Question

In: Accounting

Analyze the following costs and measures of activity in Snowtown, USA that are listed below in this table.

 

Analyze the following costs and measures of activity in Snowtown, USA that are listed below in this table. Each one of the costs must be classified as a variable cost or as a fixed cost for this particular analysis of cost behavior. There is only to be one answer in the Cost Behavior column -- either variable or fixed.  

VERY IMPORTANT: There is only one final correct answer to each item in this list , so make sure you only type the word “variable” in the column, when that is your final answer to an item, or only type the word “fixed” in the column for an item if that is your final answer.

Item

Cost
Description

Measure
of Activity

Cost Behavior
(Enter: Variable or Fixed)

1.

Cost of vaccine used at a clinic

Vaccines administered

 

2.

Building rent at a taco shop

Dollar sales

 

3.

Salary of production manager at a snowboard manufacturer

Snowboards produced

 

4.

Cost of electricity for production equipment at a snowboard manufacturer

Snowboards produced

 

5.

Ferry captain's salary on a regularly scheduled passenger ferry

Number of passengers

 

6.

Cost of glue used in furniture production

Units produced

 

7.

Janitorial wages at a snowboard manufacturer

Snowboards produced

 

8.

Depreciation on factory building at a snowboard manufacturer

Snowboards produced

 

9.

Cost of advertising at a snowboard company

Snowboards sold

 

10.

Cost of shipping bags of fertilizer to a customer at a chemical plant

Bags shipped

 

Question 3: a) Provide a definition for variable costs, and then explain how managers use variable costs to enable more effective decision making. Enter your final answer to this particular item in the space below this sentence.

Question 3: b) Provide a definition for fixed costs, and then explain how managers use fixed costs to inform decision making processes. Enter your final answer to this particular item in the space below this sentence.

Question 3: c) Analyze the information in this table and determine the correct cost behavior classification for each one of the separate items included in this list. Enter your final answer in the third column of the table for each separate item to indicate whether the cost is mainly a fixed cost or a variable cost with respect to the measure of activity listed next to it. This means the cost behavior category is either a variable cost or a fixed cost, and not both.

Solutions

Expert Solution

3a. Variable costs are those costs which varies with the change in production of goods in a company. It can be increased or decreased by increasing or decreasing the number of units producd or sold.

Variable costs are useful in decision making since managers can decide whether to continue using any cost activity by determining whether such activity could be performed in house of outsourced from any other organisation for cost reduction purpose.

3b. Fixed costs are those costs that will be incurred irrespective of the amount of goods produced. Like- depreciation, salary, etc which shall be incurred irrespective of goods produced.

3c.

Item Cost Description Measure of activity Cost behaviour
( Variable or Fixed)
1 Cost of vaccine used at a clinic Vaccines administered Variable cost
(since it is vaccine is dependent upon the number of patients)
2 Building rent at a taco shop Dollar sales Fixed cost
3 Salary of production manager at a snowboard manufacturer Snowboards produced Fixed cost
( since salary is regular in nature)
4 Cost of electricity for production equipment at a snowboard manufacturer Snowboards produced Variable cost
5 Ferry captain's salary on a regularly scheduled passenger ferry Number of passengers Variable cost
(since it is depnedent upon the number of passengers travelled)
6 Cost of glue used in furniture production Units produced Variable cost
7 Janitorial wages at a snowboard manufacturer Snowboards produced Fixed Cost
8 Depreciation on factory building at a snowboard manufacturer Snowboards produced Fixed Cost
9 Cost of advertising at a snowboard company Snowboards sold Fixed Cost
10 Cost of shipping bags of fertilizer to a customer at a chemical plant Bags shipped Variable cost

Related Solutions

Use the technology​ display, which results from measures of​ self-esteem listed in the table below. The...
Use the technology​ display, which results from measures of​ self-esteem listed in the table below. The data are from a project to study how levels of​ self-esteem in subjects relate to their perceived​ self-esteem in other target people who were described in writing. The test here works well even though the data are at the ordinal level of measurement. Assume that​ self-esteem measurements are not affected by an interaction between subject​ self-esteem and target​ self-esteem. Is there sufficient evidence to...
The table below presents durations, direct costs and immediate predecessors for each activity of a project...
The table below presents durations, direct costs and immediate predecessors for each activity of a project executed by a contracting company, under both normal and crash conditions. The weekly indirect cost is L.E. 40. Activity Code Immediate Predecessors Normal Duration (week) Normal Total Direct Cost (L.E) Crash Duration (Week) Crash Total Direct Cost (L.E) Total Allowable crash Time (Week) Cost Slope per Week (L.E) A None 8 325 5 400 3 25 B None 12 1200 11 1320 1 120...
Below is a table of the growth of the Corona Virus in USA and the requests...
Below is a table of the growth of the Corona Virus in USA and the requests for masks. date corona cases #of masks req in millions 3/22/2020 32 2 3/23/2020 42 4 3/24/2020 52 8 3/25/2020 64 12 3/26/2020 81 20 3/27/2020 101 30 3/28/2020 121 40 3/29/2020 140 60 3/30/2020 160 90 3/31/2020 186 110 4/1/2020 212 120 4/2/2020 241 200 4/3/2020 273 300 Using causal with masks being the dependent variable. Generate a forecast for the number of...
Review the following and then analyze the conditions listed below and present how these conditions should...
Review the following and then analyze the conditions listed below and present how these conditions should be dealt with as claims to an Owner, that is what types of money cost/delay, etc., should be submitted as requests for change orders or claims: Base contact- $77,000,000 to build a twenty story building Contract schedule: complete in 300 days Liquidated damages = $7000/day Owner issued notice to proceed and contractor started work on September 9, 2013 Contractor could not access site due...
Production Inc. uses activity based costing. The following estimated activity costs are identified in the table...
Production Inc. uses activity based costing. The following estimated activity costs are identified in the table below. In addition, they have two product lines, A100 and B100. Activity Cost Cost Driver A100 B100 Cost allocation base Setup $85,600 # of setups 1,600 1,750 16,000 Handling $136,500 # of parts 1,480 360 65,000 Assembly $126,000 Direct Labor Hours 800 365 5,000 Total $348,100 Summary of prime costs: A100 B100 Direct materials $16,000 $9,500 Direct labor $13,400 $12,700 Calculate the unit cost...
Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity...
Activity rates from Quattrone Corporation's activity-based costing system are listed below. The company uses the activity rates to assign overhead costs to products:   Activity Cost Pools Activity Rate   Processing customer orders $95.88 per customer order   Assembling products $2.76 per assembly hour   Setting up batches $53.30 per batch Last year, Product F76D involved 3 customer orders, 496 assembly hours, and 27 batches. How much overhead cost would be assigned to Product F76D using the activity-based costing system? Multiple Choice $1,439.10 $3,095.70...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 0.5 1 B --- 1 1 C A,B 1 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". Please indicate the schedule of acitivity B after leveling recources (Suppose the project begins on day...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor...
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 1 1 B --- 1 1 C A,B 0.5 1 D C 1 1 Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". How much slack time (in days) does acitivity C have after leveling recources?
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor...
Use the project description presented in the table below for the following questions: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 9 15 F D 4 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 5 5 5 Calculate the...
Assume that the transactions listed in the first column of the table below are anticipated by...
Assume that the transactions listed in the first column of the table below are anticipated by U.S. firms that have no other foreign transactions. Place an “X” in the table wherever you see possible ways to hedge the transaction exposure. Forward Contract Futures Contract Options Contract Long Short Long Short Call Put a. A Inc. plans to sell goods to Portugal, denominated in euro b. B Co. will import automobiles from Germany, denominated in euro c. C Corp has a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT