Question

In: Finance

You must analyze two projects, X and Y. Each project costs $10,000, and the firm’s WACC...

You must analyze two projects, X and Y. Each project costs $10,000, and the firm’s WACC is 12%. The expected net cash flows are as follows:
Project X Project Y
0 -$10,000 -$10,000
1 $6,500 $3,500
2 $3,000 $3,500
3 $3,000 $3,500
4 $1,000 $3,500

a. Calculate each project’s NPV, IRR, MIRR, payback, and discounted payback.
b. Which project(s) should be accepted if they are independent?
c. Which project(s) should be accepted if they are mutually exclusive?

Hint: (Project-X IRR = 17%, 18% : MIRR = 14.61%) (Project-Y IRR = 15%, 16% : MIRR = 13.73%)

solve the question step by step in proper format

Solutions

Expert Solution

Based on the given data, pls find below steps, workings and answers:

a. Calculate each project’s NPV, IRR, MIRR, payback, and discounted payback.

NPV of Project X is $ 966.01 and Project Y is $ 630.72

IRR of Project X is $ 18.03% and Project Y is $ 14.96% IRR of Project X is $ 14.61% and Project Y is $ 13.73%

Payback Period of Project X is 2.17 years and Project Y is 2.86 years Discounted Payback period of Proejct X is 2.85 years and Project Y is 3.72 years

b. Which project(s) should be accepted if they are independent?

If the projects are independent, both these projects can be accepted as both give Positive NPV and other positive factors like IRR, lower Payback periods.


c. Which project(s) should be accepted if they are mutually exclusive?

If the projects are mutually exclusive, Project X shoudl be accepted as the NPV of Proejct X is higher than Project Y; Also, Project X has lower payback period than Project Y and other factors like IRR, MIRR as well more healthier than Project Y.

Computation of IRR: This can be computed using formula in Excel = IRR("range of cashflows", discounting factor%);

Computation of MIRR: This can be computed using formula in Excel = MIRR("range of cashflows", discounting factor%, reinvestment factor%); Here, both discounting factor % and reinvestment factor% are considered same.

Computation of Net Present Value (NPV) based on the Discounted Cash flows; The Discounting factor is computed based on the formula: For year 0, the discounting factor is 1; For Year 1, it is computed as = Year 0 factor /(1+discounting factor%) ; Year 2 = Year 1 factor/(1+discounting factor %) and so on;

Next, the cashflows need to be multiplied with the respective years' discounting factor, to arrive at the discounting cash flows;

The total of all the discounted cash flows is equal to its respective Project NPV of the Cash Flows;

Computation of Normal / Discounted Pay Back Period: Here, the period is computed for each project, based on cumulative normal /discounted cash flows: If the cumulative value is less than or equal to zero, the period is considered as 12 months (it means that the net cumulative cash flow has not yet paid back the initial investment); Once the value turns positive in a particular year, the period for such year is observed at a proportion of actual discounted cash flow to the cumulative CF; This gives the period less than 12 months in such year; Once this is computed, total of all the years is taken and divided by 12, to arrive at the Payback period in no.of years.


Related Solutions

Consider Projects X and Y. Which project would you approve if a project must be selected?...
Consider Projects X and Y. Which project would you approve if a project must be selected? The expected period of service is 15 years, and the interest rate is 10%. Calculate EUAW for both the projects and compare. Project X Project Y Initial cost $100,000 $150,000 Annual operating costs 30,000 20,000 Annual repair costs 10,000 6,000 Salvage value 10,000 20,000
There are two projects that the company is considering: Project A costs 10,000 to implement today,...
There are two projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,900 at the end of year 1; 2,000 at the end of year 2; 5,000 at the end of year 3. Project B's initial cost is 7,500, and subsequent cash flows are 5,000 per year for 3 years. WACC is 8% for both projects. Calculate NPV and IRR for each project, and decide which to recommend.
There are two projects that the company is considering: Project A costs 10,000 to implement today,...
There are two projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,000 at the end of year 1; 4,000 at the end of year 2; 6,000 at the end of year 3. Project B's initial cost is 12,000, and subsequent cash flows are 6,000 per year for 3 years. WACC is 8% for both projects. a. Calculate NPV and IRR for each project, and decide which one to...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0 −$552,600 −$521,000 1 217,700 207,400 2 227,600 217,200 3 234,800 225,100 4 194,500 185,900 What is the crossover rate for these two projects?
You are considering two projects with the following cash flows: Project Y Project X Year 1...
You are considering two projects with the following cash flows: Project Y Project X Year 1 $9,500 $6,000 Year 2 $9,000 $6,900 Year 3 $6,900 $9,000 Year 4 $6,000 $9,500 Which one of the following statements is true concerning the two projects given a positive discount rate? A. Project Y has both a higher present value and a higher future value than project X. B. Both projects have the same future value at the end of year 4. C. Project...
The Radford Company is faced with two mutually exclusive investment projects. Each costs $10,000 and each...
The Radford Company is faced with two mutually exclusive investment projects. Each costs $10,000 and each has an expected life of three years. Annual net cash flows from each project begin one year after the initial investment is made and have the following probability distribution. Project A: Probability .3 .5 .2 Cash Flows 5,000 6,000 7,000 Project B: Probability .25 .6 .15 Cash Flows 2,000 5,000 8,000 The Radford company evalutes project A at 10% and project B at 12%...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT?    a. The crossover rate must be greater than 10%. b. If the cost of capital...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X. Years 0 1 2 3 Project X cash flows -$100 80 60 40 And the following information is available regarding Projects Y and Z. Criteria Project Y Project Z NPV $40 $67 MIRR 10% 20% IRR 2.0% 18.7% Regular Payback 2.23 years 1.77 years 5) Assuming the three projects X, Y & Z are...
ompany B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...
ompany B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X. Years 0 1 2 3 Project X cash flows -$100 80 60 40 And the following information is available regarding Projects Y and Z. Criteria Project Y Project Z NPV $40 $67 MIRR 10% 20% IRR 2.0% 18.7% Regular Payback 2.23 years 1.77 years 9) If IRR for Project X is 17.95%, and the...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $7,500...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $7,500 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $7,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 7,500 0.2 15,000 BPC has decided to evaluate the riskier project at a 11% rate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT