 5,500 0 2 5,500 0 3 5,500 40,000 IRR 30% ? PW(15%) ? 6,300 The company's MARR for this type of project is 15%. (a) Determine the IRR of project B. (b) Calculate the PW of project A. (c) Suppose alternatives A and B are mutually exclusive, determine which of them is more attractive using the rate of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT