Question

In: Accounting

What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows...

What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows (excluding the CCA tax shield) annually for six years , requires a $5,000 increase in net working capital, and depreciates the asset at 15 percent declining balance over six years and sold at zero salvage value? The discount rate is 14 percent. The tax rate is 40 percent.(Assume the half-year rule applies and working capital is recovered at the end of the project)

Select one:

a. $12,868

b. $3,329

c. $11,283

d. $6,051

e. -$30,065

Solutions

Expert Solution

Correct Option A i.e $12868
Calculation of NPV
Year Total cash flow pv Factor @14% Presnet value
0 (205,000) 1       (205,000)
1        55,000 0.878            48,290
2        53,200 0.77            40,964
3        51,670 0.675            34,877
4        50,370 0.593            29,869
5        49,264 0.52            25,617
6        83,496 0.458            38,241
Net present value            12,868
Note 1: Calculation of Annual Cash Flow
Year Cash Flow Depreciation Tax sheild on depreciation Tax sheild on disposal of asset Working capital Total cash flow
0 -200000 -5000 (205,000)
1 43000          30,000            12,000        55,000
2 43000          25,500            10,200        53,200
3 43000          21,675              8,670        51,670
4 43000          18,424              7,370        50,370
5 43000          15,660              6,264        49,264
6 43000          13,311              5,324          30,172 5000        83,496
Note 2: CALCULATION OF DEPRECIATION
Year Cost Depreciation Declining balance
0 200000 0          200,000
1 200000          30,000          170,000
2 170000          25,500          144,500
3 144500          21,675          122,825
4 122825          18,424          104,401
5 104401.25          15,660            88,741
6 88741.063          13,311            75,430

Related Solutions

What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows...
What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows (excluding the CCA tax shield) annually for six years , requires a $5,000 increase in net working capital, and depreciates the asset at 15 percent declining balance over six years and sold at zero salvage value? The discount rate is 14 percent. The tax rate is 40 percent.(Assume the half-year rule applies and working capital is recovered at the end of the project)
What is the NPV of a project that costs $95,000, provides $36,000 in cash flows annually...
What is the NPV of a project that costs $95,000, provides $36,000 in cash flows annually for 13 years, and requires a $6,000 increase in net working capital? The discount rate is 11%. Round your answer to the nearest dollar.
What is the NPV of a project that costs $100,000, provides $21,000 in cash flows annually...
What is the NPV of a project that costs $100,000, provides $21,000 in cash flows annually for six years, requires a $5,000 increase in net working capital which will be recovered later? The discount rate is 14%. -$13,283 -$21,060 - $18,142 $15,561
What is the profitability index of a project that costs $8,000 and provides cash flows of...
What is the profitability index of a project that costs $8,000 and provides cash flows of $2,100 in years 1 and 2 and $4,100 in years 3 and 4? The discount rate is 10%. (Do not round intermediate calculations. Round your answer to 4 decimal places.)
Evaluating a capital budgeting project that costs $40,000 that is expected to generate after-tax cash flows...
Evaluating a capital budgeting project that costs $40,000 that is expected to generate after-tax cash flows of $15,000 per year for three years. If the required rate of return is 10 percent calculate the project’s (a) NPV and (b) IRR. Should the project be purchased? This is for a review Please show steps and rationale for project purchase.
what is the net present value of a project with the following after tax cash flows...
what is the net present value of a project with the following after tax cash flows using a discount rate of 10% year 0 45,000 year 1 14,000 year 2 14,000 year 3 10,000 year 4 10,000 year 5 8,000 would you accept the project? ehat is payback period? what is the profitbility index?
Given the cash-flows in the table, what is the NPV of project A?
1. Project A Year Cash Flow 0 -$107 1 $69 2 $80 3 $120 WACC = 6.19% Given the cash-flows in the table, what is the NPV of project A?   State your answer to the nearest penny. Give just the number with no dollar sign (e.g., 3.26) If the NPV is negative include the - sign (e.g. -4.28) 2. Using the information in the table, what is the IRR for Project A? Cash Flow Year Project A 0 ($175) 1...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What is the NPV for the project if the required return is 8%? At a required return of 8% should the firm accept this project? What is the NPV for the project if the required return is 20%? At a required return of 20% should the firm accept this project? At what discount rate would you be indifferent between accepting the project and rejecting it? 
A project that provides annual cash flows of $17673 for eight years costs $80339 today. What...
A project that provides annual cash flows of $17673 for eight years costs $80339 today. What is the NPV for the project if the required return is 19 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16))
Calculate the NPV for Project A and accept or reject the project with the cash flows...
Calculate the NPV for Project A and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 7% Project A Time 0 1 2 3 4 5 Cash Flow -990 350 480 500 630 120 2) Calculate the NPV for project L and recommend whether the company should accept or reject the project. Cost of Capital is 6% Project L Time 0 1 2 3 4 5 Cash Flow -         8,600          ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT