Question

In: Accounting

Problem 10-12 Acquisition costs; lump-sum acquisition; noninterest-bearing note; interest capitalization [LO10-1, 10-2, 10-3, 10-7] Early in...

Problem 10-12 Acquisition costs; lump-sum acquisition; noninterest-bearing note; interest capitalization [LO10-1, 10-2, 10-3, 10-7]

Early in its fiscal year ending December 31, 2018, San Antonio Outfitters finalized plans to expand operations. The first stage was completed on March 28 with the purchase of a tract of land on the outskirts of the city. The land and existing building were purchased for $1,160,000. San Antonio paid $380,000 and signed a noninterest-bearing note requiring the company to pay the remaining $780,000 on March 28, 2020. An interest rate of 10% properly reflects the time value of money for this type of loan agreement. Title search, insurance, and other closing costs totaling $38,000 were paid at closing.
   
During April, the old building was demolished at a cost of $88,000, and an additional $68,000 was paid to clear and grade the land. Construction of a new building began on May 1 and was completed on October 29. Construction expenditures were as follows: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.)

May 1 $ 3,900,000
July 30 2,400,000
September 1 1,980,000
October 1 2,880,000


San Antonio borrowed $6,300,000 at 10% on May 1 to help finance construction. This loan, plus interest, will be paid in 2019. The company also had the following debt outstanding throughout 2018:

$3,800,000, 8% long-term note payable
$5,800,000, 5% long-term bonds payable


In November, the company purchased 10 identical pieces of equipment and office furniture and fixtures for a lump-sum price of $780,000. The fair values of the equipment and the furniture and fixtures were $572,000 and $308,000, respectively. In December, San Antonio paid a contractor $375,000 for the construction of parking lots and for landscaping.
  
Required:
1. Determine the initial values of the various assets that San Antonio acquired or constructed during 2018. The company uses the specific interest method to determine the amount of interest capitalized on the building construction.
2. How much interest expense will San Antonio report in its 2018 income statement?

Solutions

Expert Solution

Requirement 1

          Land

          Purchase price (determined below)           $1,024,631

          Closing costs                                              38,000

          Removal of old building                            88,000

          Clearing and grading                                68,000

                                                                    $1,218,631

          Purchase price of land:

               Cash paid                                          $380,000

               Value of note                                   644,631

                                                                    $1,024,631

          Present value of note payment:

          PV = $780,000 (.82645) = $644,631

          Present value of $1: n = 2, i = 10% (from Table 2)

          Land improvements

          Parking lot and landscaping                   $375,000

          Building

          Construction expenditures:

                   May 1                                       $3,900,000

                   July 30                                        2,400,000

                   September 1                                1,980,000

                   October 1                                    2,880,000

                      Total expenditures                  11,160,000

          Interest capitalized (determined below)            312,000

               Total cost of building                   $11,472,000

          Average accumulated expenditures:

          May 1, 2018             $3,900,000 x   6/6 = $ 3,900,000

          July 30, 2018             2,400,000 x   3/6 =    1,200,000

          September 1, 2018    1,980,000 x   2/6 =       660,000    

          October 1, 2018        2,880,000 x   1/6 =         480,000

                                                                              $6,240,000

          Interest capitalized:

          $6,240,000 x 10% x 6/12 =                            $312,000

Equipment and furniture and fixtures

                                                                                                  Initial

                                                             Percent of Total           Valuation

                                     Fair Value             Fair Value            % x $780,000

Equipment                     $572,000                   65%                  $507,000

Furniture & fixtures         308,000                  35%                    273,000

          Totals                   $880,000                 100%                  $780,000

Initial valuation:

Equipment                     $507,000

Furniture & fixtures         273,000

Requirement 2

Interest expense:

     Note issued to purchase land and building,

         $644,631 x 10% x 9/12 =                                $ 48,347

     Construction loan, $6,300,000 x 10% x 8/12         420,000

     Long-term note, $3,800,000 x 8%                         304,000

     Long-term bonds, $5,800,000 x 5%                       290,000

         Total                                                               1062,347

     Less: Interest capitalized (determined above)         (312,000)

Interest expense                                                         $750,347


Related Solutions

Problem 10-9 Interest capitalization; specific interest method [LO10-7] On January 1, 2018, the Mason Manufacturing Company...
Problem 10-9 Interest capitalization; specific interest method [LO10-7] On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a...
Problem 10-12 Variance Analysis in a Hospital [LO10-1, LO10-2, LO10-3] John Fleming, chief administrator for Valley...
Problem 10-12 Variance Analysis in a Hospital [LO10-1, LO10-2, LO10-3] John Fleming, chief administrator for Valley View Hospital, is concerned about the costs for tests in the hospital’s lab. Charges for lab tests are consistently higher at Valley View than at other hospitals and have resulted in many complaints. Also, because of strict regulations on amounts reimbursed for lab tests, payments received from insurance companies and governmental units have not been high enough to cover lab costs. Mr. Fleming has...
Problem 10-13 Basic Variance Analysis; the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3] Koontz...
Problem 10-13 Basic Variance Analysis; the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3] Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.90 feet at $3.00 per foot $ 5.70 Actual: 1.85 feet at $3.40 per foot $ 6.29 Direct labor: Standard: 1.00 hours at $18.00 per hour 18.00 Actual: 1.05...
Problem 10-13 Basic Variance Analysis; the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3] Koontz...
Problem 10-13 Basic Variance Analysis; the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3] Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.90 feet at $4.80 per foot $ 9.12 Actual: 1.85 feet at $5.20 per foot $ 9.62 Direct labor: Standard: 1.45 hours at $20.00 per hour 29.00 Actual: 1.50...
On January 2, SHB Company receives a 3-year, $10,000, noninterest bearing note, the present value of...
On January 2, SHB Company receives a 3-year, $10,000, noninterest bearing note, the present value of which is $7,722. The rate implicit on this transaction is 9%. You are completing SHB's note receivable account. To prepare each required journal entry: Enter the corresponding debit or credit amount in the associated column. Round all amounts to the nearest whole number. Not all rows in the table might be needed to complete each journal entry. If no journal entry is needed, check...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ? $ 3.00 per yard $ ? Direct labor ? ? ? Variable manufacturing overhead ? $ 2 per direct labor-hour ? Total standard cost per unit $ ? Overhead is applied to production on the basis...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ? $ 4.50 per yard $ ? Direct labor ? ? ? Variable manufacturing overhead ? $ 2 per direct labor-hour ? Total standard cost per unit $ ? Overhead is applied to production on the basis...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ? $ 6 per yard $ ? Direct labor ? ? ? Variable manufacturing overhead ? $ 3 per direct labor-hour ? Total standard cost per unit $ ? Overhead is applied to production on the basis...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is...
Problem 10-16 Comprehensive Variance Analysis [LO10-1, LO10-2, LO10-3] Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ? $ 4.00 per yard $ ? Direct labor ? ? ? Variable manufacturing overhead ? $ 2 per direct labor-hour ? Total standard cost per unit $ ? Overhead is applied to production on the basis...
Problem 10A-10 Comprehensive Standard Cost Variances [LO10-1, LO10-2, LO10-3, LO10-4] "Wonderful! Not only did our salespeople...
Problem 10A-10 Comprehensive Standard Cost Variances [LO10-1, LO10-2, LO10-3, LO10-4] "Wonderful! Not only did our salespeople do a good job in meeting the sales budget this year, but our production people did a good job in controlling costs as well,” said Kim Clark, president of Martell Company. “Our $20,825 overall manufacturing cost variance is only .5% of the $4,165,000 standard cost of products made during the year. That's well within the 3% parameter set by management for acceptable variances. It...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT