Question

In: Finance

consider a project with the following cash flow; Year cash flow shs '000' abandonment value shs...

consider a project with the following cash flow;

Year cash flow shs '000' abandonment value shs '000'

0 (16,000)

1 7,000 ___________

2 6,000 1,100

3 4,000 9,000

4 4,000 5,000

The cost of capital is 15% and re-investment rate is 20%.

Required;

i) Determine the optimal abandonment period.

Solutions

Expert Solution

Project can be abandoned in year 1,2,3 or 4

Re-Investment Rate = 20%

Calculation of NPV of Cash flows if project is abandoned in Year 1

Year

Project Cash flows

Present Value Factor @ 15%

Present Value of Cash flows

1

7000

0.8696

6086.96

NPV = 6086.96 -16000 = -9913.04

Calculation of NPV of Cash flows if project is abandoned in Year 2

Year

Project Cash flows

Notes

1

7000

Reinvested Until Year 2 @ 20%

2

8400

Total Reinvested matured amount at the end of Year 2 @ 20% (7000*(1+20%))

2

6000

Normal Project Cash flows

2

1100

Abandoned Cash flows

15500

Total Year 2 Cash flows

Total Year 2 Cash flows                                                                                                 =15500

Present Value Factor @ 15% for year 2   =1/((1+15%)^2)                                = 0.7561

PV of Cash flows if project is abandoned in Year 2 =(15500*0.7561)            =11720.22684    

NPV = 11720.23-16000                                                                                                    = -4279.77          

Calculation of NPV of Cash flows if project is abandoned in Year 3

Year

Project Cash flows

Notes

1

7000

Reinvested Until Year 3 @ 20% i.e., for 2 years

2

6000

Reinvested Until Year 3 @ 20% i.e., for 1 year

3

10080

Total Reinvested matured amount at the end of Year 3 @ 20% (7000*(1+20%)*(1+20%)) for year 1 reinvestment

3

7200

Total Reinvested matured amount at the end of Year 3 @ 20% (6000*(1+20%)) for year 2 reinvestment

3

4000

Normal Project Cash flows

3

9000

Abandoned Cash flows

30280

Total Year 3 Cash flows

Total Year 3 Cash flows 30280

Present Value Factor @ 15% for year 3 =1/((1+15%)^3) = 0.6575

PV of Cash flows if project is abandoned in Year 3 '=(30280*0.6575)           = 19909.59152

NPV = 19910.59-16000 =              3910.59

Calculation of NPV of Cash flows if project is abandoned in Year 4

Year

Project Cash flows

Notes

1

7000

Reinvested Until Year 4 @ 20% i.e., for 3 years

2

6000

Reinvested Until Year 4 @ 20% i.e., for 2 years

3

4000

Reinvested Until Year 4 @ 20% i.e., for 1 year

4

12096

Total Reinvested matured amount at the end of Year 3 @ 20% (7000*(1+20%)^3) for year 1 reinvestment

4

8640

Total Reinvested matured amount at the end of Year 3 @ 20% (6000*(1+20%)^2) for year 2 reinvestment

4

4800

Total Reinvested matured amount at the end of Year 3 @ 20% (6000*(1+20%)) for year 3 reinvestment

4

4000

Normal Project Cash flows

4

5000

Abandoned Cash flows

34536

Total Year 4 Cash flows

Total Year 4 Cash flows

34536

Present Value Factor @ 15% for year 3 =1/((1+15%)^4)

0.5718

PV of Cash flows if project is abandoned in Year 3 '=(34536*0.5718)

19746.07

NPV = 19746.07-16000

3746.07

Summary of NPVS

If project is abandoned in year

NPV

1

-9913.04

2

-4279.77

3

3910.59

4

3746.07

Year 3 is having highest NPV. Therefore, project shall be abandoned in year 3 which is the optimal abandonment period

Please give me a like if you find this answer helpful! Let me know if you have any doubts in the comments section. Happy to help!


Related Solutions

Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2 Cash Flow Year 3 Cash Flow Year 4 Cash Flow Discount Rate A -100 40 50 60 N/A .15 B -73 30 30 30 30 .15 Assume that projects A and B are mutually exclusive. The correct investment decision and the best rational for that decision is to: Group of answer choices a.invest in project A since NPVB < NPVA. b.invest in project B...
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II)...
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II) 0 -$12,300 -$44,000 1 $1,800 $14,000 2 $6,000 $30,000 3 $2,000 $5,000 4 $5,000 $10,000 5 $7,000 $5,000 The required return is 10% for both projects. Assume that the internal rate of return (IRR) of Project I and Project II is 18% and 15%, respectively. a) Which project will you choose if you apply the NPV criterion? Why? b) Which project will you choose...
Consider the following cash flow for an apartment development project:
Consider the following cash flow for an apartment development project: Year     Cash Flow 0          $(522,720) 1          $(441,716) 2          $74,260 3          $83,684 4          $93,391 5          $1,983,228 What is the IRR? What is the total profit? What is the Net Present Value (NPV) if the discount rate is 10%?  
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project...
Q) Consider the following cash flow on two mutually exclusive projects. Year Project A (Rs) Project B(Rs) 0 -40000 -50000 1 20000 10000 2 15000 20000 3 15000 40000 The cash flow of project A are expressed in real terms while those of project B are expressed in nominal terms.The appropriate nominal discount rate is 15% and the inflation rate is 4%. Which project should be choosen.
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1...
Question 1 Consider a project with the following cash flows: Year Cash Flow 0 R17,500 1 -80,500 2 138,425 3 -105,455 4 30,030 Required: 1.1.Fill in the following table: Cost of Capital (%) Project NPV 0 5 10 15 20 25 30 35 50 1.2.Use the values developed in part (1.1) to draw an NPV profile for this project. 1.3.What is the IRR for this project? 1.4.Describe the conditions under which the company should accept this project.
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
Abandonment option: Consider a 3-year project with a 14.00% cost of capital. The initial investment is...
Abandonment option: Consider a 3-year project with a 14.00% cost of capital. The initial investment is $1,000 and the expected cash flows are $400 per year. a. Calculate NPV and determine whether or not to undertake this project. b. Suppose instead that we have more information on the expected cash flows. First, there is a 40.00% probability that the project is a success and the cash flows will be $700 and a 60.00% probability that the project is a failure...
What is the Net Present Value of the following cash flow stream? Year Cash Flow 0...
What is the Net Present Value of the following cash flow stream? Year Cash Flow 0 -$489 1 $363 2 $192 3 $161 4 $256 Assume an interest rate of 13% Note: Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. If your answer is negative, enter your answer as a negative number rounded off to two decimal points.
Gio's Restaurants is considering a project with the following expected cash​ flows: Year Project Cash Flow​...
Gio's Restaurants is considering a project with the following expected cash​ flows: Year Project Cash Flow​ (millions) 0 ​$(180​) 1 80 2 75 3 80 4 95 If the​ project's appropriate discount rate is 12 ​percent, what is the​ project's discounted payback​ period? The​ project's discounted payback period is ___ years.
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT