Question

In: Operations Management

The demand for subassembly S is 110 units in week 7. Each unit of S requires...

The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 2 units of V, 2 units of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.

Suppose that in addition to 110 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the net material requirements plan to reflect change.

Construct a new net material requirements plan

Solutions

Expert Solution

Formulas:

Gross requirement of the child item = Planned order release quantity of the parent item as per BOM requirement

Net requirement = Gross Requirement of week – projected on-hand of previous week – Scheduled Receipts of week

Projected on-hand (POH) = Projected on-hand of previous week + Scheduled Receipt of week – Gross Requirement of week + Planned order receipt (PORc) of week

Planned order receipt = if the project-on-hand is negative, place an order.

the New MRP schedule is as follows:

Period

1

2

3

4

5

6

7

Item S

Gross requirements

110

OH = 0

Scheduled receipts

0

LT = 2

Projected available balance

0

SS = 0

Net requirements

1100

Q = L4L

Planned order receipts

110

Planned order releases

110

Period

(2 units for S)

1

2

3

4

5

6

7

Item T

Gross requirements

220

OH = 0

Scheduled receipts

0

LT = 1

Projected available balance

0

SS = 0

Net requirements

220

Q = L4L

Planned order receipts

220

Planned order releases

220

Period

(2 units for S)

1

2

3

4

5

6

7

Item U

Gross requirements

220

30

OH = 0

Scheduled receipts

0

0

LT = 2

Projected available balance

0

0

SS = 0

Net requirements

220

30

Q = L4L

Planned order receipts

220

30

Planned order releases

220

30

Period

2 units for T

1

2

3

4

5

6

7

Item V

Gross requirements

0

0

0

440

OH = 0

Scheduled receipts

0

LT = 2

Projected available balance

0

SS = 0

Net requirements

440

Q = L4L

Planned order receipts

440

Planned order releases

440

Period

2 units for T

1

2

3

4

5

6

7

Item W

Gross requirements

0

0

0

440

0

OH = 0

Scheduled receipts

0

LT = 3

Projected available balance

0

SS = 0

Net requirements

440

Q = L4L

Planned order receipts

440

Planned order releases

440

Period

2 unit for T

1

2

3

4

5

6

7

Item X

Gross requirements

0

0

0

440

0

OH = 0

Scheduled receipts

0

LT = 1

Projected available balance

0

SS = 0

Net requirements

440

Q = L4L

Planned order receipts

440

Planned order releases

440

Period

1 unit for U

1

2

3

4

5

6

7

Item Y

Gross requirements

0

0

220

30

0

0

0

OH = 0

Scheduled receipts

0

0

LT = 2

Projected available balance

0

0

SS = 0

Net requirements

220

30

Q = L4L

Planned order receipts

220

30

Planned order releases

220

30

Period

3 unit for U

1

2

3

4

5

6

7

Item Z

Gross requirements

0

0

660

90

0

0

0

OH = 0

Scheduled receipts

0

0

LT = 1

Projected available balance

0

0

SS = 0

Net requirements

660

90

Q = L4L

Planned order receipts

660

90

Planned order releases

660

90


Related Solutions

The demand for subassembly S is 100 units in week 7. Each unit of S requires...
The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of​ V, 1 unit of​ W, and 1 unit of X.​ Finally, each unit of U...
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,...
The forecast for each week is 50 units each week and customer orders are as shown...
The forecast for each week is 50 units each week and customer orders are as shown in the table below. The beginning inventory level is 0 and the production lot size is 75. Determine Available-to-promise inventory under the condition that “schedule production when the projected on-hand inventory would be negative without production”. June    July 1 2 3 4 1 2 3 4 Forecast 50 50 50 50 50 50 50 50 Customer order (committed) 52 35 20 12
E25-1 Parsons Company is planning to produce 2,000 units of product in 2017. Each unit requires...
E25-1 Parsons Company is planning to produce 2,000 units of product in 2017. Each unit requires 3 pounds of materials at $5 per pound and a half-hour of labor at $16 per hour. The overhead rate is 70% of direct labor. Instructions (a) Compute the budgeted amounts for 2017 for direct materials to be used, direct labor, and applied overhead. (b) Compute the standard cost of one unit of product. (c) What are the potential advantages to a corporation of...
Store is open 7 days/week. orders units every other week. maintains safety stock of 120 units....
Store is open 7 days/week. orders units every other week. maintains safety stock of 120 units. weekly sales is 800 units. lead time is 3 days. current inventory is 350 units, how many units should it order?
Demand for a product is 400 units per week. Lead time is one week. When inventory...
Demand for a product is 400 units per week. Lead time is one week. When inventory level reached 1000 units, the material manager orders 6 weeks of demand. Compute the average inventory. 1000 2000 3000 1800 None of the above
The Week 7 Case Study Assignment is an individual assignment that requires you to analyze a...
The Week 7 Case Study Assignment is an individual assignment that requires you to analyze a select group of alternative industries to determine which is most likely to perform best over the next 12 months. Factors to consider when comparing the industry groups include how the current and prospective economic conditions over the next year will affect them and the current and prospective domestic and global supply and demand conditions in their markets. Review briefly the list of industries below...
The Company manufactures paring knives and pocket knives. Each paring knife requires 3​ labor-hours, 7 units...
The Company manufactures paring knives and pocket knives. Each paring knife requires 3​ labor-hours, 7 units of​ steel, and 4 units of wood. Each pocket knife requires 6​ labor-hours, 5 units of​ steel, and 3 units of wood. The profit on each paring knife is​ $3, and the profit on each pocket knife is​ $5. Each day the company has available 96 ​labor-hours, 134 units of​ steel, and 120 units of wood. Suppose that the number of​ labor-hours that are...
Demand for hotdogs is 500 units per week. Lead time is one week. When inventory level...
Demand for hotdogs is 500 units per week. Lead time is one week. When inventory level reached 1500 units, the regional director orders 8 weeks of demand. Compute the average inventory. A. 1000 B. 2000 C. 3000 D. 4000 E. None of the above Demand for hamburgers is 400 units per week. Lead time is one week. When inventory level reached 1000 units, the regional director orders 6 weeks of demand. Compute the flow time. A .1.5 weeks. B. 3.5...
MD ORDER: Insulin titration of 1 unit to 3 units/hr to keep patient's blood sugar <110....
MD ORDER: Insulin titration of 1 unit to 3 units/hr to keep patient's blood sugar <110. Nurse must check blood sugar every 2 hrs. The insulin IV solution is 80 units in 1L 0.9NS. a. At what infusion rate would yo begin this titration of insulin (mL/hr)? b. The infusion started at 1300 hrs. At 1445 hrs blood sugar is 150. Do you increase, decrease or do nothing to the titration? c. At 1700 hrs the patient's blood sugar is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT