In: Accounting
The following budgeted information is available for Zeta Company:
Activity |
Budgeted Cost |
Activity Driver |
Consumption of Drivers for Zeta’s Product Lines |
||
Total Activity Driver |
Product A |
Product B |
|||
Processing & Testing |
|||||
Developing test programs |
$400,000 |
Engineering hours |
10,000 |
2,500 |
7,500 |
Making probe cards |
58,750 |
Development hours |
4,000 |
400 |
3,600 |
Testing products |
300,000 |
Test hours |
20,000 |
2,000 |
18,000 |
Setups |
40,000 |
Number of batches |
100 |
55 |
45 |
Engineering design |
80,000 |
Number of change orders |
60 |
9 |
51 |
Handling lots |
90,000 |
Number of moves |
200 |
110 |
90 |
Subtotal, Processing & Testing |
$968,750 |
||||
Procurement |
|||||
Purchasing materials |
450,000 |
Number of purchase orders |
2,500 |
500 |
2,000 |
Unloading materials |
60,000 |
Number of deliveries |
3,000 |
600 |
2,400 |
Inspecting materials |
75,000 |
Inspection hours |
5,000 |
3,500 |
1,500 |
Moving materials |
30,000 |
Distance moved (feet) |
3,000 |
2,100 |
900 |
Paying suppliers |
66,250 |
Number of invoices |
1,250 |
250 |
1,000 |
Subtotal, Procurement |
681,250 |
||||
Total |
$1,650,000 |
1. Assume the company currently uses departmental rates for allocating overhead. Calculate the pre-determined overhead rate for the Processing & Testing Department (based on Engineering hours) and the Procurement Department (based on Number of purchase orders). Round to three (3) places after the decimal.
2. Identify which activity cost pools can be combined.
3. After combining cost pools as appropriate, calculate the pre-determined overhead rates for each activity cost pool.
4. Calculate the cost of Product line A using the departmental rates calculated in #1.
5. Calculate the cost of Product line A using the ABC rates calculated in #3.
6. Is ABC better for Zeta Company? Why or why not?
1.
Pre-determined overhead rate for the Processing & Testing Department
= Total fixed overhead / Total engineering hours
= 968750 / 10000
= 96.875 per engg hour
Pre-determined overhead rate for Procurement Department
= Total fixed overhead / Number of purchase orders
= 681250 / 2500
= 272.50 per purchase order
2.
Following cost pools can be combined:
Setups | These two have cost drivers of Product A & B in the ratio of 9:11 | COST POOL 1 |
Handling lots |
Making probe cards | These two have cost drivers of Product A & B in the ratio of 1:9 | COST POOL 2 |
Testing products |
Purchasing materials | These three have cost drivers of Product A & B in the ratio of 1:4 | COST POOL 3 |
Unloading materials | ||
Paying suppliers |
Inspecting materials | These two have cost drivers of Product A & B in the ratio of 7:3 | COST POOL 4 |
Moving materials |
3.
Cost Pools | Total Cost | Ratio | Total Driver | Cost Driver Rate |
COST POOL 1 | $1,30,000.00 | 9:11 | 300 | $433.333 |
COST POOL 2 | $3,58,750.00 | 1:9 | 24000 | $14.948 |
COST POOL 3 | $5,76,250.00 | 1:4 | 6750 | $85.370 |
COST POOL 4 | $1,05,000.00 | 7:3 | 8000 | $13.125 |
Developing test programs | $4,00,000.00 | 1:3 | 10000 | $40.000 |
Engineering design | $80,000.00 | 3:17 | 60 | $1,333.333 |
4. Cost of Product line A using the ABC rates
Cost Pools | Cost Driver Rate | Cost Drivers | Total Cost |
COST POOL 1 | $433.333 | 165 | $71,500.000 |
COST POOL 2 | $14.948 | 2400 | $35,875.000 |
COST POOL 3 | $85.370 | 1350 | $1,15,250.000 |
COST POOL 4 | $13.125 | 4600 | $60,375.000 |
Developing test programs | $40.000 | 2500 | $1,00,000.000 |
Engineering design | $1,333.333 | 9 | $12,000.000 |
Total | $395,000 |
5.
Overhead Cost of A using traditional Approach = (98.875 * 2500) + (272.50 * 500) = $383,438
Overhead Cost of A using ABC Approach = $395,000
Since there is a difference in both approaches, it is better to use ABC approach. The main reason being ABC approach is said to be more accurate in allocation of overhead costs among products.