Question

In: Finance

A project that provides annual cash flows of $2,450 for nine years costs $10,100 today. Requirement...

A project that provides annual cash flows of $2,450 for nine years costs $10,100 today.


Requirement 1:

At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)


  NPV   $   


Requirement 2:

At a required return of 25 percent, what is the NPV of the project? Use the IRR function. (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).)


  NPV   $   


Requirement 3:

At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)


  Discount rate %

Solutions

Expert Solution

1

Discount rate 9.000%
Year 0 1 2 3 4 5 6 7 8 9
Cash flow stream -10100 2450 2450 2450 2450 2450 2450 2450 2450 2450
Discounting factor 1.000 1.090 1.188 1.295 1.412 1.539 1.677 1.828 1.993 2.172
Discounted cash flows project -10100.000 2247.706 2062.116 1891.850 1735.642 1592.332 1460.855 1340.234 1229.572 1128.048
NPV = Sum of discounted cash flows
NPV Project = 4588.35
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

2

Discount rate 25.000%
Year 0 1 2 3 4 5 6 7 8 9
Cash flow stream -10100 2450 2450 2450 2450 2450 2450 2450 2450 2450
Discounting factor 1.000 1.250 1.563 1.953 2.441 3.052 3.815 4.768 5.960 7.451
Discounted cash flows project -10100.000 1960.000 1568.000 1254.400 1003.520 802.816 642.253 513.802 411.042 328.833
NPV = Sum of discounted cash flows
NPV Project = -1615.33
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

3

Project
IRR is the rate at which NPV =0
IRR 19.30%
Year 0 1 2 3 4 5 6 7 8 9
Cash flow stream -10100.000 2450.000 2450.000 2450.000 2450.000 2450.000 2450.000 2450.000 2450.000 2450.000
Discounting factor 1.000 1.193 1.423 1.698 2.026 2.417 2.883 3.440 4.104 4.896
Discounted cash flows project -10100.000 2053.591 1721.321 1442.812 1209.366 1013.691 849.676 712.199 596.966 500.377
NPV = Sum of discounted cash flows
NPV Project = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 19.30% = indifference rate

Related Solutions

A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.   ...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today.    What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations. Round the final answer to 2 decimal places.)      NPV $       At a required return of 8 percent, should the firm accept this project? Accept or Reject    What is the NPV for the project if the required return is 20 percent? (Do not...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What...
A project that provides annual cash flows of $17,300 for nine years costs $78,000 today. What is the NPV for the project if the required return is 8%? At a required return of 8% should the firm accept this project? What is the NPV for the project if the required return is 20%? At a required return of 20% should the firm accept this project? At what discount rate would you be indifferent between accepting the project and rejecting it? 
A project that will provde annual cash flows of $2,800 for nine years costs $9,200 today....
A project that will provde annual cash flows of $2,800 for nine years costs $9,200 today. a. At a required return of 11 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 27 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a)...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a) If the required return is 13 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a....
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today. A)...
A project that provides annual cash flows of $14,700 for 9 years costs $81,395 today. A) If the required return is 4 percent, what is the NPV for this project? B)Determine the IRR for this project.
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a....
A project that provides annual cash flows of $10,500 for 8 years costs $50,387 today. a. If the required return is 19 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a....
A project that provides annual cash flows of $20,000 for 5 years costs $64,000 today. a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.   ...
A project that provides annual cash flows of $2,500 for 7 years costs $9,400 today.    Required: (a) If the required return is 9 percent, what is the NPV for this project?    (b) Determine the IRR for this project. rev: 09_18_2012, 09_26_2017_QC_C
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.   ...
A project that provides annual cash flows of $12,300 for 11 years costs $79,889 today.    a. If the required return is 14 percent, what is the NPV for this project?    b. Determine the IRR for this project.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT