In: Accounting
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100 per unit; variable costs = $620 per unit; fixed costs = $4.4 million; quantity = 92,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent? Scenario Units Sales Unit Price Unit Variable cost Fixed Costs Base $ $ $
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you. | |||||||||||||
Unit Sales | Unit Price | Unit VC | Fixed Cost | ||||||||||
Scenario | Calculation | Units | Calculation | $ | Calculation | $ | Calculation | $ | |||||
Base | $ 92,000 | $ 3,100 | $ 620 | $ 4,400,000 | |||||||||
Best | 92000+15% | $ 105,800 | 3100+15% | $ 3,565 | 620-15% | $ 527 | 4400000-15% | $ 3,740,000 | |||||
Worst | 92000-15% | $ 78,200 | 3100-15% | $ 2,635 | 620+15% | $ 713 | 4400000+15% | $ 5,060,000 | |||||