Question

In: Accounting

Abel Company uses activity-based costing. The company has two products: A and B. The annual production...

Abel Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 200 units and of Product B is 400 units. There are three activity cost pools, with estimated costs and expected activity as follows: 



Expected Activity

Activity Cost PoolEstimated CostProduct AProduct BTotal
Activity 1$16,660600100700
Activity 218,4501,1007001,800
Activity 39,73160160220

22. The cost per unit of Product A is closest to which of the following? 

A. $27.91. 

B. $56.38. 

C. $141.04. 

D. $70.52.

Solutions

Expert Solution

Activity rate=Respective cost/Respective activity

Activity rate for:

Activity 1=(16,660/700)=$23.8

Activity 2=(18450/1800)=$10.25

Activity 3=(9731/220)=$44.2318182(Approx)

Hence cost for A=(23.8*600)+(10.25*1100)+(44.2318182*60)

=$28208.91(Approx)

Hence cost per unit=28208.91/200

=$141.04(Approx)


Related Solutions

Lindsey Company uses activity-based costing. The company has two products: A and B. The annual production...
Lindsey Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 9,000 units and of Product B is 8,000 units. There are three activity cost pools, with total cost and total activity as follows: Total Activity Activity Cost Pool Total Cost Product A Product B Total Activity 1 $31,000 100 520 620 Activity 2 $46,287 860 250 1,110 Activity 3 $156,750 840 3,910 4,750 The activity-based costing cost per...
A company has two products: A and B. It uses activity-based costing and has prepared the...
A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three acivity cot pools. Cost Pool Budgeted Cost Product A Product B Activity 1 $87,000 3,000 2,800 Activity 2 $62,000 4,500 5,500 Activity 3 $93,000 2,500 5,250 Annual Production and sales level of Product A is, 34,300 units, and the annual production and sales level of Product B is 69,550 Units. What is...
Jennifer Company has two products: A and B. The company uses activity-based costing
Jennifer Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows: The activity rate under the activity based costing system for Supporting customers is closest to:
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
A company has two products: A1 and B2. It uses activity-based costing and has prepared the...
A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Budgeted Activity Activity Cost Pool Budgeted Cost Product A1 Product B2 Activity 1 $ 49,000 1,300 4,900 Activity 2 $ 64,000 2,340 4,860 Activity 3 $ 82,000 7,300 900 Annual production and sales level of Product A1 is 8,580 units, and the annual production and sales level of Product...
4) X Company makes two products, A and B, and uses an activity-based costing overhead allocation...
4) X Company makes two products, A and B, and uses an activity-based costing overhead allocation system, with three cost pools and three cost drivers. Budgeted costs and driver information for 2017 were as follows: Cost Pool 1 Cost Pool 2 Cost Pool 3 Budgeted costs $113,000 $53,000 $31,000 Cost Drivers Product A 84,000 62,000 75,000 Product B 63,000 54,000 47,000 What was the allocation to Product B in 2017?
1. A company has two products: A1 and B2. It uses activity-based costing and has prepared...
1. A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Budgeted Activity Activity Cost Pool Budgeted Cost Product A1 Product B2 Activity 1 $ 63,000 2,700 6,300 Activity 2 $ 78,000 3,740 6,260 Activity 3 $ 110,000 8,700 2,300 Annual production and sales level of Product A1 is 9,980 units, and the annual production and sales level of...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 85,000 7,500 10,500 21,500 Activity 2 $ 60,000 8,500 16,500 9,500 Activity 3 $ 112,000 4,000 2,500 3,125 How much overhead will be assigned to Product B...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted...
A company uses activity-based costing to determine the costs of its three products: A, B, and...
A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 75,000 6,500 9,500 20,500 Activity 2 $ 50,000 7,500 15,500 8,500 Activity 3 $ 92,000 3,000 1,500 2,125 How much overhead will be assigned to Product B...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT