Question

In: Accounting

The following budgeted information is available for Zeta Company: Activity Budgeted Cost Activity Driver Consumption of...

The following budgeted information is available for Zeta Company:

Activity

Budgeted Cost

Activity Driver

Consumption of Drivers for Zeta’s Product Lines

Total Activity Driver

Product A

Product B

Processing & Testing

Developing test programs

$400,000

Engineering hours

10,000

2,500

7,500

Making probe cards

58,750

Development hours

4,000

400

3,600

Testing products

300,000

Test hours

20,000

2,000

18,000

Setups

40,000

Number of batches

100

55

45

Engineering design

80,000

Number of change orders

60

9

51

Handling lots

90,000

Number of moves

200

110

90

Subtotal, Processing & Testing

$968,750

Procurement

Purchasing materials

450,000

Number of purchase orders

2,500

500

2,000

Unloading materials

60,000

Number of deliveries

3,000

600

2,400

Inspecting materials

75,000

Inspection hours

5,000

3,500

1,500

Moving materials

30,000

Distance moved (feet)

3,000

2,100

900

Paying suppliers

66,250

Number of invoices

1,250

250

1,000

Subtotal, Procurement

681,250

Total

$1,650,000

1. Assume the company currently uses departmental rates for allocating overhead. Calculate the pre-determined overhead rate for the Processing & Testing Department (based on Engineering hours) and the Procurement Department (based on Number of purchase orders). Round to three (3) places after the decimal.

2.   Identify which activity cost pools can be combined.

3. After combining cost pools as appropriate, calculate the pre-determined overhead rates for each activity cost pool.

4. Calculate the cost of Product line A using the departmental rates calculated in #1.

5. Calculate the cost of Product line A using the ABC rates calculated in #3.

6. Is ABC better for Zeta Company? Why or why not?

Solutions

Expert Solution

1.

Pre-determined overhead rate for the Processing & Testing Department

= Total fixed overhead / Total engineering hours

= 968750 / 10000

= 96.875 per engg hour

Pre-determined overhead rate for Procurement Department

= Total fixed overhead / Number of purchase orders

= 681250 / 2500

= 272.50 per purchase order

2.

Following cost pools can be combined:

Setups These two have cost drivers of Product A & B in the ratio of 9:11 COST POOL 1
Handling lots
Making probe cards These two have cost drivers of Product A & B in the ratio of 1:9 COST POOL 2
Testing products
Purchasing materials These three have cost drivers of Product A & B in the ratio of 1:4 COST POOL 3
Unloading materials
Paying suppliers
Inspecting materials These two have cost drivers of Product A & B in the ratio of 7:3 COST POOL 4
Moving materials

3.

Cost Pools Total Cost Ratio Total Driver Cost Driver Rate
COST POOL 1 $1,30,000.00 9:11 300 $433.333
COST POOL 2 $3,58,750.00 1:9 24000 $14.948
COST POOL 3 $5,76,250.00 1:4 6750 $85.370
COST POOL 4 $1,05,000.00 7:3 8000 $13.125
Developing test programs $4,00,000.00 1:3 10000 $40.000
Engineering design $80,000.00 3:17 60 $1,333.333

4. Cost of Product line A using the ABC rates

Cost Pools Cost Driver Rate Cost Drivers Total Cost
COST POOL 1 $433.333 165 $71,500.000
COST POOL 2 $14.948 2400 $35,875.000
COST POOL 3 $85.370 1350 $1,15,250.000
COST POOL 4 $13.125 4600 $60,375.000
Developing test programs $40.000 2500 $1,00,000.000
Engineering design $1,333.333 9 $12,000.000
Total $395,000

5.

Overhead Cost of A using traditional Approach = (98.875 * 2500) + (272.50 * 500) = $383,438

Overhead Cost of A using ABC Approach = $395,000

Since there is a difference in both approaches, it is better to use ABC approach. The main reason being ABC approach is said to be more accurate in allocation of overhead costs among products.


Related Solutions

The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $77,385 $150,000 3,300 labor hours Correspondence $9,585 $26,000 2,700 letters Account billing $171,500 $79,000 2,450,000 lines Payment verification $12,980 $78,000 22,000 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $225,403 3,220 labor hours Correspondence $35,231 2,650 letters Account...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $79,200 $156,000 3,200 labor hours Correspondence $9,639 $22,000 2,700 letters Account billing $144,000 $77,000 2,400,000 lines Payment verification $12,095 $80,000 20,500 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $234,023 3,140 labor hours Correspondence $31,154 2,550 letters Account...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Statement inquiry $73,888 $166,000 3,200 labor hours Correspondence $9,604 $27,000 2,800 letters Account billing $130,000 $70,000 2,600,000 lines Payment verification $11,825 $77,000 21,500 accounts In September, actual total costs and activity were as follows: Activity Center Total Costs Driver Amount Statement inquiry $241,803 3,240 labor hours Correspondence $36,377 2,660 letters Account...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $76,416 $150,000 3,200 labor hours Correspondence $10,063 $24,000 2,900 letters Account billing $182,000 $82,000 2,600,000 lines Bill verification $10,750 $79,000 21,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $224,331 3,080 labor hours Correspondence $34,101 2,990 letters Account billing...
The following is total monthly budgeted cost and activity information for the four activity centers in...
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center Variable Fixed Cost Driver Account inquiry $82,926 $167,000 3,400 labor hours Correspondence $9,396 $25,000 2,700 letters Account billing $147,000 $88,000 2,450,000 lines Bill verification $11,890 $77,000 20,500 accounts In September, actual costs and activity were as follows: Activity Center Total Costs Driver Amount Account inquiry $252,913 3,540 labor hours Correspondence $34,868 2,630 letters Account billing...
The following budgeted information is available:                                         ...
The following budgeted information is available:                                                         X-Rays   Ultrasound   CT Scan   MRI   Total       Technician Labour   $61,440   $105,600   $96,000   $105,000   $368,040       Depreciation   $32,240   $268,000   $439,000   $897,500   $1,636,740       Materials   $22,080   $16,500   $24,000   $31,250   $93,830       Administration                   $20,610       Maintenance                   $247,320       Sanitation                   $196,180       Utilities                   $134,350       Totals   $115,760   $390,100  ...
2) Gable Company uses three activity cost pools. Each pool has a cost driver. Information for...
2) Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 380,120 Number of machine hours 88,400 Designing costs 86,400 Number of design hours 9,000 Setup costs 74,672 Number of batches 525 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Product A Product B Product C Number of machine hours...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 259,000 Number of machine hours 85,600 Designing costs 59,000 Number of design hours 7,800 Setup costs 72,000 Number of batches 370 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Activity Rate Machining per Machine Hrs Design Costs per Design...
Use the following information regarding Musketeer Novelties: Activity Activity Costs Cost driver Product design $212,000 1,500...
Use the following information regarding Musketeer Novelties: Activity Activity Costs Cost driver Product design $212,000 1,500 design hours Product scheduling $180,000 400 Set ups Machining $600,000 5,000 machine hours Material Handling $160,000 4,000 Pallet moved Cost and activity with procuring 2,000 units of a Blueblob Bobblehead are as follows: Direct Materials: $5,400 Direct Labor: $1,200 Design Hours: 5 Set-Ups: 3 Labor Hours 40 Machine Hours 18 Pallets Moved 10 United produced 400 1.) Develop activity rates for each of the...
1) Required information Gable Company uses three activity cost pools. Each pool has a cost driver....
1) Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 236,300 Number of machine hours 69,500 Designing costs 58,725 Number of design hours 6,750 Setup costs 71,350 Number of batches 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. 2) Required information Gable...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT