Question

In: Accounting

The Leonard Company uses standard costs in its factory.   The standard cost to produce one unit...

The Leonard Company uses standard costs in its factory.   The standard cost to produce one unit is as follows:

               Direct materials (1 g × $32/g)                                                   $32

               Direct labor (1.5 hours x $20 per hour)                                       30

               Variable overhead (1.5 direct labour hours x $10 per hour)       15

               Fixed Overhead (1.5 direct labour hours x $16 per hour)           24

                                                                                                                $101

Standards are based on normal monthly production involving 9,000 direct labor hours (6,000 units). The actual results for the most recent month are:

               Direct materials purchased and used (5,300 g × $33/g)              $ 174,900

               Direct labor (8,400 hours)                                                              176,400

               Actual fixed factory overhead                                                        135,000

               Actual variable factory overhead                                                   100,000

A total of 5,000 units were produced and sold during the month.

  1. What was the Direct Materials Price Variance for the month?
  1. $9,600 U
  2. Unable to calculate with data given
  3. $5,300 F
  4. $5,300 U

  1. What was the Direct Labour Efficiency Variance for the month?
  1. $18,000 U
  2. $12,000 U
  3. $12,000 F
  4. $18,900 U

  1. What was the Variable Overhead Price (Rate) Variance for the month?
  1. $16,000 F
  2. $16,000 U
  3. $25,000 F
  4. $ 9,000 F

  1. What was over or under-applied variable overhead for the month?
  1. $100,000 over applied
  2. $ 75,000 under applied
  3. $ 25,000 under applied
  4. $ 25,000 over applied

  1. What was the Fixed Overhead Production Volume Variance for the month?
  1. $ 24,000 U
  2. $120,000 U
  3. $144,000 U
  4. $ 24,000 F

  1. What would be a possible reason for an unfavourable Direct Labour Efficiency Variance?
  1. One of the machines broke down and a batch had to be scrapped.
  2. The worker’s hourly rate of pay increased.
  3. The rates for payroll taxes like CPP and EI increased.
  4. The supervisors’ salaries were increased.

Solutions

Expert Solution

Answer:

Data for Various variance

Budget (Standard)    Revised Budget Actual data

Per Unit Total cost ($) For 5000 units Total Cost ($) For 5000 Units Total Cost ($)
Direct Material 1 g 32 5,000 g 160,000 5,300 g 174,900
@ $ 32 per g @ $ 32 per g @ $ 33 per g
Direct labour 1.5 hours 30 7,500 hours 150,000 8,400 hours 176,400
@ $ 20 per hour @ $ 20 per hour

@ $ 21 per hour

($176400/8400)

Variable overhead 1.5 hours 15 7,500 hours 75,000 8,400 hours 100,000
@ $ 10 per hour @ $ 10 per hour

@ $ 11.90476190 per hour

($100000/8400)

Fixed overhead 1.5 hours 24 7,500 hours 120,000 8,400 hours 135,000
@ $ 16 per hour @ $ 16 per hour

1. Direct Material Price variance = ( SP - AP ) * AQ

= ($ 32 - $ 33) * 5,300 g

= ( - $ 1 ) * 5,300 g

= $ 5,300 U

Here, the correct answer is (D) $ 5,300 U.

Note:

Where, SP is the standard unit price of direct material

AP is the actual unit price of direct material

AQ is the actual quantity of direct material used

2. Direct Labour Efficiency Variance = ( SH - AH ) * SR

= ( 7,500 - 8,400 ) * $ 20

= ( - 900 ) * $ 20

= $ 18,000 U

Here, the correct answer is (A) $ 18,000 U

Note:

Where, SH are the standard direct labour hours allowed ( Standard direct labour hours per unit * Actual number of finished units produced )

AH are the actual direct labour hours used

SR is the standard direct labour rate per hour

  

3. Variable Overhead Price (Rate) Variance = ( SR - AR ) * AH

= ( $ 10 - $ 11.9047619047619 ) * 8,400

= ( - $ 1.9047619047619 ) * 8,400

= $ 16,000 U

Here, the correct answer is (B) $ 16,000 U

Note:

Where, SR is the standard variable overhead rate

AR is the actual variable overhead rate

AH are the actual direct labour hours of allocation base

4. Over or Under Applied variable overhead:

As per the Revised budget the budgeted variable overhead for actual output is $ 75,000

However the actual variable overhead for actual output is $ 100,000

Since, the company charged off only $ 75,000, it has Under applied overhead.

the variable overhead is under applied by $ 25,000

Here, the correct answer is (C) $ 25,000 underapplied.

5. Fixed Overhead Production Volume Variance = Budgeted fixed overhead -Fixed overhead applied

= $ 144,000 - $ 120,000

= $ 24000 F

Here, the correct answer is (D) $ 24,000 F.

Note:

Where, Budgeted Fixed overhead = standard direct labour hours * Fixed overhead recovery rate per hour

= 9000 * $ 16

= $ 144,000

Fixed overhead applied = Fixed overhead recovery rate per hour * ( Actual output * Standard hours per unit )

= $ 16 * ( 5000 units * 1.5 hours )

= $ 120,000

6. Possible reason for an Unfavourable Direct labour efficiency variance:

The correct answer is (A) One of the machines broke down and a batch had to be scrapped.

The main reason for Unfavourable labour efficiency variance is higher of actual labour hours than standard labour hours for actual output.

Due to machine break down the actual labour hours for actual output will increase.

Here, the other three options are not correct, because an increase in workers hourly rate, increase in payroll taxes and increase in supervisors salaries would not affect the actual labour hours required for actual output.


Related Solutions

West Manufacturing Company uses a standard cost system in its accounting records. The standard costs for...
West Manufacturing Company uses a standard cost system in its accounting records. The standard costs for its one product are as follows:                      Materials                                    8 pounds at $1.00 =   $ 8.00                      Direct labor                              1.2 hours at $14.00 =     16.80                      Variable overhead     1.2 direct-labor hours at $4.00 =       4.80                      Fixed overhead         1.2 direct-labor hours at $6.00 =       7.20                      Total standard cost                                                      $36.80             The standard costs per unit are based on normal capacity of 3,600 direct-labor...
Antuan Company set the following standard costs for one unit of its product.
  Antuan Company set the following standard costs for one unit of its product.       Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.8 hrs. @ $11.00 per hr.)   19.80 Overhead (1.8 hrs. @ $18.50 per hr.)   33.30 Total standard cost $ 73.10   The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are...
11. Regent Corp. uses a standard cost system to account for the costs of its one...
11. Regent Corp. uses a standard cost system to account for the costs of its one product. Materials standards are 2.8 pounds of material at $13 per pound, and labor standards are 4 hours of labor at a standard wage rate of $10. During July Regent Corp. produced 3,280 units. Materials purchased and used totaled 10,050 pounds at a total cost of $132,050. Payroll totaled $147,380 for 13,240 hours worked.    a. Calculate the direct materials price variance. (Do not round...
Viking Corp. uses a standard cost system to account for the costs of its one products....
Viking Corp. uses a standard cost system to account for the costs of its one products. Material standards are 13 pounds of material at $1.30 per pound and 3 hours of labor at a standard wage rate of $13.4. During November, Viking Corp. produced and sold 2,400 units. Material purchases totaled 31,470 pounds at a total cost of $41,421. Material usage totaled 31,290 pounds. Payroll totaled $97,282 for 7,430 hours worked. Viking Corp. does not maintain inventories other than direct...
Regency Corp. uses a standard cost system to account for the costs of its one product....
Regency Corp. uses a standard cost system to account for the costs of its one product. Fixed overhead is applied to production at a rate of $27.10 per unit, based on budgeted production is 2,445 per month. During November, Regency produced 2,295 units. Fixed overhead incurred totaled $70,420. a. Calculate the fixed overhead spending variance. b. Calculate the fixed overhead volume variance.
Sedona Company set the following standard costs for one unit of its product for this year.
Sedona Company set the following standard costs for one unit of its product for this year.           Direct material (30 Ibs. @ $2.00 per Ib.)   $ 60.00   Direct labor (20 hrs. @ $4.50 per hr.)     90.00   Variable overhead (20 hrs. @ $2.50 per hr.)     50.00   Fixed overhead (20 hrs. @ $1.20 per hr.)     24.00   Total standard cost   $ 224.00     The $3.70 ($2.50...
Sedona Company set the following standard costs for one unit of its product for 2017.
  Sedona Company set the following standard costs for one unit of its product for 2017. Direct material (20 Ibs. @ $2.50 per Ib.) $ 50.00 Direct labor (10 hrs. @ $22.00 per hr.) 220.00 Factory variable overhead (10 hrs. @ $4.00 per hr.) 40.00 Factory fixed overhead (10 hrs. @ $1.60 per hr.) 16.00 Standard cost $ 326.00 The $5.60 ($4.00 + $1.60) total overhead rate per direct labor hour is based on an expected operating level equal to...
Sedona Company set the following standard costs for one unit of its product for 2017.    ...
Sedona Company set the following standard costs for one unit of its product for 2017.                 Direct material (15 Ibs. @ $3.40 per Ib.)      $   51.00      Direct labor (10 hrs. @ $9.70 per hr.)         97.00      Factory variable overhead (10 hrs. @ $4.90 per hr.)         49.00      Factory fixed overhead (10 hrs. @ $2.00 per hr.)         20.00      Standard cost      $   217.00      The $6.90 ($4.90 +...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 53,100 machine hours per year, which represents 26,550 units of output. Annual budgeted fixed factory overhead costs are $265,500 and the budgeted variable factory overhead cost rate is $3.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT