Demand for a product is 400 units per week. Lead time is one week. When inventory...

Demand for a product is 400 units per week. Lead time is one week. When inventory level reached 1000 units, the material manager orders 6 weeks of demand. Compute the average inventory.

1000

2000

3000

1800

None of the above

Solutions

Expert Solution

Order Quantity = 6 weeks of demand

One week of demand = 400 units

6 weeks of demand = 400*6 = 2,400 units

Average Inventory = Order quantity/2 =2400/2 = 1200 units

None of the above is true


Related Solutions

Demand for hotdogs is 500 units per week. Lead time is one week. When inventory level...
Demand for hotdogs is 500 units per week. Lead time is one week. When inventory level reached 1500 units, the regional director orders 8 weeks of demand. Compute the average inventory. A. 1000 B. 2000 C. 3000 D. 4000 E. None of the above Demand for hamburgers is 400 units per week. Lead time is one week. When inventory level reached 1000 units, the regional director orders 6 weeks of demand. Compute the flow time. A .1.5 weeks. B. 3.5...
1. The MAD for a forecast is one unit per week. If the lead time is...
1. The MAD for a forecast is one unit per week. If the lead time is one month, what will be the standard deviation of the forecast error for one month (assuming 4 weeks in a month). Please enter your answer to two decimal places. 2. The MAD for a forecast is one unit per week. If the lead time is one year, what will be the standard deviation of the forecast error for one year (assuming 52 weeks in...
(This is all one question): A firm produces 400 units of output per week and this...
(This is all one question): A firm produces 400 units of output per week and this firms faced with both input and output competitive markets. This produces a revenue of $20,000 per week. The firm could use capital technology (K1) to produce output together with labor in which case each worker would need 2hours to produce 1 unit of output per unit of K1. The firm could use capital technology (K2) in which case the worker would be able to...
Average lead time demand in a warehouse is 24000 units. The standard deviation of lead time...
Average lead time demand in a warehouse is 24000 units. The standard deviation of lead time demand is 5500 units. The warehouse orders 60000 units whenever inventory reaches 28000 units. What is the service level? A) around 72% B) around 81% C) around 77% D) around 89% E) none of the above
1. a) The demand per week for television sets is 1200 units when the price is...
1. a) The demand per week for television sets is 1200 units when the price is $575 each and 800 units when the price is $725 each. Find the demand equation for the sets, assuming that it is linear? b) Suppose a manufacturer of some product will produce 10 units when the price is SR150 each and 6 units when the price is SR70 each. Find the supply equation, assuming it is linear? c) In each of the following, sketch...
Campbell Company had 400 units of product in work in process inventory at the beginning of...
Campbell Company had 400 units of product in work in process inventory at the beginning of the period. It started 1,300 units during the period and transferred 1,100 units to finished goods inventory. The ending work in process inventory was estimated to be 60 percent complete. Cost data for the period follow: Product Costs Beginning balance $ 37,560 Added during period 58,800 Total $ 96,360 Required Calculate the number of equivalent units of production. Calculate the product cost per equivalent...
Minimum order quantity is 500 units, lead time is 1 week. What is/are the Net Requirements for week 8?
Week 7 8 9 10 11 12 Gross Requirements 0 300 400 400 400 200 Scheduled Receipts 500 Projected ending inventory: 100 100 Net requirements ??? Planned Receipts Planned orders Q1: Minimum order quantity is 500 units, lead time is 1 week. What is/are the Net Requirements for week 8? a. 300 units. b. None of these answers is correct. c. 500 units. d. Negative 300 units. e. 0 units. Week 7 8 9 10 11 12 Gross Requirements 0...
A firm produces 400 units of output per week and this firms faced with both input...
A firm produces 400 units of output per week and this firms faced with both input and output competitive markets. This produces a revenue of $20,000 per week. The firm could use capital technology (K1) to produce output together with labor in which case each worker would need 2hours to produce 1 unit of output per unit of K1. The firm could use capital technology (K2) in which case the worker would be able to produce 1 unit of output...
Q5: Minimum order quantity is 500 units, lead time is 1 week. What is/are the Planned Receipts for week 9?
Week 7 8 9 10 11 12 Gross Requirements 0 300 400 400 400 200 Scheduled Receipts 500 Projected ending inventory: 100 100 Net requirements Planned Receipts ??? Planned orders Q5: Minimum order quantity is 500 units, lead time is 1 week. What is/are the Planned Receipts for week 9? a. None of these answers are correct. b. 100 units. c. 0 units. d. 500 units. e. 400 units. Week 7 8 9 10 11 12 Gross Requirements 0 300...
P6.3 Marlow Bed and Bath had a beginning inventory of 400 units of Product Kimbo at...
P6.3 Marlow Bed and Bath had a beginning inventory of 400 units of Product Kimbo at a cost of £8 per unit. During the year, purchases were : Feb.20 200 units at £9 May.6   500 units at £10 Aug.12  600 units at £11 Dec.8.   300 units at £12 Marlow uses a periodic inventory system. Sales totaled 1,500 units. Instructions Determine the cost of goods available for sale. Determine (1) the ending inventory and (2) the cost of goods sold under the...