Question

In: Finance

A four-year financial project has estimates of net cash flows shown in the following table: Year...

  1. A four-year financial project has estimates of net cash flows shown in the following table:

Year

Net Cash Flow

1

$20,000

2

25,000

3

30,000

4

35,000

It will cost $65,000 to implement the project, all of which must be invested at the beginning of the project. After the fourth year, the project will have no residual value.

Using the most likely estimates of cash flows, conduct a discounted cash flow calculation assuming a 20 percent hurdle rate with no inflation.

What is the discounted profitability index of the project?

Solutions

Expert Solution

The given figures are:

Initial Cash Outflow= $65,000

Hurdle rate = 20%

Calculation of discounted cash inflow:

Year Net cash flow Discount factor Discounted cash flows ($)

(In $) (@ 20%) (Net cash flows* Discount factor)

1 20,000 0.833 16,660   

2 25,000 0.694 17,350

3 30,000   0.579 17,370

4 35,000 0.482 16,870

  Total discounted cash flows 68,250

Discounted profitability index= PV of future cash inflow/ Initial investment

Hence, the profitability index is $68,250/ $65,000= 1.05


Related Solutions

The cash flows and Net salvage value of Project X is given the following table: Year...
The cash flows and Net salvage value of Project X is given the following table: Year Cash flows Salvage Value 0 -5,800 4,800 1 2,100 3,000 2 3,400 2,200 3 3,600 1,800 4 1,800 0 Based on the Economic Life of this project and the cost of capital is 12%, in what year should you abandoning this Project X? A. Year 3, since NPV in year 3 = $8,429 B. Year 3, since NPV in year 3 = $2,629 C....
6. A project has the following total (or net) cash flows. __________________________________________ Year Total (or net)...
6. A project has the following total (or net) cash flows. __________________________________________ Year Total (or net) cash flow _________________________________________ 1- $20,000 2- 30,000 3- 50,000 4- 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate of return...
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. 6. A project has the following...
The net cash flows for project X, Y and Z are shown below. Each project has...
The net cash flows for project X, Y and Z are shown below. Each project has an initial cost of $100, and the company uses a 10% cost of capital (i.e., the discount rate = 10%) for each project. Which project is most sensitive to the change of the cost of capital? End of Year Net Cash Flow From Project X Y Z 1 $110 0 0 2 0 $121 0 3 0 0 $133.1 X Y Z All the...
8. The (net) cash flows of project C and D are shown below: Net Cash Flow...
8. The (net) cash flows of project C and D are shown below: Net Cash Flow ($) Year Project C Project D 0 -2,000 -1,000 1 3,000 650 2 125 1,500 a. Find the crossover rates. (1.5 point) b. The cost of capital is 12 percent. If C and D are mutually exclusive, which project should be accepted? Why? (0.5 point)
A project has the following total (or net) after-tax cash flows.                ____________________________________________________         Year&nbs
A project has the following total (or net) after-tax cash flows.                ____________________________________________________         Year             Total (or net) after-tax cash flow                ____________________________________________________                   1 $1,000,000 2 1,500,000 3 2,000,000 4 2,500,000                   _______________________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $4,000,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. c) Find...
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
If a project has a cost of $10,000, expected net cash flows of $1500 a year...
If a project has a cost of $10,000, expected net cash flows of $1500 a year for 12 years and you use a discount rate of 6%, what is the following: Payback period (no application of discount rate) Payback period (using discount rate) NPV IRR Should the project be accepted? If another project has a cost of $10,000 and has expected life of 8 years and it will generate $3000 a year should you accept the project if your boss...
A four-year financial project is forecast to have net cash inflows of $10,000; $25,000; $60,000; and...
A four-year financial project is forecast to have net cash inflows of $10,000; $25,000; $60,000; and $50,000 in the next four years. It will cost $125,000 to implement the project payable at the beginning of the project. The discount rate is 11%. What is the NPV of this project? What is the BCR of this project? Based on the NPV and BCR, would you do this project? What is the NPV of the project if the cost is due in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT