Question

In: Operations Management

The demand for subassembly S is 110 units in week 7. Each unit of S requires...

The demand for subassembly S is

110

units in week 7. Each unit of S requires

2

unitss

of T and

1

unitnothing

of U. Each unit of T requires

1

unitnothing

of​ V,

2

unitss

of​ W, and

1

unitnothing

of X.​ Finally, each unit of U requires

1

unitnothing

of Y and

2

units of Z. One firm manufactures all items. It takes 2 weeks to make​ S,

2

weekss

to make​ T, 2 weeks to make​ U,

1

weeknothing

to make​ V,

2

weeks to make​ W,

2

weekss

to make​ X, 2 weeks to make​ Y, and

2

weekss

to make Z.

LOADING...

Click the icon to view the product structure and the​ time-phased product structure.

In addition to

110

units of​ S, there is also a demand for

20

units of​ U, which is a component of S. The

20

units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change ​(type 0 if the input box is not​ used).

Week

Lead Time

Item

1

2

3

4

5

6

7

​(weeks)

S

Gross req

0

0

0

0

0

0

110

  Order release

0

0

0

0

110

0

0

2

T

Gross req

nothing

nothing

nothing

nothing

nothing

nothing

nothing

  Order release

nothing

nothing

nothing

nothing

nothing

nothing

nothing

2

Solutions

Expert Solution

Below is the screenshot of the MRP schedule -

Below is the screenshot of the formula applied -


Related Solutions

The demand for subassembly S is 110 units in week 7. Each unit of S requires...
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks make U, 2...
The demand for subassembly S is 100 units in week 7. Each unit of S requires...
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of​ V, 1 unit of​ W, and 1 unit of X.​ Finally, each unit of U...
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...
The forecast for each week is 50 units each week and customer orders are as shown...
The forecast for each week is 50 units each week and customer orders are as shown in the table below. The beginning inventory level is 0 and the production lot size is 75. Determine Available-to-promise inventory under the condition that “schedule production when the projected on-hand inventory would be negative without production”. June    July 1 2 3 4 1 2 3 4 Forecast 50 50 50 50 50 50 50 50 Customer order (committed) 52 35 20 12
E25-1 Parsons Company is planning to produce 2,000 units of product in 2017. Each unit requires...
E25-1 Parsons Company is planning to produce 2,000 units of product in 2017. Each unit requires 3 pounds of materials at $5 per pound and a half-hour of labor at $16 per hour. The overhead rate is 70% of direct labor. Instructions (a) Compute the budgeted amounts for 2017 for direct materials to be used, direct labor, and applied overhead. (b) Compute the standard cost of one unit of product. (c) What are the potential advantages to a corporation of...
Store is open 7 days/week. orders units every other week. maintains safety stock of 120 units....
Store is open 7 days/week. orders units every other week. maintains safety stock of 120 units. weekly sales is 800 units. lead time is 3 days. current inventory is 350 units, how many units should it order?
Demand for a product is 400 units per week. Lead time is one week. When inventory...
Demand for a product is 400 units per week. Lead time is one week. When inventory level reached 1000 units, the material manager orders 6 weeks of demand. Compute the average inventory. 1000 2000 3000 1800 None of the above
The Week 7 Case Study Assignment is an individual assignment that requires you to analyze a...
The Week 7 Case Study Assignment is an individual assignment that requires you to analyze a select group of alternative industries to determine which is most likely to perform best over the next 12 months. Factors to consider when comparing the industry groups include how the current and prospective economic conditions over the next year will affect them and the current and prospective domestic and global supply and demand conditions in their markets. Review briefly the list of industries below...
Each unit of A is composed of one unit of B, two units of C, and...
Each unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 10 units, respectively. Item B has a scheduled receipt of 10 units in Period 1, and C has a scheduled receipt of 50 units in Period 1. Lot-for-lot (L4L) lot sizing is used...
The Company manufactures paring knives and pocket knives. Each paring knife requires 3​ labor-hours, 7 units...
The Company manufactures paring knives and pocket knives. Each paring knife requires 3​ labor-hours, 7 units of​ steel, and 4 units of wood. Each pocket knife requires 6​ labor-hours, 5 units of​ steel, and 3 units of wood. The profit on each paring knife is​ $3, and the profit on each pocket knife is​ $5. Each day the company has available 96 ​labor-hours, 134 units of​ steel, and 120 units of wood. Suppose that the number of​ labor-hours that are...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT