What is the NPV of a project that costs $95,000, provides
$36,000 in cash flows annually...
What is the NPV of a project that costs $95,000, provides
$36,000 in cash flows annually for 13 years, and requires a $6,000
increase in net working capital? The discount rate is 11%.
What is the NPV of a project that costs $100,000, provides
$21,000 in cash flows annually for six years, requires a $5,000
increase in net working capital which will be recovered later? The
discount rate is 14%.
-$13,283
-$21,060
- $18,142
$15,561
What is the NPV of a project that costs $200,000,
provides $43,000 in after-tax cash flows (excluding the CCA tax
shield) annually for six years , requires a $5,000 increase in net
working capital, and depreciates the asset at 15 percent declining
balance over six years and sold at zero salvage value? The discount
rate is 14 percent. The tax rate is 40 percent.(Assume the
half-year rule applies and working capital is recovered at the end
of the project)
Select...
What is the NPV of a project that costs $200,000, provides
$43,000 in after-tax cash flows (excluding the CCA tax shield)
annually for six years , requires a $5,000 increase in net working
capital, and depreciates the asset at 15 percent declining balance
over six years and sold at zero salvage value? The discount rate is
14 percent. The tax rate is 40 percent.(Assume the half-year rule
applies and working capital is recovered at the end of the
project)
What is the NPV of a project that costs $80,000 today and cash
inflows $45,000 annually for three years from today if the
opportunity cost of capital is 14?
What is the profitability index of a project that costs $8,000
and provides cash flows of $2,100 in years 1 and 2 and $4,100 in
years 3 and 4? The discount rate is 10%. (Do not round
intermediate calculations. Round your answer to 4 decimal
places.)
1.
Project A
Year
Cash Flow
0
-$107
1
$69
2
$80
3
$120
WACC =
6.19%
Given the cash-flows in the table, what is the NPV of project
A?
State your answer to the nearest penny.
Give just the number with no dollar sign (e.g., 3.26)
If the NPV is negative include the - sign (e.g. -4.28)
2.
Using the information in the table, what is the IRR for Project
A?
Cash Flow
Year
Project A
0
($175)
1...
A project that provides annual cash flows of $17,300 for nine
years costs $78,000 today. What is the NPV for the project if the
required return is 8%? At a required return of 8% should the firm
accept this project? What is the NPV for the project if the
required return is 20%? At a required return of 20% should the firm
accept this project? At what discount rate would you be indifferent
between accepting the project and rejecting it?
A project that provides annual cash flows of $17673 for eight
years costs $80339 today. What is the NPV for the project if the
required return is 19 percent? (Negative amount should be indicated
by a minus sign. Round your answer to 2 decimal places. (e.g.,
32.16))
Calculate the NPV for Project A and accept or reject the project
with the cash flows shown below if the appropriate cost of capital
is 7%
Project A
Time 0 1 2 3 4 5
Cash Flow -990 350 480 500 630 120
2) Calculate the NPV for project L and recommend whether the
company should accept or reject the project. Cost of Capital is
6%
Project L
Time 0 1 2 3 4 5
Cash Flow - 8,600
...