Question

In: Economics

A. An equipment installation job in the completion stage can be completed in 40 days of...

A. An equipment installation job in the completion stage can be completed in 40 days of 8 hour day work, with 40 men working. With the contract expiring in 30 days, the mechanical engineer contractor decided to add 10 men on the job, overtime not being permitted. If the liquidated damages is $2,000 per day of delay, and the men are paid $80 per day, will the engineer be able to complete the job on time? How much should he save money with the addition of workers?

B. An 8-m wide concrete road pavement 500 meters long is desired to be constructed over a well-compacted gravel road, together with the necessary concrete curbs and gutters on both sides. In order to put the subgrade on an even level grade, a 500 cu. m. of sand filling is necessary, over which the 10-inch concrete pavement will be placed. How much will the project cost, allowing for 15% contingency and assuming the following data?
(a.) Sand fill, including rolling and watering – $10 per cu.m.
(b.) Concrete curb and gutter (labor and materials) – $12 per linear meter
(c.) Concrete pavement, 10 in. thick (labor and materials), including curing – $22 per sq.m.

C. Seawater contains 2.1 pounds of magnesium per ton. By using the processing method A, 85% of the metal can be recovered at a cost of $3.25 per ton of water pumped and processed. If process B is used only 70% of the available metal is recovered, at a cost of only $2.60 per ton of water pumped and processed. The two processes are substantially equal as to investment costs and time requirements. If the extracted material can be sold for $2.40 per pound, which processing method should be used?

Solutions

Expert Solution

Answer:

A. 40 men can complete a job in 40 days means each worker per day is completing 1/(40*40)=1/1600 of job.

50 men can complete this job in 32 days(50*32=1600).

But there is penalty of $2000 per day. So if 10 extra workers are not employed then the penalty would have been $20,000. With employing 10 additional workers penalty is $4000 for 2 days delay.

With addition of 10 workers, additional workers are paid $80*32*10=$25600. While saving of 8 days of work of 40 workers=$80*40*8=$25600. So extra cost incurred by employing extra labor is saved by reducing work days by 8.

Engineer was not able to complete job in 30 days(completed in 32 days). Employing extra labor saved $16000 of penalty($20000-$4000).

B.

(a) Cost of sandfill= $10/cum*500 cum.=$5000.

(b) Concrete curb and gutter=$12/linear metre*500 metre=$6000.

(c) Concrete pavement 10 inch thick=$22/sqm.*4000sqm.(8m wide*500m long)=$88000.

Total cost of project=$101000+15%of 101000 for contingency=$116150.

C.

Price of magnesium extracted using method A=2.1 pound*85%*$2.40=$4.284.

Cost of using method A=$3.25 per ton.

Profit by using Method A=$4.284-$3.25=$1.034.

Price of magnesium extracted using method B=2.1 pound*70%*$2.40=$3.528

Cost of using method B=$ 2.60 per ton.

Profit by using method B=$3.528-$2.6=$0.928.

Method A should be used because it is giving higher profit.


Related Solutions

The equipment cost (equipment plus shipping and installation) can be depreciated at the rate of 21%...
The equipment cost (equipment plus shipping and installation) can be depreciated at the rate of 21% in the first year. For the remaining 5 years (years 2-6) the depreciation will be equal to $30,000 per year. What is the amount of depreciation in year 1?
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $12 per unit and 900 units for Job 42 at $18 per unit. During August, Prichard Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 500 units for Job 40 at $18 per unit and 900 units for Job 42 at $14 per unit. During August, Prichard Company accumulated 500 hours of direct labor costs on Job 40...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 700 units for Job 40 at $16 per unit and 900 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 800 units for Job 40 at $10 per unit and 1,500 units for Job 42 at $20 per unit. During August, Ingram Company accumulated 800 hours of direct labor costs on Job 40...
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42....
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,200 units for Job 42 at $24 per unit. During August, Ingram Company accumulated 200 hours of direct labor costs on Job...
A company purchased new equipment for $270,000 including installation. The company estimates that the equipment will...
A company purchased new equipment for $270,000 including installation. The company estimates that the equipment will have a residual value (salvage value) of $24,000 and estimates it will use the machine for six years or about 12,000 total hours. Prepare a depreciation schedule for three years using the following methods: Straight line Activity based Actual use per year was as follows: Year Hours Used 1 3,100 2 1,100 3 1,200 2. Assume the equipment was purchased on August 1. What...
Rover Company, a public company, manufactures equipment and also provides installation services. The installation process does...
Rover Company, a public company, manufactures equipment and also provides installation services. The installation process does not involve changes to the features of the equipment to perform specifications. Rover has the following relationship with Canine Inc.: • Canine decides to purchase equipment from Rover and contracts with Rover to install the equipment for a total price of $420,000. If Canine only purchased the equipment from Rover, the price would be $400,000 • Canine contacts another company and determines installation service...
A tasks completion time is normally distributed with a mean of 200 work days and a...
A tasks completion time is normally distributed with a mean of 200 work days and a SD of 10 work days. What is the probability that: (a) The task finishes within 185 work days. (b) The task takes longer than 212 work days (c) In order to be 99% sure that the task will not be completed late, the contractor must request a completion time of _______ days
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity duration (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many feeder buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ Options: 0 1 2 3
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT