Question

In: Finance

Consider two mutually exclusive projects with the following cash flows: Project A Project B Time 0...

Consider two mutually exclusive projects with the following cash flows:

Project A

Project B

Time 0

-10,000

-10,000

Time 1

5,000

4,000

Time 2

5,000

3,000

Time 3

2,000

6,000

At a cost of capital of 8%, which project should the company choose? Explain which decision rule you should use in this case.

Solutions

Expert Solution

Net Present Value (NPV) of PROJECT-A

Year

Annual cash inflow ($)

Present Value factor at 8.00%

Present Value of Annual cash inflow ($)

1

5,000

0.92593

4,629.63

2

5,000

0.85734

4,286.69

3

2,000

0.79383

1,587.66

TOTAL

10,503.99

Net Present Value = Present Value of annual cash inflows - Initial Investment

= $10,503.99 - $10,000

= $503.99

Net Present Value (NPV) of PROJECT-B

Year

Annual cash inflow ($)

Present Value factor at 8.00%

Present Value of Annual cash inflow ($)

1

4,000

0.92593

3,703.70

2

3,000

0.85734

2,572.02

3

6,000

0.79383

4,762.99

TOTAL

11,038.71

Net Present Value = Present Value of annual cash inflows - Initial Investment

= $11,038.71 - $10,000

= $1,038.71

DECISION

Evaluation of Investment proposal using NPV Decision Rule

If the Projects are mutually exclusive, then the Project with the higher Net Present Value should be selected. Here, the Project-A has the higher NPV of $1,038.71 as compared to the NPV of Project-B. Therefore, the firm should “Accept Project-A”

NOTE

The formula for calculating the Present Value Inflow Factor (PVIF) is [1 / (1 + r)n], where “r” is the Discount Rate/Cost of capital and “n” is the number of years.


Related Solutions

Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
2. Consider the following cash flows on two mutually exclusive projects: The cash flows of project...
2. Consider the following cash flows on two mutually exclusive projects: The cash flows of project A are expressed in real terms while those of Popject B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 4 percent. Which project should you choose? Project A (real cash flow) Project B (nominal cash flow) Year 0            (67,000)                 (74,000) 1             34,000                  34,000 2             37,000                  45,000 3            ...
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$ 364,000 –$ 52,000 1 46,000 25,000 2 68,000 22,000 3 68,000 21,500 4 458,000 17,500 Whichever project you choose, if any, you require a return of 11 percent on your investment. a-1. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)    a-2. If you apply the payback criterion, which...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$199,124        –$15,993          1 25,800        5,691          2 51,000        8,855          3 54,000        13,391          4 416,000        8,695             Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A?     b. What is the payback period for Project B? c. What is the discounted...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$ 360,000 –$ 45,000 1 35,000 23,000 2 55,000 21,000 3 55,000 18,500 4 430,000 13,600    Whichever project you choose, if any, you require a 14 percent return on your investment.    a-1 What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)    Payback period   Project A years     Project...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$260,730        –$15,011          1 27,800        4,942          2 56,000        8,023          3 55,000        13,040          4 426,000        9,138             Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A?     b. What is the payback period for Project B? c. What is the discounted...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...
Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$251,835        –$15,247          1 25,100        4,828          2 55,000        8,358          3 50,000        13,472          4 385,000        8,102             Whichever project you choose, if any, you require a 6 percent return on your investment. a.What is the discounted payback period for Project A? b.What is the discounted payback period for Project B?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT