Question

In: Finance

Empire Manufacturing is considering two mutually exclusive projects with the following cash flows. Empire’s cost of...

Empire Manufacturing is considering two mutually exclusive projects with the following cash flows. Empire’s cost of capital is 10 percent.

Year                   Project A               Project B

                                    0          (485,000)                     (485,000)

                                    1                     0                      155,000

                                    2                     0                      152,000        

                                    3                     0                      131,000

                                    4                     0                      110,000

                                    5                     0                      108,000        

                                    6      1,000,000                           98,500

a) Compute the NPV, IRR and Payback Period for each project. Assuming the projects were mutually exclusive:

b) If the payback criterion was four years, which project would be chosen?

c) If the hurdle rate was 13% which project would be chosen based on IRR?

d) Which project would be chosen if NPV was the decision method? Assuming the projects were independent:

e) If the payback criterion was four years, which project would be chosen?

f) If the hurdle rate was 13% which project would be chosen based on IRR?

g) Which project would be chosen based on NPV?

Solutions

Expert Solution

EXCEL FORMULA:


Related Solutions

Jamison is considering two mutually exclusive projects with the following cash flows and the cost of...
Jamison is considering two mutually exclusive projects with the following cash flows and the cost of capital of 10%. Year XX YY 0 -$1,000 -$1,200 1 $800 $700 2 $800 $700 3 $700 a) Based on Annualized NPV, which project would you choose? Why ANPV is better than NPV in this case.?
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $300 $400 $700 Project Y -$1,000 $900 $100 $55 $45 The projects are equally risky, and their WACC is 10%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations.
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $100 $300 $400 $650 Project Y -$1,000 $1,000 $110 $45 $55 The projects are equally risky, and their WACC is 10%. What is the MIRR of the project that maximizes shareholder value? Do not round intermediate calculations. Round your answer to two decimal places.   %_____
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $280 $400 $700 Project Y -$1,000 $1,100 $110 $45 $50 The projects are equally risky, and their WACC is 11%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations.
The Winston Co. is considering two mutually exclusive projects with the following cash flows:                           &nbs
The Winston Co. is considering two mutually exclusive projects with the following cash flows:                                                                         Project A               Project B                                     Year                         Cash Flow             Cash Flow                                        0                              -$75,000               -$60,000                                        1                              $30,000                $25,000                                        2                              $35,000                $30,000                                        3                              $35,000                $25,000            B-1 what is the IRR of project A?            B-2 What is the IRR of project B?            B-3 Based on the IRR rule, which project should be accepted and why?            B-4...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $320 $400 $750 Project Y -$1,000 $1,000 $90 $45 $50 The projects are equally risky, and their WACC is 11%. What is the MIRR of the project that maximizes shareholder value? Do not round intermediate calculations. Round your answer to two decimal places
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $90 $300 $370 $650 Project Y -$1,000 $900 $100 $50 $45 The projects are equally risky, and their WACC is 10%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations. ____%
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $280 $370 $650 Project Y -$1,000 $1,100 $100 $55 $45 The projects are equally risky, and their WACC is 8%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations. %
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: Project X: CF0= -$1,000, CF1= $110, CF2= $300, CF3= $370, CF4= $750 Project Y: CF0= -$1,000, CF1= $900, CF2= $110, CF3= $50, CF4= $50 The projects are equally risky, and their WACC is 13%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations.
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT