McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...

McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2017 and completed in 2018. Cost and other data are presented below:

                                                                        2017                2018

Costs incurred during the year                           $1,500               $1,300

Estimated costs to complete                                1,200                        0

Billings during the year                                      1,200                  1,300

Cash collections during the year                          1,000                  1,500

1. Compute the amount of revenue and gross profit recognized during 2017 and 2018.

2. Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Prepare all journal entries for 2017 and 2018 to record costs, billings, collections, profit (loss) recognition, and transferring of the asset when construction is complete. Round your answers to the nearest whole dollar.

3. Assume that McCombs recognizes revenue upon project completion according to the percentage of completion. Prepare all journal entries for 2017 and 2018 to record costs, billings, collections, and profit (loss) recognition, and transferring of the asset when construction is complete. Round your answers to the nearest whole dollar.

Solutions

Expert Solution

1) 2017 2017 2018 2018
% of completion 1500/(1200+1500) 0.56 1300/1300 1
revenue 2500*0.56 1400 2500-1400 1100
Gross profit 1400-1500 -100 1100-1300 -200
2. Journal Entries FOR 2017:
To record costs:
Debit WIP $1,500
Credit Accounts Payable $1,500
To record billings:
Debit Accounts Receivable 1200
Credit Progress Billings 1200
To record collections:
Debit Cash 1000
Credit Accounts Receivable 1000
To record loss recognition:
Debit Progress Billings 1400
Credit Revenue 1400
To record COGS:
Debit Cost of Services 1500
Credit WIP 1500
Journal Entries FOR 2018:
To record costs:
Debit WIP $1,300
Credit Accounts Payable $1,300
To record billings:
Debit Accounts Receivable 1300
Credit Progress Billings 1300
To record collections:
Debit Cash 1500
Credit Accounts Receivable 1500
To record loss recognition:
Debit Progress Billings 1100
Credit Revenue 1100
To record COGS:
Debit Cost of Services 1300
Credit WIP 1300
3. Journal Entries FOR 2017:
To record costs:
Debit WIP $1,500
Credit Accounts Payable $1,500
To record billings:
Debit Accounts Receivable 1200
Credit Progress Billings 1200
To record collections:
Debit Cash 1000
Credit Accounts Receivable 1000
Journal Entries FOR 2018:
To record costs:
Debit WIP $1,300
Credit Accounts Payable $1,300
To record billings:
Debit Accounts Receivable 1300
Credit Progress Billings 1300
To record collections:
Debit Cash 1500
Credit Accounts Receivable 1500
To record loss recognition:
Debit Progress Billings 2500
Credit Revenue 2500
(1400+1100)
To record COGS:
Debit Cost of Services 2800
Credit WIP 2800
(1500+1300)

Related Solutions

McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                         2017                2018 Costs incurred during the year                           $1,500               $1,300 Estimated costs to complete                                1,200                        0 Billings during the year                                      1,200                  1,300 Cash collections during the year                          1,000                  1,500 1.Compute the amount of revenue and gross profit recognized during 2017 and 2018. 2.Assume that McCombs recognizes revenue on this contract over...
McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $1,500,000 $1,300,000 Estimated costs to complete 1,200,000 0 Billings during the year 1,200,000 1,300,000 Cash collections during the year 1,000,000 1,500,000 Part 1: Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: 2014 2015 2016 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000 Collections to date 2,000,000 3,500,000 5,500,000 Instructions Fill in...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work on this contract began in 2013 and the financial data pertaining to this contract is available here. Cost incurred till Dec.31, 2013 $1,080,000 Billings made to City $1,000,000 Amount collected from City $ 750,000 The estimated future cost to complete this contract is $3,240,000. (a) Prepare Chicago contractors 2013 journal entries using COMPLETED CONTRACT method. (b) Show how the contract accounts will appear in...
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is...
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is incomplete and the contractor is confused about how to transfer profit or loss in the P/L account. Being a student of cost accounting, you are required to state the rules regarding the transfer of profits to profit and loss account in case of incomplete contracts( 0%,20%,50%,75%,90 %) to the contractor.
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract provided for progress payments. RCL’s accounting year ends December 31. Work began under the contract on August 1, 2019, and was completed on October 31, 2021. RCL uses the percentage-of-completion method to account for this long-term contract. Construction activities are summarized below: 2019 2020 2021 Construction costs incurred to date 180,000 630,000 825,000 Estimated remaining costs to complete 630,000 190,000 0 Progress Billings during...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT