In: Finance
A project that provides annual cash flows of $2,450 for nine years costs $10,100 today. |
Requirement 1: |
At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).) |
NPV | $ |
Requirement 2: |
At a required return of 25 percent, what is the NPV of the project? Use the IRR function. (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).) |
NPV | $ |
Requirement 3: |
At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) |
Discount rate | % |
1
Discount rate | 9.000% | |||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
Cash flow stream | -10100 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 |
Discounting factor | 1.000 | 1.090 | 1.188 | 1.295 | 1.412 | 1.539 | 1.677 | 1.828 | 1.993 | 2.172 |
Discounted cash flows project | -10100.000 | 2247.706 | 2062.116 | 1891.850 | 1735.642 | 1592.332 | 1460.855 | 1340.234 | 1229.572 | 1128.048 |
NPV = Sum of discounted cash flows | ||||||||||
NPV Project = | 4588.35 | |||||||||
Where | ||||||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||||||
Discounted Cashflow= | Cash flow stream/discounting factor |
2
Discount rate | 25.000% | |||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
Cash flow stream | -10100 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 | 2450 |
Discounting factor | 1.000 | 1.250 | 1.563 | 1.953 | 2.441 | 3.052 | 3.815 | 4.768 | 5.960 | 7.451 |
Discounted cash flows project | -10100.000 | 1960.000 | 1568.000 | 1254.400 | 1003.520 | 802.816 | 642.253 | 513.802 | 411.042 | 328.833 |
NPV = Sum of discounted cash flows | ||||||||||
NPV Project = | -1615.33 | |||||||||
Where | ||||||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||||||
Discounted Cashflow= | Cash flow stream/discounting factor |
3
Project | ||||||||||
IRR is the rate at which NPV =0 | ||||||||||
IRR | 19.30% | |||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
Cash flow stream | -10100.000 | 2450.000 | 2450.000 | 2450.000 | 2450.000 | 2450.000 | 2450.000 | 2450.000 | 2450.000 | 2450.000 |
Discounting factor | 1.000 | 1.193 | 1.423 | 1.698 | 2.026 | 2.417 | 2.883 | 3.440 | 4.104 | 4.896 |
Discounted cash flows project | -10100.000 | 2053.591 | 1721.321 | 1442.812 | 1209.366 | 1013.691 | 849.676 | 712.199 | 596.966 | 500.377 |
NPV = Sum of discounted cash flows | ||||||||||
NPV Project = | 0.000 | |||||||||
Where | ||||||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||||||
IRR= | 19.30% = indifference rate |