Question

In: Finance

Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...

  1. Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT?   

I know A is correct, but just would like to know the logic to it as I have no idea how the answer is A. Thanks.

Solutions

Expert Solution

Answer: Option A is correct.

Explanation:
The rate of return at which the net present value (or NPV) of two projects are equal, is referred to as the crossover rate.
Internal rate of return (or IRR) of project Y=17%
IRR of Project X=19%
So, IRR of project Y is less than the IRR of project X

IRR is the rate of return at which the NPV is zero, if we increase this rate of return, NPV will become negative because NPV=-Initial cash outflow+Present value of future cash inflows and this present present value is discounted using the cost of capital (return rate) and IRR is a case at which present values of future cash flows becomes equal to initial cash outflow.

So, at 19% rate of return, NPV of Project Y will become negative.

Given that, if the cost of capital is 10%, project Y has a higher NPV than project X.

For crossover rate, the NPV of both the projects should be equal and they will have same NPV when the rate lies between 10% and 19% because above this range NPV of project Y will become negative (move down) and at 10%, project Y will have higher (move up) NPV than project X.

So, as per the options given, the crossover rate must be greater than 10%.


Related Solutions

Consider Projects X and Y. Which project would you approve if a project must be selected?...
Consider Projects X and Y. Which project would you approve if a project must be selected? The expected period of service is 15 years, and the interest rate is 10%. Calculate EUAW for both the projects and compare. Project X Project Y Initial cost $100,000 $150,000 Annual operating costs 30,000 20,000 Annual repair costs 10,000 6,000 Salvage value 10,000 20,000
Consider the following two mutually exclusive projects.  Project A has an NPV of $0.5 billion, an IRR...
Consider the following two mutually exclusive projects.  Project A has an NPV of $0.5 billion, an IRR of 16% and a payback period of 4 years.  Project B has an NPV of $600 million, and IRR of 15% and a Payback period of 3 years. Which project should be chosen?
Consider the following two mutually exclusive projects X and Y: X Y Year 0 -$5,500 -$4,500...
Consider the following two mutually exclusive projects X and Y: X Y Year 0 -$5,500 -$4,500 Year 1 $3,000 $2,800 Year 2 $2,000 $2,000 Year 3 $2,000 $1,000 Year 4 $1,000 $1,000 What is the crossover rate for these two projects? Sketch the NPV profiles for X and Y (point out the IRR of each project and the crossover rate in the NPV profiles). The required return is 10%. Which project should be chosen?
Consider the following projects X and Y where the firm can choose only once. Project X...
Consider the following projects X and Y where the firm can choose only once. Project X costs $600 and has cash flows of $400 in each of the next two years. Project B also costs $ 600 and generates cash flows $500 and $275 for the next two years, respectively. Sketch a net present value profile (graphs) for each of these projects. For graphs you may use approximation Which project should the firm choose if the cost of capital is...
Consider the following projects, X and Y where the firm can only choose one. Project X...
Consider the following projects, X and Y where the firm can only choose one. Project X costs $1500 and has cash flows of $678, $652, $347, $111, $54, $16 in each of the next 6 years. Project Y also costs $1500, and generates cash flows of $738, $693, $405 for the next 3 years, respectively. WACC=9.5%. A) Draw the timelines for both projects: X and Y. B) Calculate the projects’ NPVs, IRRs, payback periods. C) If the two projects are...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0 −$552,600 −$521,000 1 217,700 207,400 2 227,600 217,200 3 234,800 225,100 4 194,500 185,900 What is the crossover rate for these two projects?
You are considering two projects with the following cash flows: Project Y Project X Year 1...
You are considering two projects with the following cash flows: Project Y Project X Year 1 $9,500 $6,000 Year 2 $9,000 $6,900 Year 3 $6,900 $9,000 Year 4 $6,000 $9,500 Which one of the following statements is true concerning the two projects given a positive discount rate? A. Project Y has both a higher present value and a higher future value than project X. B. Both projects have the same future value at the end of year 4. C. Project...
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000​ and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 9 percent. The expected annual free cash inflows from each project are in the popup​ window: Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted.   ...
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000 and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 12 percent. The expected annual free cash inflows from each project are in the popup​ window: .Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted. a....
Consider two mutually exclusive projects X and Y with identical initial outlays of $500,000 and useful...
Consider two mutually exclusive projects X and Y with identical initial outlays of $500,000 and useful lives of 5 years. Project X is expected to produce an after-tax cash flow of $150,000 each year. Project Y is expected to generate a single after-tax net cash flow of $1,015,000 in year 5. The discount rate is 15 percent. Calculate the net present value for each project. Calculate the IRR for each project. What decision should you make regarding these projects?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT