In: Finance
Consider the following two mutually exclusive projects: |
Year | Cash Flow (A) | Cash Flow (B) |
0 | –$199,124 | –$15,993 |
1 | 25,800 | 5,691 |
2 | 51,000 | 8,855 |
3 | 54,000 | 13,391 |
4 | 416,000 | 8,695 |
Whichever project you choose, if any, you require a 6 percent return on your investment. |
a. What is the payback period for Project A? |
b. What is the payback period for Project B? |
c. What is the discounted payback period for Project A? |
d. What is the discounted payback period for Project B? |
e. What is the NPV for Project A? |
f. What is the NPV for Project B ? |
g. What is the IRR for Project A? |
h. What is the IRR for Project B? |
i. What is the profitability index for Project A? |
j. What is the profitability index for Project B |
1. Project A
year cash flow pvf@6% PV cumulative pv
1 25800 0.943 24330 24330
2 51000 0.890 45390 69720
3 54000 0.840 45360 115080
4 416000 0.792 329472 444552
Total cash flow 546800
Total Discounted cash flow 444552
initial invest ment= 199124
a.)Pay back period - Project A= initial investment/ total net cash flow= 199124/546800= 0.364 years
b) Pay back period -Project B
Project B
year cash flow pvf@6% PV cumulative pv
1 5691 0.943 5367 5367
2 8855 0.890 7881 13248
3 13391 0.840 11248 24496
4 8695 0.792 6886 31382
Total cash flow 36632
Total discounted cash flow 31382
initial investment= 15993
pay back period for project B= initial investment/ total net cash flow= 15993/36632= 0.437years
c) discounted pay back period for project A= 199124-115080/329472= 0.26 years
d) discounted pay back period for project B= 15993-13248/11248= 0.24 Years
e) NPV for project A= discounted cash inflows- discounted cash out flow= 444552-199124=245428
f) NPV for project B= discounted cash inflows- discounted cash out flow= 36632-15993= 20639
g) IRR FOR PROJECT A= LR + NPV AT LR/NPV AT LR-NPV AT HR*HR-LR
h)IRR FOR PROJECT B= LR + NPV AT LR/NPV AT LR-NPV AT HR*HR-LR
i) profitability index for Project A= discounted cash inflows/initial investment=444552/199124= 2.23
j)profitability index for Project B= discounted cash inflows/initial investment= 31382/15993 = 1.96
Since NPV is higher as well as profitability index is higher ,also pay back period is lower than Project B- Project A should be chosen