In: Operations Management
The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of
$100100
per unit, inventory carrying costs of
$2525
per unit per month, and zero beginning and ending inventory, evaluate these two plans on an incremental cost basis:Plan A: Produce at a steady rate (equal to minimum requirements) of
1 comma 1001,100
units per month and subcontract additional units at a
$7070
per unit premium cost. Subcontracting capacity is limited to
800800
units per month.
(Enter
all responses as whole
numbers).
Month |
Demand |
Production |
Ending Inventory |
Subcontract (Units) |
|
1 |
July |
13001300 |
1 comma 1001,100 |
00 |
200200 |
2 |
August |
11501150 |
1 comma 1001,100 |
00 |
5050 |
3 |
September |
11001100 |
1 comma 1001,100 |
00 |
00 |
4 |
October |
16001600 |
1 comma 1001,100 |
00 |
500500 |
5 |
November |
19001900 |
1 comma 1001,100 |
00 |
800800 |
6 |
December |
19001900 |
1 comma 1001,100 |
00 |
800800 |
The total cost, excluding normal time labor costs, for Plan A =
$164,500164,500.
(Enter your response as a whole number.)Plan B: Vary the workforce to produce the prior month's demand. The firm produced
1 comma 3001,300
units in June. The cost of hiring additional workers is
$3535
per unit produced. The cost of layoffs is
$6060
per unit cut back.
(Enter
all responses as whole numbers.)Note: Both hiring and layoff costs are incurred in the month of the change (i.e., going from production of
1 comma 3001,300
in July to
13001300
in August requires a layoff (and related costs) of
00
units in August).
Month |
Demand |
Production |
Hire (Units) |
Layoff (Units) |
Ending Inventory |
Stockouts (Units) |
|
1 |
July |
13001300 |
nothing |
nothing |
nothing |
nothing |
nothing |
2 |
August |
11501150 |
nothing |
nothing |
nothing |
nothing |
nothing |
3 |
September |
11001100 |
nothing |
nothing |
nothing |
nothing |
nothing |
4 |
October |
16001600 |
nothing |
nothing |
nothing |
nothing |
nothing |
5 |
November |
19001900 |
nothing |
nothing |
nothing |
nothing |
nothing |
6 |
December |
19001900 |
nothing |
nothing |
nothing |
nothing |
nothing |
Enter your answer in the edit fields and then click Check Answer.
|
Clear All |
Check Answer |
Subcontracting units of July=Demand of July-(ending inventory of June+Production of July) and so on.
=1300-0-1100=200
Total cost of this plan=Total subcontract cost=SUM(F3:F8)*70=$ 164500
Plan B:
Stockout occurs when Demand >Ending inventory of previous period.
Total cost of hiring=SUM(E3:E8)*35=28000
Total cost of layoff=SUM(F3:F8)*60=12000
Total inventory cost=SUM(G3:G8)*25=8750
Total cost of stockout=SUM(H3:H8)*100=60000
Total cost of this plan=SUM(E9:H9)=$ 108750