Question

In: Accounting

Activity-Based Management, Non-Value-Added Costs, Target Costs, Kaizen Costing Joseph Hansen, president of Electronica, Inc., was concerned...

Activity-Based Management, Non-Value-Added Costs, Target Costs, Kaizen Costing Joseph Hansen, president of Electronica, Inc., was concerned about the end-of-the-year marketing report that he had just received. According to Kylee Hepworth, marketing manager, a price decrease for the coming year was again needed to maintain the company's annual sales volume of integrated circuit boards (CBs). This would make a bad situation worse. The current selling price of $27 per unit was producing a $3-per-unit profit—half the customary $6-per-unit profit. Foreign competitors keep reducing their prices. To match the latest reduction would reduce the price from $27 to $21. This would put the price below the cost to produce and sell it. How could the foreign firms sell for such a low price? Determined to find out if there were problems with the company's operations, Joseph decided to hire Carsen Hepworth, a well-known consultant and brother of Kylee, who specializes in methods of continuous improvement. Carsen indicated that he felt that an activity-based management system needed to be implemented. After three weeks, Carsen had identified the following activities and costs: Batch-level activities: Setting up equipment 187,500 Materials handling 270,000 Inspecting products 183,000 Product-sustaining activities: Engineering support 180,000 Handling customer complaints 150,000 Filling warranties 255,000 Storing goods 120,000 Expediting goods 112,500 Unit-level activities: Using materials 750,000 Using power 72,000 Manual insertion labora 375,000 Other direct labor 225,000 Total costs $2,880,000b aDiodes, resistors, and integrated circuits are inserted manually into the circuit board. bThis total cost produces a unit cost of $24 for last year’s sales volume. Carsen indicated that some preliminary activity analysis shows that per-unit costs can be reduced by at least $10.50. Since Kylee had indicated that the market share (sales volume) for the boards could be increased by 50 percent if the price could be reduced to $18, Joseph became quite excited. Required: 1. Compute the cost savings per unit that would be realized if these costs were eliminated. If required, round your answer to the nearest cent. $ per unit 2. Compute the target cost required to maintain current market share, while earning a profit of $6 per unit. $ per unit Now, compute the target cost required to expand sales by 50 percent. $ per unit How much cost reduction would be required to achieve each target? Cost reduction to maintain $ per unit Cost reduction to expand $ per unit 4. Assume that Carsen suggested that kaizen costing be used to help reduce costs. The first suggested kaizen initiative is described by the following: switching to automated insertion would save $90,000 of engineering support and $135,000 of direct labor. Now, what is the total potential cost reduction per unit available? If required, round your answer to the nearest cent. $ per unit 5. Calculate income based on current sales, prices, and costs. Sales $ per unit Costs per unit Income $ per unit Now, calculate the income using a $21 price and an $18 price, assuming that the maximum cost reduction possible is achieved (including Requirement 4's kaizen reduction). Income $21 price $ per unit $18 price $ per unit What price should be selected? $18 price

Solutions

Expert Solution

1. Computation of Cost savings per unit

At present cost per unit = present selling price - profit per unit

= 27 -3

=24

proposed cost reduction = 10.5 per unit

reduced price to be fixed to earn same profit to match competition = 21

cost per unit on reduced price =21-3 = 18

savings in cost = old cost - new cost

=24 - 18

=6 per unit

2.computation of target cost required to maintain current market share, while earning a profit of $6 per unit

new sales price = $21

less: target profit =$6

Target Cost =$15 per unit

cost to be reduced to achieve target = old cost - new cost

=$24 - $15

=$9

3.computation of arget cost required to expand sales by 50 percent.

Targeted salling price per unit = $18

less: present profit    =$3

Target Cost =$15

cost to be reduced to achieve target = old cost - new cost

=$24 - $15

=$9

4. potential cost reduction per unit if kaizen costing method applied.

Total cost = $2,880,000

per unit cost as per last year = $24

So, number unit sold last year =2880000 / 24

=120,000 units

cost reduction due to kaizen costing

engineering support =$90,000

direct labor =$135,000

Total cost reduction =$225,000

reduced cost = $2,880,000 - $225,000

=$2,655,000

New cost per unit = reuced cost / number of unit sold

=$2,655,000 / 120,000 units

=$ 22.13 (round off)

reduction in cost due to kaizen costing = $24 - $22.13

=$1.87

5.Calculation of income based on current sales, prices, and costs

PARTICULERS UNITS AMOUNTS ($)
sales price 27
less: cost per unit 24
profit 3
units sold 120000
total income 360,000

calculation of the income using $21 price and $18 price

Particulers Sales Units Amount Sales Units Amounts
Price 21 18
less: cost * 11.63 11.63
profit 9.37 6.37
units sold 120000 180000
Total Income $1,124,400 $1,146,600

* Cost = 24 - 10.5(cost reduction) - 1.87(kaizen reduction)

=$11.63

IT IS ADVISED TO FIX PRICE 18 SO THAT COMPANY CAN EARN $22200 MORE PROFIT THAN PRICE 21


Related Solutions

“Differentiate Between Value-Added and Non-Value-Added activities? What are two advantages and two criticisms of activity-based costing?...
“Differentiate Between Value-Added and Non-Value-Added activities? What are two advantages and two criticisms of activity-based costing? Comment, Why ABC and ABM is Necessary in Manufacturing Entity? Explain Few Reasons.”
Problem Three NON-VALUE-ADDED COSTS, ACTIVITY COSTS, ACTIVITY COST REDUCTION (LO 4) John Thomas, vice president of...
Problem Three NON-VALUE-ADDED COSTS, ACTIVITY COSTS, ACTIVITY COST REDUCTION (LO 4) John Thomas, vice president of Mallett Company (a producer of a variety of plastic products), has been supervising the implementation of an ABC management system. One of John's objectives is to improve process efficiency by improving the activities that define the processes. To illustrate the potential of the new system to the president, John has decided to focus on two processes: production and customer service. Within each process, one...
Explain the difference between a value-added activity and a non-value added activity.
Explain the difference between a value-added activity and a non-value added activity.
Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made...
Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made machine parts. Maquina recently has implemented an activity-based management (ABM) system with the objective of reducing costs. Maquina has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred...
Production Inc. uses activity based costing. The following estimated activity costs are identified in the table...
Production Inc. uses activity based costing. The following estimated activity costs are identified in the table below. In addition, they have two product lines, A100 and B100. Activity Cost Cost Driver A100 B100 Cost allocation base Setup $85,600 # of setups 1,600 1,750 16,000 Handling $136,500 # of parts 1,480 360 65,000 Assembly $126,000 Direct Labor Hours 800 365 5,000 Total $348,100 Summary of prime costs: A100 B100 Direct materials $16,000 $9,500 Direct labor $13,400 $12,700 Calculate the unit cost...
Hansen Company uses activity-based costing.  The factory overhead budget for the coming period is $1,053,000, consisting of...
Hansen Company uses activity-based costing.  The factory overhead budget for the coming period is $1,053,000, consisting of the following: Cost Pool Budgeted Amount Supervision $320,000 Machine usage 420,000 Machine setups 187,000 Design changes 126,000 Totals $1,053,000 The potential allocation bases and their estimated amounts were as follows: Allocation Base Budgeted Amount Number of design changes 35 Number of setups 110 Machine hours 6,000 Direct labor hours 10,000 a.       What is the reason behind the difference in the costs of the job...
Activity Cost Pools, Activity Rates, and Product Costs using Activity-Based Costing Caldwell Home Appliances Inc. is...
Activity Cost Pools, Activity Rates, and Product Costs using Activity-Based Costing Caldwell Home Appliances Inc. is estimating the activity cost associated with producing ovens and refrigerators. The indirect labor can be traced into four separate activity pools, based on time records provided by the employees. The budgeted activity cost and activity-base information are provided as follows: Activity Activity Pool Cost Activity Base Procurement $12,600 Number of purchase orders Scheduling 90,000 Number of production orders Materials handling 11,000 Number of moves...
Part 3: Activity-Based Costing Banquet Services uses activity-based costing to compute the costs of their catered...
Part 3: Activity-Based Costing Banquet Services uses activity-based costing to compute the costs of their catered parties. Each party is limited to 40 guests and requires five people to serve and clean up. Two types of parties, an afternoon picnic and an evening formal dinner, are offered. The breakdown of the costs follows: Activities (and cost drivers) Afternoon Picnic Formal Dinner Advertising (parties) $175 per party $100 per party Planning (parties) $50 per party $75 per party Renting equipment $75...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT