In: Finance
Consider the following two mutually exclusive projects:
Year |
Cash Flow (Project I) |
Cash Flow (Project II) |
0 |
-$12,300 |
-$44,000 |
1 |
$1,800 |
$14,000 |
2 |
$6,000 |
$30,000 |
3 |
$2,000 |
$5,000 |
4 |
$5,000 |
$10,000 |
5 |
$7,000 |
$5,000 |
The required return is 10% for both projects. Assume that the internal rate of return (IRR) of Project I and Project II is 18% and 15%, respectively.
a) Which project will you choose if you apply the NPV criterion? Why?
b) Which project will you choose if you apply the payback
criterion? Why?
c) Which project will you choose if you apply the IRR criterion? Why?
d) Based on the above answers, which project will you finally
choose? Why?
1) Project II will be selected since, NPV of project II is higher than the NPV of project I
Project I | |||
Year | Cashflow | PVF @10% | Cashflow * PVF |
0 | $ -12,300 | 1.0000 | $ -12,300.00 |
1 | $ 1,800 | 0.9091 | $ 1,636.36 |
2 | $ 6,000 | 0.8264 | $ 4,958.68 |
3 | $ 2,000 | 0.7513 | $ 1,502.63 |
4 | $ 5,000 | 0.6830 | $ 3,415.07 |
5 | $ 7,000 | 0.6209 | $ 4,346.45 |
NPV | $ 3,559.19 |
Project II | |||
Year | Cashflow | PVF @10% | Cashflow * PVF |
0 | $ -44,000 | 1.0000 | $ -44,000.00 |
1 | $ 14,000 | 0.9091 | $ 12,727.27 |
2 | $ 30,000 | 0.8264 | $ 24,793.39 |
3 | $ 5,000 | 0.7513 | $ 3,756.57 |
4 | $ 10,000 | 0.6830 | $ 6,830.13 |
5 | $ 5,000 | 0.6209 | $ 3,104.61 |
NPV | $ 7,211.98 |
b) Project II will be selected since, payback of project II is lower than the payback of project I
Project I | |||
Year | Cashflow | cummulative cashflow | |
0 | $ -12,300 | ||
1 | $ 1,800 | $ 1,800 | |
2 | $ 6,000 | $ 7,800 | |
3 | $ 2,000 | $ 9,800 | |
4 | $ 5,000 | $ 14,800 | |
5 | $ 7,000 | $ 21,800 | |
Payback | 3.5 years | =>3years+(12300-9800)/5000 |
Project II | ||
Year | Cashflow | cummulative cashflow |
0 | $ -44,000 | |
1 | $ 14,000 | $ 14,000 |
2 | $ 30,000 | $ 44,000 |
3 | $ 5,000 | $ 49,000 |
4 | $ 10,000 | $ 59,000 |
5 | $ 5,000 | $ 64,000 |
Payback | 2years |
c) Internal rate of return (IRR) of Project I and Project II is 18% and 15%, respectively, project I will be selected based on IRR being higher IRR
d) Project II is selcted being higher NPV and lower payback period
Thumbs up Please! Thank You