Question

In: Economics

Consider Projects X and Y. Which project would you approve if a project must be selected?...

  1. Consider Projects X and Y. Which project would you approve if a project must be selected? The expected period of service is 15 years, and the interest rate is 10%. Calculate EUAW for both the projects and compare.

Project X

Project Y

Initial cost

$100,000

$150,000

Annual operating costs

30,000

20,000

Annual repair costs

10,000

6,000

Salvage value

10,000

20,000

Solutions

Expert Solution

Ans. Cash flows in,

Year 0 = - Initial Cost

=> For X = -$100000 and for Y = -$150000

Year 1-14 = -(Annual Operating cost+ Annual repair cost)

=> For X = -$40000 and for Y = -$26000

Year 15 = -(Annual Operating cost + Annual repair cost) + Salvage value

=> For X = -$30000 and for Y = -$6000

The present worth of X at 10% interest rate,

PWa = -100000 - 40000*(P/A, 10%, 14) - 26000*(P/F, 10%, 15)

=> PWa = -$401849.26

The present worth of Y at 10% interest rate,

PWb = -150000 - 26000*(P/A, 10%, 14) - 6000*(P/F, 10%, 15)

=> PWb = -$342970.23

For EUAW,

PWa = EUAWa * (P/A, 10%, 15)

=> EUAWa = -$52832.64

For EUAW,

PWb = EUAWb*(P/A, 10%, 15)

=> EUAWb = -$45091.59


Related Solutions

You must analyze two projects, X and Y. Each project costs $10,000, and the firm’s WACC...
You must analyze two projects, X and Y. Each project costs $10,000, and the firm’s WACC is 12%. The expected net cash flows are as follows: Project X Project Y 0 -$10,000 -$10,000 1 $6,500 $3,500 2 $3,000 $3,500 3 $3,000 $3,500 4 $1,000 $3,500 a. Calculate each project’s NPV, IRR, MIRR, payback, and discounted payback. b. Which project(s) should be accepted if they are independent? c. Which project(s) should be accepted if they are mutually exclusive? Hint: (Project-X IRR...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT?    a. The crossover rate must be greater than 10%. b. If the cost of capital...
Consider the following projects X and Y where the firm can choose only once. Project X...
Consider the following projects X and Y where the firm can choose only once. Project X costs $600 and has cash flows of $400 in each of the next two years. Project B also costs $ 600 and generates cash flows $500 and $275 for the next two years, respectively. Sketch a net present value profile (graphs) for each of these projects. For graphs you may use approximation Which project should the firm choose if the cost of capital is...
Consider the following projects, X and Y where the firm can only choose one. Project X...
Consider the following projects, X and Y where the firm can only choose one. Project X costs $1500 and has cash flows of $678, $652, $347, $111, $54, $16 in each of the next 6 years. Project Y also costs $1500, and generates cash flows of $738, $693, $405 for the next 3 years, respectively. WACC=9.5%. A) Draw the timelines for both projects: X and Y. B) Calculate the projects’ NPVs, IRRs, payback periods. C) If the two projects are...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0 −$552,600 −$521,000 1 217,700 207,400 2 227,600 217,200 3 234,800 225,100 4 194,500 185,900 What is the crossover rate for these two projects?
You are considering two projects with the following cash flows: Project Y Project X Year 1...
You are considering two projects with the following cash flows: Project Y Project X Year 1 $9,500 $6,000 Year 2 $9,000 $6,900 Year 3 $6,900 $9,000 Year 4 $6,000 $9,500 Which one of the following statements is true concerning the two projects given a positive discount rate? A. Project Y has both a higher present value and a higher future value than project X. B. Both projects have the same future value at the end of year 4. C. Project...
Consider the following two mutually exclusive projects X and Y: X Y Year 0 -$5,500 -$4,500...
Consider the following two mutually exclusive projects X and Y: X Y Year 0 -$5,500 -$4,500 Year 1 $3,000 $2,800 Year 2 $2,000 $2,000 Year 3 $2,000 $1,000 Year 4 $1,000 $1,000 What is the crossover rate for these two projects? Sketch the NPV profiles for X and Y (point out the IRR of each project and the crossover rate in the NPV profiles). The required return is 10%. Which project should be chosen?
which would evaluate to false? ((x&&!y ||z) || !z&&x) a. x and y are false b....
which would evaluate to false? ((x&&!y ||z) || !z&&x) a. x and y are false b. x and z are false c. z is false d. x y z are true e. x is false
You are ask to evaluate the following mutually exclusive projects, Project X which has an initial...
You are ask to evaluate the following mutually exclusive projects, Project X which has an initial cost of $5,060,000 and ten annual estimated net cash flows of $1,722,000 and Project Y which has an initial cost of $5,060,000 and five annual estimated cash flows of $2,079,000. Use two different standardized NPV methods to evaluate these projects at a cost of capital of 11 percent. (Please show all of your calculations).   Discuss the logic of each of these methods. Are they...
You need to consider two projects which have the following cash flows: Project A requires an...
You need to consider two projects which have the following cash flows: Project A requires an initial investment of $10,000 and will generate net cash flows of $5,000 at the end of year 1, $6,000 at the end of year 2, $7,000 at the end of year 3, and $8,000 at the end of year 4. At the end of year 2, maintenance costs of $8,000 will have to be disbursed. Project B requires an initial investment of $15,500 and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT