The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
On-hand inventory information is given as below:
ITEM |
ON-HAND INVENTORY |
ITEM |
ON-HAND INVENTORY |
S |
20 |
W |
30 |
T |
20 |
X |
25 |
U |
40 |
Y |
240 |
V |
30 |
Z |
40 |