Question

In: Finance

What is the NPV of a project that costs $80,000 today and cash inflows $45,000 annually...

What is the NPV of a project that costs $80,000 today and cash inflows $45,000 annually for three years from today if the opportunity cost of capital is 14?

Solutions

Expert Solution

Pls find below workings and answer:

NPV of this project is $ 24473.44; Since this is a positive NPV, the project is recommended.

Computation of Net Present Value (NPV) based on the Discounted Cash flows; The Discounting factor is computed based on the formula: For year 0, the discounting factor is 1; For Year 1, it is computed as = Year 0 factor /(1+discounting factor%) ; Year 2 = Year 1 factor/(1+discounting factor %) and so on;

Next, the cashflows need to be multiplied with the respective years' discounting factor, to arrive at the discounting cash flows;

The total of all the discounted cash flows is equal to its respective Project NPV of the Cash Flows;


Related Solutions

What is the NPV of a project that costs $95,000, provides $36,000 in cash flows annually...
What is the NPV of a project that costs $95,000, provides $36,000 in cash flows annually for 13 years, and requires a $6,000 increase in net working capital? The discount rate is 11%. Round your answer to the nearest dollar.
What is the NPV of a project that costs $100,000, provides $21,000 in cash flows annually...
What is the NPV of a project that costs $100,000, provides $21,000 in cash flows annually for six years, requires a $5,000 increase in net working capital which will be recovered later? The discount rate is 14%. -$13,283 -$21,060 - $18,142 $15,561
Project L costs $45,000, its expected cash inflows are $9,000 per year for 8 years, and...
Project L costs $45,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 11%. What is the project's payback? Round your answer to two decimal places.   years
Project L costs $45,000, its expected cash inflows are $13,000 per year for 8 years, and...
Project L costs $45,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places.
Project L costs $45,000, its expected cash inflows are $11,000 per year for 12 years, and...
Project L costs $45,000, its expected cash inflows are $11,000 per year for 12 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
What is the NPV of a project that costs $100,000.00 and returns $50,000.00 annually for three...
What is the NPV of a project that costs $100,000.00 and returns $50,000.00 annually for three years if the opportunity cost of capital is 8.22%?
What is the NPV of a project that costs $120,000 today and is expected to generate...
What is the NPV of a project that costs $120,000 today and is expected to generate annual cash inflows of $10,000 for the next 12 years, followed by a final inflow of $21,000 in the year after. Use discount rate of 14%. Round to the nearest cent.  
What is the NPV of a project that costs $31,000 today and is expected to generate...
What is the NPV of a project that costs $31,000 today and is expected to generate annual cash inflows of $11,000 for the next 7 years, followed by a final inflow of $13,000 in year 8. Cost of capital is 8.7%. Round to the nearest cent.
What is the NPV of a project that costs $111,000 today and is expected to generate...
What is the NPV of a project that costs $111,000 today and is expected to generate annual cash inflows of $12,000 for the next 11 years. Cost of capital (discount rate) is 11%. Round to the nearest cent.
What is the NPV of a project that costs $38,000 today and is expected to generate...
What is the NPV of a project that costs $38,000 today and is expected to generate annual cash inflows of $9,000 for the next 7 years, followed by a final inflow of $15,000 in year 8. Cost of capital is 7.4%. Round to the nearest cent.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT