Review the following and then analyze the conditions listed below and present how these conditions should be dealt with as claims to an Owner, that is what types of money cost/delay, etc., should be submitted as requests for change orders or claims:
Hi,
Solution as follows:
Since the cost request was accepted by the owner, contractor needs to claim again for the extra time request. This can be requested in the form of a request letter by listing chronological events as below:
To,
Name of Owner__________
Address________________
Project_________________
Subject –Approval of Extra time for the project
Sir,
Reference to the above subject, we have following submissions with respect to above said project:
From above point number 3, 4 and 6 it is extracted that more than 4.5 months of precious time has been already elapsed due to the reasons beyond control of contractor.
Due to this delay, timely completion of project may also be extended. However we have estimated the revised project duration by planning additional efforts during execution and it is found to be at least three months.
In view of above it is requested to approve the time extension of three months.