Question

In: Finance

Consider the following two mutually exclusive projects X and Y: X Y Year 0 -$5,500 -$4,500...

  1. Consider the following two mutually exclusive projects X and Y:

X

Y

Year 0

-$5,500

-$4,500

Year 1

$3,000

$2,800

Year 2

$2,000

$2,000

Year 3

$2,000

$1,000

Year 4

$1,000

$1,000

    1. What is the crossover rate for these two projects?
    1. Sketch the NPV profiles for X and Y (point out the IRR of each project and the crossover rate in the NPV profiles).
    2. The required return is 10%. Which project should be chosen?

Solutions

Expert Solution

The formulas and the inputs used is as follows:


The result is as follows:

a. The crossover rate is 7.13%

b. The IRR of each project and the crossover rate is depicted in the NPV profile.

c. If the required return is 10%, project Y should be selected based on NPV technique. Find the calculation in the above table.


Related Solutions

Consider the following two mutually exclusive projects:     Year Cash Flow (X) Cash Flow (Y) 0...
Consider the following two mutually exclusive projects:     Year Cash Flow (X) Cash Flow (Y) 0 –$ 19,400 –$ 19,400 1 8,700 9,800 2 8,800 7,650 3 8,650 8,550      Calculate the IRR for each project. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)     IRR   Project X %     Project Y %     What is the crossover rate for these two projects? (Do not round intermediate calculations. Enter your answer...
Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 –$...
Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 –$ 23,000 –$ 23,000 1 10,490 12,000 2 10,900 9,360 3 10,500 10,400 Calculate the IRR for each project. (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) What is the crossover rate for these two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g.,...
Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 –$...
Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 –$ 20,900 –$ 20,900 1 9,075 10,550 2 9,550 8,025 3 9,025 8,925 A) Calculate the IRR for each project B) What is the crossover rate for these two projects? C) What is the NPV of Projects X and Y at discount rates of 0 percent, 15 percent, and 25 percent?
Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 -$23,400...
Consider the following two mutually exclusive projects: Year Cash Flow (X) Cash Flow (Y) 0 -$23,400 -$23,400 1 $13,100 $9,200 2 $9,480 $10,620 3 $7,890 $11,180 Sketch the NPV profiles for X and Y over a range of discount rates from 0 to 25 percent. What is the crossover rate for these two projects?
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$ 364,000 –$ 52,000 1 46,000 25,000 2 68,000 22,000 3 68,000 21,500 4 458,000 17,500 Whichever project you choose, if any, you require a return of 11 percent on your investment. a-1. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)    a-2. If you apply the payback criterion, which...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$199,124        –$15,993          1 25,800        5,691          2 51,000        8,855          3 54,000        13,391          4 416,000        8,695             Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A?     b. What is the payback period for Project B? c. What is the discounted...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$ 360,000 –$ 45,000 1 35,000 23,000 2 55,000 21,000 3 55,000 18,500 4 430,000 13,600    Whichever project you choose, if any, you require a 14 percent return on your investment.    a-1 What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)    Payback period   Project A years     Project...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$260,730        –$15,011          1 27,800        4,942          2 56,000        8,023          3 55,000        13,040          4 426,000        9,138             Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A?     b. What is the payback period for Project B? c. What is the discounted...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$251,835        –$15,247          1 25,100        4,828          2 55,000        8,358          3 50,000        13,472          4 385,000        8,102             Whichever project you choose, if any, you require a 6 percent return on your investment. a.What is the discounted payback period for Project A? b.What is the discounted payback period for Project B?
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$251,835        –$15,247          1 25,100        4,828          2 55,000        8,358          3 50,000        13,472          4 385,000        8,102             Whichever project you choose, if any, you require a 6 percent return on your investment. a.What is the discounted payback period for Project A? b.What is the discounted payback period for Project B?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT