In: Finance
Consider the following two mutually exclusive projects: |
Year | Cash Flow (A) |
Cash Flow (B) |
|||||
0 | –$ | 360,000 | –$ | 45,000 | |||
1 | 35,000 | 23,000 | |||||
2 | 55,000 | 21,000 | |||||
3 | 55,000 | 18,500 | |||||
4 | 430,000 | 13,600 | |||||
Whichever project you choose, if any, you require a 14 percent return on your investment. |
a-1 |
What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) |
Payback period | ||
Project A | years | |
Project B | years | |
a-2 | If you apply the payback criterion, which investment will you choose? | ||||
|
b-1 |
What is the discounted payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) |
Discounted payback period | ||
Project A | years | |
Project B | years | |
b-2 | If you apply the discounted payback criterion, which investment will you choose? | ||||
|
c-1 |
What is the NPV for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) |
NPV | ||
Project A | $ | |
Project B | $ | |
c-2 | If you apply the NPV criterion, which investment will you choose? | ||||
|
d-1 |
What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) |
IRR | ||
Project A | % | |
Project B | % | |
d-2 | If you apply the IRR criterion, which investment will you choose? | ||||
|
e-1 |
What is the profitability index for each project? (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) |
Profitability index | ||
Project A | ||
Project B | ||
e-2 | If you apply the profitability index criterion, which investment will you choose? | ||||
|
f. | Based on your answers in (a) through (e), which project will you finally choose? |
(Click to select)Project AProject B |
a1
Payback period is the time taken for the cumulative cash flows to become 0
Hence, Project A Payback period = 3.50 years
Project B Payback period = 2.05 years
a2)
If you apply the payback criterion, you would choose Project B
This is because Project B has a lower payback period and hence lesser time required to recover investments.
b1)
Discounted payback period is the time taken for the cumulative discounted cash flows to become 0
Hence, Project A Discounted payback period = 3.98 years
Project B Discounted payback period = 2.69 years
b2)
If you apply the Discounted payback period criterion, you would choose Project B
This is because Project B has a lower Discounted payback period and hence lesser time required to recover investments.
c1)
NPV is calculated using NPV function in excel
Project A NPV = $4740.42
Project B NPV = $11873.52
c2)
If you apply the NPV criterion, you would choose Project B
This is because Project B has a higher and positive NPV and more expected present value cash-flow
d1)
Referring to part c1)
Project A IRR= 14.44%
Project B IRR= 27.54%
d2)
If you apply the IRR criterion, you would choose Project B
This is because Project B has a higher IRR and more expected return.
e1) Profitability Index = PV of future cash flows/ Initial investment
Project A profitability index = 1.01
Project B profitability index = 1.26
e2)
If you apply the profitability index criterion, you would choose Project B
This is because Project B has a higher profitability index and hence more expected profitability
f)
Since all the criterion indicates to take up Project B
Project B should be finally choosen