In: Accounting
Cardinal Company has determined the following standard cost data necessary to manufacture one unit of its primary product:
Direct Materials….. (6 pounds @ $20)
Direct Labor…………. .(8 hours @ $15)
During 20X1, Cardinal produced only 1 unit of product. This unit required 7 pounds of direct material (a total of 8 pounds were purchased at a cost of $18 per pound). In addition, total payroll costs for direct labor during 20X1 were $130 (10 hours @ $13 per hour).
Required:
Answer the following questions, indicating BOTH the dollar amount of each variance and whether each variance is FAVORABLE (F) or UNFAVORABLE (U).
The materials price variance was $__
The materials efficiency (usage) variance was $__
The labor rate (price) variance was $__
The labor efficiency (usage) variance was $__
The total cost of the unit completed in 20X1 and transferred from Work in Process to Finished Goods was $
a.) | Material Price Variance:- | ||||||||
Material price variance= ( Actual Price - Standard price ) x Actual quantity | |||||||||
= ( 18 - 20 ) x 7 | |||||||||
= - 2 x 7 | |||||||||
= - $ 14 Favorable | |||||||||
b.) | Material efficiency (usage) Variance:- | ||||||||
Material efficiency variance= ( Actual quantity - Standard quantity ) x Standard price | |||||||||
= ( 7 - 6 ) x 20 | |||||||||
= 1 x 20 | |||||||||
= $ 20 Unfavorable | |||||||||
c.) | Labour Rate (Price )Variance:- | ||||||||
Labour rate variance= ( Actual rate - Standard rate ) x Actual hours | |||||||||
= ( 13 - 15 ) x 10 | |||||||||
= - 2 x 10 | |||||||||
= - $ 20 Favorable | |||||||||
d.) | Labour efficiency (usage) Variance:- | ||||||||
Labour efficiency variance= ( Actual hours - Standard hours ) x Standard rate | |||||||||
= ( 10 - 8 ) x 15 | |||||||||
= 2 x 15 | |||||||||
= $ 30 Unfavorable | |||||||||
e) | Total cost of the unit completed in 20X1 and transferred from Work in Process to Finished Goods | ||||||||
Direct Material cost | 126 | (7 x 18) | |||||||
Direct Labor Cost | 130 | (10 x 13) | |||||||
Total Cost | 256 | ||||||||