Question

In: Accounting

Activity-Based Costing, Unit Cost, Ending Work-in-Process Inventory, Journal Entries Feldspar Company uses an ABC system to...

Activity-Based Costing, Unit Cost, Ending Work-in-Process Inventory, Journal Entries

Feldspar Company uses an ABC system to apply overhead. There are three activity rates:

Setting up $20 per setup
Machining $5.20 per machine hour
Other overhead 80% of direct labor cost

During September, Feldspar worked on three jobs. Data relating to these jobs follow:

Job 13-280 Job 13-281 Job 13-282
Units in each order 200 510 100
Units sold 200 100
Materials requisitioned $4,750 $3,800 $5,600
Direct labor cost $2,000 $4,700 $800
Machine hours 80 100 40
Number of setups 20 15 25

During September, Jobs 13-280 and 13-282 were completed and transferred to Finished Goods Inventory. Job 13-280 was sold by the end of the month. Job 13-281 was the only unfinished job at the end of the month.

Required:

1. Calculate the per-unit cost of Jobs 13-280 and 13-282. Round unit cost to nearest cent.

Job 13-280 $ per unit
Job 13-282 $ per unit

2. Compute the ending balance in the work-in-process inventory account.

$

3. Prepare the journal entries reflecting (a.) the completion of Jobs 13-280 and 13-282 and (b.) the sale of Job 13-280 on account. Make the entry to record the cost of Job 13-280 first, followed by the entry to record the revenue from its sale. The selling price is 150 percent of cost.

a.
b (1).
b (2).

Solutions

Expert Solution

Unit cost and WIP at the end :
Job 13-280 13.282 13.281
Material $4,750.00 $5,600.00 $3,800.00
Direct Labour Cost $2,000.00 $800.00 $4,700.00
Overhead:
set up @$20 $400.00 $500.00 $300.00
($20X20) ($20X25) ($20X15)
Machining @$5.10 $416.00 $208.00 $520.00
($5.20X80) ($5.20X40) ($5.20X100)
others (80% of DLC) $1,600.00 $640.00 $3,760.00
Total cost $9,166.00 $7,748.00 $13,080.00
Number of units 200 100
Unit cost $45.83 $77.48
1) Unit cost of Job 13-280 $45.83 per Unit
Unit cost of Job 13-282 $77.48 Per Unit
2) WIP inventory at the end = $13080
3) Journal entries:
Date Accounts Titles Debit $ Credit $
a Finished Goods Inventory $16,914.00
Work in Process inventory $16,914.00
b1 Accounts Receivable $13,749.00
Sales $13,749.00
(=9166*150%)
b2 Cost of goods sold $9,166.00
Finished Goods Inventory $9,166.00

Related Solutions

Unit Cost, Ending Work-in-Process Inventory, Journal Entries During August, Skyler Company worked on three jobs. Data...
Unit Cost, Ending Work-in-Process Inventory, Journal Entries During August, Skyler Company worked on three jobs. Data relating to these three jobs follow: Job 39 Job 40 Job 41 Units in each order 60 100 80 Units sold — 100 — Materials requisitioned $700 $680 $800 Direct labor hours 360 400 200 Direct labor cost $1,980 $2,480 $1,240 Overhead is assigned on the basis of direct labor hours at a rate of $2.30 per direct labor hour. During August, Jobs 39...
ABC Company uses a traditional costing system. Management is considering switching to an activity-based costing system....
ABC Company uses a traditional costing system. Management is considering switching to an activity-based costing system. What steps must Star take in initiating an activity-based costing system? Need unique answer
As you might imagine the ABC Tank Manufacturing Company uses an activity-based costing system. ABC has...
As you might imagine the ABC Tank Manufacturing Company uses an activity-based costing system. ABC has given you the following data that is used in its activity-based costing system: Overhead Costs Wages and salaries $ 348,000 Other overhead costs 193,000 Total overhead costs $ 541,000 Activity Cost Pool Activity Measure Total Activity Direct labor support Number of direct labor-hours 10,500 DLHs Order processing Number of orders 480 orders Customer support Number of customers 105 customers Other This is an organization-sustaining...
Weighted Average Method, Journal Entries Muskoge Company uses a process-costing system. The company manufactures a product...
Weighted Average Method, Journal Entries Muskoge Company uses a process-costing system. The company manufactures a product that is processed in two departments: Molding and Assembly. In the Molding Department, direct materials are added at the beginning of the process; in the Assembly Department, additional direct materials are added at the end of the process. In both departments, conversion costs are incurred uniformly throughout the process. As work is completed, it is transferred out. The following table summarizes the production activity...
SCS Co. uses activity-based costing in their manufacturing process. The company produces two products, ABC and...
SCS Co. uses activity-based costing in their manufacturing process. The company produces two products, ABC and XYZ. SCS has provided their costing department the following information from this year’s budget relating to the production of these two products: ABC XYZ Units to be produced 4,000 6,000 Machine-hours expected 100 200 Direct labor-hours expected 200 300 Materials handling (number of moves) 60 70 Machine setups (number of setups) 20 15 The following costs are expected to be incurred throughout the year,...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $270,000 Other overheard $2,304,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,800 12,600 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $322,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $420,000 Other overheard $5,208,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 4,200 29,400 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $720,000 Other overheard $2,160,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 12,000 3,000 Oven hours 1,800 12,600 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $870,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 12,000 3,000 Oven hours 5,000 35,000 Required: Round your answers to the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT