Question

In: Accounting

Problem 10-9 Interest capitalization; specific interest method [LO10-7] On January 1, 2018, the Mason Manufacturing Company...

Problem 10-9 Interest capitalization; specific interest method [LO10-7]

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019.

Expenditures on the project were as follows:

January 1, 2018 $ 1,420,000
March 1, 2018 1,140,000
June 30, 2018 1,340,000
October 1, 2018 1,140,000
January 31, 2019 351,000
April 30, 2019 684,000
August 31, 2019 981,000


On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate. The loan was outstanding all of 2018 and 2019. The company’s other interest-bearing debt included two long-term notes of $6,000,000 and $9,000,000 with interest rates of 8% and 10%, respectively. Both notes were outstanding during all of 2018 and 2019. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:
1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the specific interest method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.

Solutions

Expert Solution

Expenditure for 2018
January 1, 2018 1420000 * 12/12 1420000
March 1, 2018 1140000 * 10/12 950000
June 30, 2018 1340000 * 6/ 12 670000
October 1, 2018 1140000 * 3/12 285000
Accumulated expenditures 5040000
Before interest
Average Accumulated expenditures 3325000

Interest capitalized:$3,325,000 x 12% = $399,000 = Interest capitalized in 2018

Expenditure for 2019
January 1, 2019 5439000 * 9/9 5439000
January 31, 2019 351000 * 8/9 312000
April 30, 2019 684000 * 5/9 380000
August 31, 2019 981000 * 1/9 109000
Accumulated expenditures 7455000
Before interest
Average Accumulated expenditures 6240000

Weighted-average rate of all other debt

$6,000,000 * 8% = $ 480,000

$9,000,000 * 10% = $ 900,000

Weighted Average = 1380000 / 15,000,000 = 9.2%

Interest capitalized:

$3,900,000 * 12% x 9/12 = $351,000

2,340,000 x 9.2% x 9/12 = 161,460

Total = 512460 Interest capitalized in 2019

Cost of Building:

Expenditures in 2018= $3,325,000

Interest capitalized in 2018: 399,000

Expenditures in 2019: 2,016,000

Interest capitalized in 2019 : 512,460

Total cost of building $ 6252460

Interest Expense for 2018:

$3,900,000 x 12% =$ 468,000

6,000,000 x 8% = 480,000

9,000,000 x 10% =900,000

Total interest incurred 1,779,000

Less: Capitalized (399,000)

2018 expense $ 1,449,000

Interest Expense for 2019:

Total interest incurred $1,779,000

Less: Capitalized (512,460)

2019 expense $ 1,266,540


Related Solutions

Problem 10-12 Acquisition costs; lump-sum acquisition; noninterest-bearing note; interest capitalization [LO10-1, 10-2, 10-3, 10-7] Early in...
Problem 10-12 Acquisition costs; lump-sum acquisition; noninterest-bearing note; interest capitalization [LO10-1, 10-2, 10-3, 10-7] Early in its fiscal year ending December 31, 2018, San Antonio Outfitters finalized plans to expand operations. The first stage was completed on March 28 with the purchase of a tract of land on the outskirts of the city. The land and existing building were purchased for $1,160,000. San Antonio paid $380,000 and signed a noninterest-bearing note requiring the company to pay the remaining $780,000 on...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,070,000 March 1, 2018 840,000 June 30, 2018 380,000 October 1, 2018 710,000 January 31, 2019 1,170,000 April 30, 2019 1,485,000 August 31, 2019 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 660,000 June 30, 2018 520,000 October 1, 2018 620,000 January 31, 2019 360,000 April 30, 2019 675,000 August 31, 2019 1,080,000 On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT