Question

In: Accounting

Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...

Job Costs

At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units.

The following data relate to these two jobs:

On August 4, raw materials were requisitioned for production as follows: 500 units for Job 40 at $18 per unit and 900 units for Job 42 at $14 per unit.

During August, Prichard Company accumulated 500 hours of direct labor costs on Job 40 and 1,200 hours on Job 42. The total direct labor was incurred at a rate of $16 per direct labor hour for Job 40 and $14 per direct labor hour for Job 42.

The predetermined factory overhead rate is $5.00 per direct labor hour.

a. Determine the balance on the job cost sheets for Jobs 40 and 42 at the end of August.

Job 40 $
Job 42 $

b. Determine the cost per unit for Jobs 40 and 42 at the end of August. If required, round your answers to the nearest cent.

Job 40 $
Job 42 $

Solutions

Expert Solution

Solution a:

Balance for Job 40 = Direct material + diract labor + factory overead applied

= (500*$18) + (500*$16) +(500*$5)

= $19,500

Balance for Job 42 = (900*$14) + (1200*$14) + (1200*$5)

= $35,400

Solutin b:

Cost per unit for Job 40 = $19500/ 200 = $97.50

Cost per unit for Job 42 = $35400 /500 = $70.80


Related Solutions

Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $12 per unit and 900 units for Job 42 at $18 per unit. During August, Prichard Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 700 units for Job 40 at $16 per unit and 900 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 200 hours of direct labor costs on Job 40...
Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 800 units for Job 40 at $10 per unit and 1,500 units for Job 42 at $20 per unit. During August, Ingram Company accumulated 800 hours of direct labor costs on Job 40...
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42....
5.0 Job Costs At the end of August, Ingram Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,200 units for Job 42 at $24 per unit. During August, Ingram Company accumulated 200 hours of direct labor costs on Job...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job 200 is for 2,390 units, and Job 305 is for 2,053 units. The following data relate to these two jobs: On May 7, Bergan Company purchased on account 10,000 units of raw materials at $8 per unit. During May, raw materials were requisitioned for production as follows: 7,500 units for Job 200 at $8 per unit and 1,480 units for Job 305 at $5...
At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job...
At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information: JobDirect MaterialsDirect LaborMachine Hours Job 765$10,920              $3,276        39 Job 76614,706              4,644        86 Job 765 produced 234 units, and Job 766 consisted of 344 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $135 per hour. a. Determine the balance on the job cost sheets for each job. Job 765$ Job 766$ b. Determine the...
At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is...
At the end of April, Cavy Company had completed Job 766 and 765. Job 766 is for 675 units, and Job 765 is for 900 units. According to the individual job cost sheets the information is as follows: Job Direct Materials Direct Labor Machine Hours Job 765 $5,670 $3,500 27Job 766  $8,900  $4,775  44Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job,...
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,180. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,610 $2,520 102 3,180 3,400 103 2,110 1,660 104 7,150 6,250 105 4,540 4,760 106 3,310 3,020 For general factory use 890 3,730 Factory overhead costs incurred on account, $4,990....
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,700 Materials requisitioned and factory labor used: Job No.MaterialsFactory Labor 101$2,660 $1,870 1023,250 2520 1032,150 1,230 1047,290 4,640 1054,630 3,530 1063,380 2,240 For general factory use900 2,770 Factory overhead costs incurred on account, $5,080. Depreciation of machinery and equipment, $1,330. The factory overhead...
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,700 Materials requisitioned and factory labor used: Job No.MaterialsFactory Labor 101$2,660 $1,870 1023,250 2520 1032,150 1,230 1047,290 4,640 1054,630 3,530 1063,380 2,240 For general factory use900 2,770 Factory overhead costs incurred on account, $5,080. Depreciation of machinery and equipment, $1,330. The factory overhead...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT