In: Accounting
Norther Leasing Corp. has the following standards for one unit of product:
Direct material: 80 pounds X $6 |
$480 |
Direct labor: 3 hours X $16 per hour |
48 |
Variable overhead: 1.5 hours of machine time X $50 per hour |
75 |
Fixed overhead: 1.5 hours of machine time X $30 per hour |
45 |
The predetermined OH rates were developed using a practical capacity of 6,000 units per year. Production is assumed to occur evenly throughout the year.
During May 2010, the company produced 525 units. Actual data for May 2010 are as follows:
Direct material purchased: 45,000 pounds X $5.92 per pound
Direct material used: 43,020 pounds (all from May’s purchases)
Total labor cost: $24,955 for 1,550 hour
Variable overhead incurred: $43,750 for 800 hours of machine time
Fixed overhead incurred: $22,800 for 800 hours of machine time
Required: Calculate the following:
a) Material cost variance
b) Material price variance based on purchases
c) Material quantity variance
d) Labor cost variance
e) Labor rate variance
f) Labor efficiency variance
g) Variable overhead Cost
h) Variable overhead expenditure variance
i) Variable efficiency variances
j) Fixed overhead cost
k) Fixed overhead expenditure
l) Fixed volume variances
Solution:
a) |
Material Cost Variance |
||
Direct material price variance (Refer part b) |
$3,600 |
Favorable |
|
Direct Material Quantity Variance (Refer part c) |
$6,120 |
Unfavorable |
|
Material Cost Variance |
$2,520 |
Unfavorable |
|
b) |
Direct Material Price Variance |
||
Actual Price |
$5.92 |
per pound |
|
Standard Price |
$6.00 |
per pound |
|
Variance or Difference in Price |
$0.08 |
per pound |
|
x Actual Quantity PURCHASED |
45,000 |
Pounds |
|
Direct Material Price Variance |
$3,600 |
Favorable |
|
c) |
Direct Material Quantity/Efficiency Variance |
||
Standard Quantity Allowed for actual production: |
|||
Actual Production/Activity |
525 |
Units |
|
x Allowed Standard Quantity Per Unit |
80 |
Pounds |
|
Total Standard Quantity Allowed for actual production (SQAP) |
42,000 |
Pounds |
|
Actual Quantity USED (AQU) (Total Purchase 25,000 - Ending Inventory 5,000) |
43,020 |
Pounds |
|
Variance or Difference in Quantity |
1,020 |
Pounds |
|
x Standard Price (SP) |
$6.00 |
Per Pound |
|
Material Quantity/Efficiency Variance |
$6,120.00 |
Unfavorable |
|
d) |
Labor Cost Variance |
||
Direct Labor Rate Variance (Refer e) |
$155 |
Unfavorable |
|
Direct Labor Efficiency Variance (Refer f) |
$400 |
Favorable |
|
Labor Cost Variance |
$245 |
Favorable |
|
e) |
Labor Rate Variance |
||
Actual Hourly Rate ($24,955 / 1550 Hrs) |
$16.10 |
Per Hour |
|
Standard Hourly Rate |
$16.00 |
Per Hour |
|
Variance or Difference in Rate |
$0.10 |
Per Hour |
|
x Actual Labor Hours worked |
1550 |
Hours |
|
Labor Rate Variance |
$155 |
Unfavorable |
|
f) |
Labor Quantity / Efficiency Variance |
||
Standard Hours Allowed for actual production: |
|||
Actual Production |
525 |
Units |
|
x Allowed Standard Hours Per Unit |
3 |
hours |
|
Total Standard Hours Allowed for actual production (SHAP) |
1,575 |
hours |
|
Actual Labor Hours Worked (AH) |
1,550 |
hours |
|
Variance or Difference in Hours |
25 |
hours |
|
x Standard Hourly Rate (SHR) |
$16.00 |
per hour |
|
Labor Efficiency Variance |
$400 |
Favorable |
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Pls ask separate question for remaining parts