In: Finance
Pls find below workings and answer:
NPV of this project is $ 24473.44; Since this is a positive NPV, the project is recommended.
Computation of Net Present Value (NPV) based on the Discounted Cash flows; The Discounting factor is computed based on the formula: For year 0, the discounting factor is 1; For Year 1, it is computed as = Year 0 factor /(1+discounting factor%) ; Year 2 = Year 1 factor/(1+discounting factor %) and so on;
Next, the cashflows need to be multiplied with the respective years' discounting factor, to arrive at the discounting cash flows;
The total of all the discounted cash flows is equal to its respective Project NPV of the Cash Flows;