Question

In: Accounting

The following is total monthly budgeted cost and activity information for the four activity centers in...

The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company:

Activity Center

Variable

Fixed

Cost Driver

Statement inquiry

$79,200

$156,000

3,200 labor hours

Correspondence

$9,639

$22,000

2,700 letters

Account billing

$144,000

$77,000

2,400,000 lines

Payment verification

$12,095

$80,000

20,500 accounts


In September, actual total costs and activity were as follows:

Activity Center

Total Costs

Driver Amount

Statement inquiry

$234,023

3,140 labor hours

Correspondence

$31,154

2,550 letters

Account billing

$231,898

2,580,000 lines

Payment verification

$92,876

20,630 accounts


Required
Compute the flexible-budget variances for the following two activity cost items (round unit costs to two decimal places and enter favorable variances as positive numbers and unfavorable variances as negative numbers):

  Correspondence :

  Statement inquiry :

Solutions

Expert Solution

Total budgeted variable cost for statement inquiry = $ 79200

Cost driver for statement inquiry is labor hours and budgeted labor hours for statement inquiry = 3200 labor hours

Budgeted Statement inquiry variable cost per labor hour

= Variable cost / labor hours

     = $ 79200 /3200 labor hours = $ 24.75 per hour

Budgeted fixed cost for statement inquiry = $ 156000

Fixed cost will remain unchanged for a relevant range of activity. There is nothing mentioning about relevant range or normal capacity change. So, it is assumed that still the operation will be in the relevant range. So fixed cost will remain unchanged.

Actual labor hours incurred for statement inquiry= 3140 labor hours

Flexible budget cost for statement inquiry

   = (Actual labor hours * budgeted variable cost per unit) + Budgeted fixed cost

   = (3140 hours * $ 24.75 per hour ) + $ 156000 = $ 233715

Actual cost for statement inquiry = $ 234023

Flexible budget variance for statement inquiry = Actual cost – Flexible budget cost

    = $ 234023 - $ 233715 = - $ 308

Flexible budget variance for statement inquiry is unfavorable because actual cost is greater than the flexible budget cost.

Total budgeted variable cost for Correspondence = $ 9639

Cost driver for Correspondence is letters and budgeted number of letters for Correspondence = 2700 letters

Budgeted Correspondence variable cost per labor hour

= Variable cost / Budgeted number of letters

= $ 9639/2700 letters = $ 3.57 per letter

Budgeted fixed cost for Correspondence = $ 22000

Fixed cost will remain unchanged for a relevant range of activity. There is nothing mentioning about relevant range or normal capacity change. So, it is assumed that still the operation will be in the relevant range. So, fixed cost will remain constant.

Actual activity of letters in September = 2550 letters

Flexible budget cost for Correspondence

   = (Actual Activity * budgeted variable cost per unit) + Budgeted fixed cost

= (2550 letters * $ 3.57 per letter ) + $ 22000 = $ 31103.5

Actual cost for Correspondence for September = $ 31154

Flexible budget variance for Correspondence = Actual cost – Flexible budget cost

= $ 31154 - $ 31103.5 = - $ 50.5

Flexible budget variance for Correspondence is unfavorable because actual cost is greater than the flexible budget cost.

Flexible budget

Activity center

Actual total cost

Flexible budget cost

Flexible budget variance

(Actual – flexible)

Correspondence

$ 31154

$ 31103.5

- $ 50.5

Statement inquiry

$ 234023

$ 233715

- $ 308


Related Solutions

The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $77,385 $150,000 3,300 labor hours Correspondence $9,585 $26,000 2,700 letters Account billing $171,500 $79,000 2,450,000 lines Payment verification $12,980 $78,000 22,000 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $225,403 3,220 labor hours Correspondence $35,231 2,650 letters Account...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $73,888 $166,000 3,200 labor hours Correspondence $9,604 $27,000 2,800 letters Account billing $130,000 $70,000 2,600,000 lines Payment verification $11,825 $77,000 21,500 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $241,803 3,240 labor hours Correspondence $36,377 2,660 letters Account...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $76,416 $150,000 3,200 labor hours Correspondence $10,063 $24,000 2,900 letters Account billing $182,000 $82,000 2,600,000 lines Bill verification $10,750 $79,000 21,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $224,331 3,080 labor hours Correspondence $34,101 2,990 letters Account billing...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $82,926 $167,000 3,400 labor hours Correspondence $9,396 $25,000 2,700 letters Account billing $147,000 $88,000 2,450,000 lines Bill verification $11,890 $77,000 20,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $252,913 3,540 labor hours Correspondence $34,868 2,630 letters Account billing...
PROBLEM # 7 [ VARIANCE ANALYSIS ... The following is total monthly budgeted cost and activity...
PROBLEM # 7 [ VARIANCE ANALYSIS ... The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $75,936 $165,000 3,200 labor hours Correspondence $10,324 $21,000 2,900 letters Account billing $156,000 $76,000 2,600,000 lines Bill verification $10,105 $78,000 21,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $236,390 3,030 labor...
The following budgeted information is available for Zeta Company: Activity Budgeted Cost Activity Driver Consumption of...
The following budgeted information is available for Zeta Company: Activity Budgeted Cost Activity Driver Consumption of Drivers for Zeta’s Product Lines Total Activity Driver Product A Product B Processing & Testing Developing test programs $400,000 Engineering hours 10,000 2,500 7,500 Making probe cards 58,750 Development hours 4,000 400 3,600 Testing products 300,000 Test hours 20,000 2,000 18,000 Setups 40,000 Number of batches 100 55 45 Engineering design 80,000 Number of change orders 60 9 51 Handling lots 90,000 Number of...
Orion Limited had total overheads for a month of £24,000. The total monthly budgeted labour hours...
Orion Limited had total overheads for a month of £24,000. The total monthly budgeted labour hours were 1,200 and the total budgeted material usage was 1,600 kg. During the month the company gives a quotation for a job which requires 60 kg of materials at £7.50 per kg and 12 direct labour hours at £25 per hour. Overheads are recovered on the basis of direct labour hours. The profit is 25% based on selling price. (i) if the actual direct...
Ruby Company follows activity-based budgeting. From the information given below, calculate the total activity cost of...
Ruby Company follows activity-based budgeting. From the information given below, calculate the total activity cost of the company. Activity description Activity driver Cost per unit of driver Amount of driver Processing mail Number of clients $120 $75 Paying bills Number of bills $ 2.5 $10,000 Investigating Number of new hires $110 $75 Writing reports Number of clients $150 $75 a. $52,500 b. $52,800 c. $53,500 d. $53,200
a company provides the following abc costing information: activities total costs activity cost drivers labor 384000...
a company provides the following abc costing information: activities total costs activity cost drivers labor 384000 8000 hours gas 36000 6000 gallons invoices 180000 total costs 600000 the above activities used by their three departments are : department 1 department 2 department 3 labor 2500 hours 1400 hours 4100 hours gas 1800 gallons 1000 gallons 3200 gallons invoices 1300 invoices 300 invoices 5900 invoices how much of invoice cost will be assigned to department 2?
Assume Domino's Pizza has the following monthly revenue and cost functions: Total Revenue= $10.00x Total Cost=...
Assume Domino's Pizza has the following monthly revenue and cost functions: Total Revenue= $10.00x Total Cost= $16000+$4.00x a. Prepare a graph illistrating Domino's cost-volume-profit relationship. The vertical axis should range from $0 to $72,000, in increments os $12,000. The horizontal axis should range from 0 units to 6,000 units, in increments of 2,000 units. b. Prepare a graph illustrating Domino's profit-volume relationship. The horizontal axis should range from 0 units to 6,000 units, in increments of 2,000 units. c. When...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT