Question

In: Accounting

Orion Limited had total overheads for a month of £24,000. The total monthly budgeted labour hours...

Orion Limited had total overheads for a month of £24,000. The total monthly budgeted labour hours were 1,200 and the total budgeted material usage was 1,600 kg. During the month the company gives a quotation for a job which requires 60 kg of materials at £7.50 per kg and 12 direct labour hours at £25 per hour. Overheads are recovered on the basis of direct labour hours. The profit is 25% based on selling price.

(i) if the actual direct labour hours worked on the job were 15, what would be the new profit, assuming that the quoted selling price could not be renegotiated?

(ii) if overheads were instead recovered based on material usage rather than labour hours, would that have changed your answer to part (i) above, if so what would be the new profit?

(c) “Managing costs is very important given the competitive environment in which modern businesses operate “. Discuss this statement including in your discussion some of the recent approaches to costing which have emerged to help businesses manage their costs (maximum 600 words).

Solutions

Expert Solution

Note 1 :

Recovery Rate of overheads :

Based on Labour Hours = Total Ovhds / Total Labor hrs = 24000 / 1200 hrs = £ 20 / hr

Based on Direct material = Total Ovhds / Direct material = 24000 / 1600 kg = £ 15 / kg

Note 2 :

Calculation of Standard Job quotation

Particulars

Details

£

D. MAt

60 kg * £7.50 per kg

450

D.Labor

12 hours * £25 per hour

300

Prime Cost

750

Overheads (on the basis of direct labour hours)

12 hours *   £ 20 / hr ( NOte 1)

240

Total Cost

990

Add: Profit (25 % on S.P. or 33.33333 % on Cost )

990 * 1/3

330

Selling Price

1320

Ans (i)

Calculation of Job quotation if Labour hours were 15 instead of 12

Particulars

Details

£

D. MAt

60 kg * £7.50 per kg

450

D.Labor

15 hours * £25 per hour

375

Prime Cost

825

Overheads (on the basis of direct labour hours)

15 hours *   £ 20 / hr ( NOte 1)

300

Total Cost

1125

Add: Profit

Balancing figure

195

Selling Price( Note 2 )

1320

So , the new profit would be £ 195

Ans (ii)

Calculation of Job quotation if Ovhds were recovered on material usage

Particulars

Details

£

D. MAt

60 kg * £7.50 per kg

450

D.Labor

15 hours * £25 per hour

375

Prime Cost

825

Overheads (on the basis of direct material )

60 kg * £ 15 per kg ( NOte 1)

900

Total Cost

1725

Less : Loss

Balancing figure

(405)

Selling Price( Note 2 )

1320

So , in this case it would have resulted in a loss instead of profit of £ (405)

c) “Managing costs is very important given the competitive environment in which modern businesses operate “. Discuss

Ans : This is very true in terms of present competitive scenario shared world wide . The world is a Global village. Hence , Costing is of Utmost importance in Today's context . The living example is Growing economy of China and world's dependence on it , knowing what China is up to .

The management should move on to more recent techniques of costing like Marginal and ABC costing rather than traditional costing.


Related Solutions

During the month of July, direct labour cost totalled $24,000 and direct labour cost was 30%...
During the month of July, direct labour cost totalled $24,000 and direct labour cost was 30% of prime cost. If total manufacturing costs during June were $105,000, the manufacturing overhead was:
A business absorbs overheads on a machine hour basis, which were budgeted at 12,250 machine hours...
A business absorbs overheads on a machine hour basis, which were budgeted at 12,250 machine hours with overheads of £147,000. Actual results were 9,870 hours with actual overheads of £154,645. Calculate the over or under recovery. Over recovery of £36,205 Over recovery of £7,645 Under recovery of £7,645 Under recovery of £36,205 A highly automated process is used to make tins of paint. It has a budgeted overhead of £40,000, taking 1,250 machine hours and 500 direct labour hours. Each...
Q 12 LCC has total budgeted production overheads for next year of GHS816,000 and has traditionally...
Q 12 LCC has total budgeted production overheads for next year of GHS816,000 and has traditionally absorbed overheads on machine hour basis. It makes two products Product V and Product W Product V Product W Direct materials cost per unit GHS20 GHS60 Direct labour cost per unit GHS50 GHS40 Machine time per unit 3 hours 4 hours Annual production 6000 units 4,000 units Required: a) Calculate the product cost for each of the two products on the assumption the firm...
The following information pertains to Glass Works Company for 2014. Budgeted direct-labour cost: --------------------------------75,000 hours at...
The following information pertains to Glass Works Company for 2014. Budgeted direct-labour cost: --------------------------------75,000 hours at $16 per hour Actual direct-labour cost: ------------------------------------80,000 hours at $17.50 per hour. Budgeted Manufacturing Overhead: ---------------------$ 997,500 Actual Manufacturing Overhead: Depreciation ------------------------------------------------- $ 240,000 Property Taxes---------------------------------------------------12,000 Indirect Labour --------------------------------------------------82,000 Supervisory Salaries --------------------------------------------200,000 Utilities------------------------------------------------------------ 59,000 Insurance ----------------------------------------------------------30,000 Rental of Space-------------------------------------------------- 300,000 Indirect Material --------------------------------------------------- 79,000 Required (i) Compute the firm’s predetermined overhead rate, which is based on direct-labour hours. (ii) Calculate the overapplied or underapplied...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $77,385 $150,000 3,300 labor hours Correspondence $9,585 $26,000 2,700 letters Account billing $171,500 $79,000 2,450,000 lines Payment verification $12,980 $78,000 22,000 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $225,403 3,220 labor hours Correspondence $35,231 2,650 letters Account...
PROBLEM # 7 [ VARIANCE ANALYSIS ... The following is total monthly budgeted cost and activity...
PROBLEM # 7 [ VARIANCE ANALYSIS ... The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $75,936 $165,000 3,200 labor hours Correspondence $10,324 $21,000 2,900 letters Account billing $156,000 $76,000 2,600,000 lines Bill verification $10,105 $78,000 21,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $236,390 3,030 labor...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $79,200 $156,000 3,200 labor hours Correspondence $9,639 $22,000 2,700 letters Account billing $144,000 $77,000 2,400,000 lines Payment verification $12,095 $80,000 20,500 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $234,023 3,140 labor hours Correspondence $31,154 2,550 letters Account...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $73,888 $166,000 3,200 labor hours Correspondence $9,604 $27,000 2,800 letters Account billing $130,000 $70,000 2,600,000 lines Payment verification $11,825 $77,000 21,500 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $241,803 3,240 labor hours Correspondence $36,377 2,660 letters Account...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $76,416 $150,000 3,200 labor hours Correspondence $10,063 $24,000 2,900 letters Account billing $182,000 $82,000 2,600,000 lines Bill verification $10,750 $79,000 21,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $224,331 3,080 labor hours Correspondence $34,101 2,990 letters Account billing...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $82,926 $167,000 3,400 labor hours Correspondence $9,396 $25,000 2,700 letters Account billing $147,000 $88,000 2,450,000 lines Bill verification $11,890 $77,000 20,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $252,913 3,540 labor hours Correspondence $34,868 2,630 letters Account billing...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT