Question

In: Accounting

Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100...

Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100 per unit; variable costs = $620 per unit; fixed costs = $4.4 million; quantity = 92,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent? Scenario Units Sales Unit Price Unit Variable cost Fixed Costs Base $ $ $

Solutions

Expert Solution

Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.
Unit Sales Unit Price Unit VC Fixed Cost
Scenario Calculation Units Calculation $ Calculation $ Calculation $
Base $       92,000 $       3,100 $        620 $       4,400,000
Best 92000+15% $     105,800 3100+15% $       3,565 620-15% $        527 4400000-15% $       3,740,000
Worst 92000-15% $       78,200 3100-15% $       2,635 620+15% $        713 4400000+15% $       5,060,000

Related Solutions

Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,600...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,600 per unit; variable costs = $320 per unit; fixed costs = $2.7 million; quantity = 78,000 units. Suppose the company believes all of its estimates are accurate only to within ±10 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario?   
Johnson, Schaub and Shiffler, Inc., has the following estimates for its electric car roadster project: price...
Johnson, Schaub and Shiffler, Inc., has the following estimates for its electric car roadster project: price = $140,000 per unit; variable costs = $75,000 per unit; fixed costs = $62,000,000; quantity = 2,700 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. Enter the values the company should use for the four variables given here when it performs its base-, best-, and worst-case scenario analysis
During the year, Sloan Inc. began a project to construct new corporate headquarters. Sloan purchased land...
During the year, Sloan Inc. began a project to construct new corporate headquarters. Sloan purchased land with an existing building for $750,000. The land was valued at $700,000 and the building at $50,000. Sloan planned to demolish the building and construct a new office building on the site. 1. Classify as land and do not depreciate. 2. Classify as building and depreciate. 3. Expense. 4. Capitalized 5. Expensed as a period cost Purchase of land for $700,000 Interest of $147,000...
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project....
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project. The project will last 5 years and requires Gallatin to purchase a machine with a cost of $335,200, a 5-year life and no salvage value. Annual cash sales $ 350,000 Annual out-of-pocket cash expenses $ 250,000 Annual depreciation on equipment $ 67,040 Initial cost of equipment $ 335,200             a. Compute the payback period for the investment b. Compute the investment's approximate IRR c....
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project....
1. Gallatin, Inc., has assembled the estimates shown below relating to a proposed new investment project. The project will last 5 years and requires Gallatin to purchase a machine with a cost of $335,200, a 5-year life and no salvage value. Annual cash sales $ 350,000 Annual out-of-pocket cash expenses $ 250,000 Annual depreciation on equipment $ 67,040 Initial cost of equipment $ 335,200 a.         Compute the payback period for the investment b.         Compute the investment’s approximate IRR c.         Compute...
Consider the new product launch project that Kerring-Sloan is considering. The PTA-09 project is a proposed...
Consider the new product launch project that Kerring-Sloan is considering. The PTA-09 project is a proposed EV Fishing Boat that requires an initial investment of $2,600,000 in production infrastructure in 2020 (year 0) for production to begin in 2021. Cash flows for the project for years 0 - 8 are shown below. The introduction of a new product at year 9 will terminate further cash flows from this project. Assume a cost of capital of 9% where necessary to solve...
A plastic gear manufacturer is invstigating a new gear, which the company claims it has a...
A plastic gear manufacturer is invstigating a new gear, which the company claims it has a mean diameter of 12cm with a standard deviation of .5cm. The company wishes to test the hypothesis Ho: mu=12 against H1: Mu < 12 using a random sample of 16 specimens. What is the type 1 error if the critical region is defined as x< 11.5cm? Fine B for the case in which the true mean diameter is 11.25cs Fine B for the case...
C.A.S. has two production departments, Assembly and Customizing. The company used the following estimates to calculate...
C.A.S. has two production departments, Assembly and Customizing. The company used the following estimates to calculate predetermined overhead rates:                                                                                                 Assembly                    Customizing Total machine hours                                                               19,000                         15,000 Direct labor hours                                                                   4,000                           6,000 Fixed manufacturing overhead                                               $100,700                     $63,000 Variable manufacturing overhead per machine hour             $2.00                           - Variable manufacturing overhead per labor hour                   -                                   $3.90 Overhead rate based on:                                                         Machine hour              Labor hour 1. What is the predetermined overhead rate for the Assembly department? 2. What is the predetermined overhead...
A financial analyst has been following Davis Inc., a new high-tech firm. He estimates that the...
A financial analyst has been following Davis Inc., a new high-tech firm. He estimates that the current risk-free rate (rF) is 6.25%, the market risk premium (rM - rF) is 5%, and the firm’s beta is 1.75. The current dividend just paid (D0) is $1.00. The analyst estimates that the company’s dividend will grow at a rate of 25% this year, 20% next year, and 15% the following year. After three years the dividend is expected to grow at a...
A financial analyst has been following Davis Inc., a new high-tech firm. He estimates that the...
A financial analyst has been following Davis Inc., a new high-tech firm. He estimates that the current risk-free rate (rF) is 6.25%, the market risk premium (rM - rF) is 5%, and the firm’s beta is 1.75. The current dividend just paid (D0) is $1.00. The analyst estimates that the company’s dividend will grow at a rate of 25% this year, 20% next year, and 15% the following year. After three years the dividend is expected to grow at a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT