Question

In: Finance

Scenario Analysis. Automatic Transmissions, Inc., has the following estimates for its new gear assembly project; price...

Scenario Analysis. Automatic Transmissions, Inc., has the following estimates for its new gear assembly project; price = $1,070 per unit; variable cost = $290 per unit; fixed costs = $4.8 million; quantity = 70,000 units. Suppose the company believes all of its estimates are accurate only to within + / - 15 percent. What values should the company use for the four variables given here when it performs the best –case scenario analysis? What about the worst-case scenario? Hint: Use the top part only of the NPV template. Also review the scenario analysis of the presentation within this folder.

Scenario

Pappy's Potato has come up with a new product, the Potato Pet (they are freeze-died to last longer). Pappy's paid $120,000 for a marketing survey to determine the viability of the product. It is felt that Potato pet will generate sales of $725,000 per year. The fixed costs associated with this will be $187,000 per year, and variable costs wil amount to 20 percent of sales. The equipment necessary for production of the Potato pet will cost $835,000 and will be depreicated in a straight-line manner for the four years of the product life (as with all fads, it is felt that sales will end quickly). This is the only intial cost for the production.. Pappy's is in a 40% tax bracket and has a required return of 13 percent. Calculate the payback period, NPV and IRR.

Solutions

Expert Solution

Best Case:

Compute the expected selling price, using the equation as shown below:

Expected selling price = Current price*(1 + Increase)

                                     = $1,070*(1 + 0.15)

                                     = $1,230.50

Hence, the expected selling price is $1,230.50.

Compute the expected variable cost, using the equation as shown below:

Expected variable cost = Current cost*(1 – Decrease)

                                     = $290*(1 - 0.15)

                                     = $246.50

Hence, the expected variable cost is $246.50.

Compute the expected fixed cost, using the equation as shown below:

Expected fixed cost = Fixed cost*(1 – Decrease)

                                 = $4,800,000*(1 – 0.15)

                               = $4,080,000

Hence, the expected fixed cost is $4,080,000.

Compute the expected quantity, using the equation as shown below:

Expected quantity = Quantity*(1 + Increase)

                              = 70,000*(1 + 0.15)

                              = 80,500

Hence, the expected quantity is 80,500.

Worst Case:

Compute the expected selling price, using the equation as shown below:

Expected selling price = Current price*(1 – Decrease)

                                     = $1,070*(1 - 0.15)

                                     = $909.50

Hence, the expected selling price is $909.50.

Compute the expected variable cost, using the equation as shown below:

Expected variable cost = Current cost*(1 + Increase)

                                     = $290*(1 + 0.15)

                                     = $333.50

Hence, the expected variable cost is $333.50.

Compute the expected fixed cost, using the equation as shown below:

Expected fixed cost = Fixed cost*(1 + Increase)

                                 = $4,800,000*(1 + 0.15)

                               = $5,520,000

Hence, the expected fixed cost is $5,520,000.

Compute the expected quantity, using the equation as shown below:

Expected quantity = Quantity*(1 - Decrease)

                              = 70,000*(1 - 0.15)

                              = 59,500

Hence, the expected quantity is 59,500.


Related Solutions

Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100 per unit; variable costs = $620 per unit; fixed costs = $4.4 million; quantity = 92,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent? Scenario Units Sales Unit Price Unit Variable cost Fixed Costs Base $ $ $
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,600...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,600 per unit; variable costs = $320 per unit; fixed costs = $2.7 million; quantity = 78,000 units. Suppose the company believes all of its estimates are accurate only to within ±10 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario?   
Johnson, Schaub and Shiffler, Inc., has the following estimates for its electric car roadster project: price...
Johnson, Schaub and Shiffler, Inc., has the following estimates for its electric car roadster project: price = $140,000 per unit; variable costs = $75,000 per unit; fixed costs = $62,000,000; quantity = 2,700 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. Enter the values the company should use for the four variables given here when it performs its base-, best-, and worst-case scenario analysis
Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates...
Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$36 million     Below average 0.20...
Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates...
Scenario Analysis Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis: Economic Scenario Probability of Outcome NPV Recession 0.05 -$60 million Below average 0.20...
Best Why Inc. is considering a new project that consists of buying an automatic dispenser that...
Best Why Inc. is considering a new project that consists of buying an automatic dispenser that will have a useful life of 8 years. The project's initial cost is $52644.09. The project is expected to generate benefits of $24,000 per year for the first 4 years while it will only generate 12,000 per year for the next 4 years. In addition, the O&M costs of this project will be $8,000 per year for the first 3 years, $7,000 per year...
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project....
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project. The project will last 5 years and requires Gallatin to purchase a machine with a cost of $335,200, a 5-year life and no salvage value. Annual cash sales $ 350,000 Annual out-of-pocket cash expenses $ 250,000 Annual depreciation on equipment $ 67,040 Initial cost of equipment $ 335,200             a. Compute the payback period for the investment b. Compute the investment's approximate IRR c....
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project....
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project. The project will last 5 years and requires Gallatin to purchase a machine with a cost of $335,200, a 5-year life and no salvage value. Annual cash sales $ 350,000 Annual out-of-pocket cash expenses $ 250,000 Annual depreciation on equipment $ 67,040 Initial cost of equipment $ 335,200 a.         Compute the payback period for the investment b.         Compute the investment’s approximate IRR c.         Compute...
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence...
Problem #4 PERT Analysis: Consider the project with the following estimates for activity times and precedence relationships (be sure to use the triple time estimate). All times are in days: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 6 --- B 5 7 10 --- C 2 3 11 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6...
A financial analyst has been following Davis Inc., a new high-tech firm. He estimates that the...
A financial analyst has been following Davis Inc., a new high-tech firm. He estimates that the current risk-free rate (rF) is 6.25%, the market risk premium (rM - rF) is 5%, and the firm’s beta is 1.75. The current dividend just paid (D0) is $1.00. The analyst estimates that the company’s dividend will grow at a rate of 25% this year, 20% next year, and 15% the following year. After three years the dividend is expected to grow at a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT